|
North-Eastern Electricity Supply
Company of Orissa Ltd., Januganj, Balasore (NESCO, for short), the holder of licence
for carrying on the business of Distribution & Retail Supply of electricity in
electrical circles of Balasore and Jajpur Road, submitted an application on 27.09.99 u/s 26 of the Orissa Electricity Reform Act, 1995
(Reform Act, 1995, for short) in respect of tariff for retail supply of electricity to
different categories of consumers.
|
2.0
|
NESCO and its two other
sister concerns, namely, WESCO and SOUTHCO, jointly filed an application for Retail Supply
Tariff (RST, for short) on 30.07.99. The Commissions staff, after preliminary
scrutiny of the application, raised a number of comments/queries thereon. The Commission
forwarded the comments/queries to NESCO vide letter No.2269 dt.13.08.99 and asked for
additional information from NESCO in order to enable the Commission to decide whether the
filing would be treated as complete for the purpose of proceeding u/s 26 of the Reform Act, 1995. |
2.1
|
NESCO submitted a fresh application with
clarifications to the comments/queries of the Commission in two volumes on 27th
September, 1999. In the light of the clarifications to the comments/queries and additional
information received from it, the filing appeared to be generally in order. Accordingly
the filing was treated as complete and by Order No.2 dt.04.10.99 (Vol. I), the application
in question was admitted and issue of public notice inviting objections to NESCOs
application was ordered.
|
2.1.1
|
Notice was published, as
approved by the Commission, in several local newspapers on two consecutive days in terms
of Clause 39 r/w sub-clause
(1) of Clause-126 of the Orissa Electricity Regulatory Commission (Conduct of Business)
Regulations, 1996 (Regulations, 1996, for short) outlining the broad features of the
Distribution & Retail Supply Licensees proposed tariff and the rates &
charges in a Schedule appended to the notice and inviting objections from interested
persons. The public notice required the interested persons to file their objections and
such documents as they seek to rely upon, supported by an affidavit, in six copies and to
indicate also if they would like to be heard in person by the Commission in terms of Clause 43 of the Regulations, 1996. The notice further
required the interested persons to serve a copy of the reply/objection alongwith the
documents relied upon on the petitioner/applicant and to file proof of such service before
the Commission at the time of filing of the reply/objection in terms of Clause 44 of the Regulations, 1996. |
2.1.2
|
The above public notice also
called upon the interested persons/objectors to inspect/peruse NESCOs application
and take note thereof during office hours within 15 days of the publication of the notice.
The public notice also permitted the interested persons to obtain the salient features of
the application on payment of Rs.20/- towards photocopying charges from Managing Director,
NESCO, Balasore and all Executive Engineers in charge of Distribution Divisions such as
Balasore Electrical Division, Balasore, Central Electrical Division, Balasore, Bhadrak
Electrical Division, Bhadrak, Baripada Electrical Division, Baripada, Rairangpur
Electrical Division, Rairangpur, Jajpur Road Electrical Division, Jajpur Road, Keonjhar
Electrical Division, Keonjhar, Anandapur Electrical Division, Anandapur. They were also
permitted to obtain a full set of the application together with supporting materials on
payment of Rs.100/- towards photocopying charges. |
2.1.3
|
The last date of filing of
objection complying with the terms & conditions of the public notice was initially
fixed as 31.10.99. The date fixed for filing of objection was extended to 15.11.99 because
of the super cyclone which hit Orissa on 29th and 30th October,
1999. A notice in print media such as "Samaya" (dt.05.11.99) and "New
Indian Express" (dt.3.11.99) was published extending the date of filing of objection
with regard to the Retail Supply Tariff (RST) applications of the Distribution and Retail
Supply Licensees for the information of the general public and interested persons. The
notice regarding extension of the date of filing of the objection was also displayed on
the office Notice Board. |
2.2
|
The Commission received 19
objections against NESCOs application out of which five were rejected for
non-compliance of the terms & conditions as laid down in the public notice while 14
objections were admitted according permission to the objectors for participating in the
hearing. The objectors whose objections were admitted for hearing are (1) Chief Electrical
Engineer, S.E. Railway, Garden Reach, Calcutta. (2) M/s Jayshree Chemicals Ltd., P.O.
Jayshree, Dist., Ganjam. (3) M/s Ispat Alloys Ltd., At/P.O. Balgopalpur, Dist. Balasore.
(4) M/s Emami Paper Mills, At. Balgopalpur, P.O. Rasulpur, Dist. Balasore (5) Orissa
Assembly of Small & Medium Enterprises, Balasore Chapter, Balasore. (6) Shri Maheswar
Bag, Ex-Minister, President, Nagarika Adhikar Surakshya Committee O Durniti
Nibarana Sangha, Balasore. (7) Shri Rajkishore Mohanty, Grahak Swarth Surakshya Parisada,
Balasore. (8) President, East Coast Rice Millers Association, A/P.O. Charampa, Dist.
Bhadrak (9) M/s FACOR, D.P. Nagar, Randia, Dist. Bhadrak. (10) Secretary, Bhadrak Bar
Association, Bhadrak. (11) Shri K.N. Jena, General Secretary, Orissa Consumers
Association, Biswanath lane, Cuttack. (12) M/s Utkal Chamber of Commerce & Industry
Ltd., Barabati Stadium, Cuttack. (13) M/s Tata Iron & Steel Co. Ltd., 273,
Bhoumanagar, Unit-IV, Bhubaneswar. (14) Shri R.C. Padhi, Retd. Chief Engineer, MIG A/24,
Brit Colony, Nayapalli, Bhubaneswar. |
2.3
|
After receipt of the
objections and scrutiny thereof, the Commission published a notice in two Oriya dailies
and one English daily on 17th & 18th November99 whereunder
the list of valid objections with regard to NESCOs application and the date of
hearing (03.12.99) were notified for the information of the general public. |
2.3.1
|
In terms of Clause-45 of the Regulations, 1996, the Commission permitted
the applicant to file a rejoinder to all the objections/reply filed by the objectors. |
2.4
|
As notified, the hearing of the RST application
commenced on 03.12.99. None of the parties present made any prayer to adduce oral or
documentary evidence in course of the proceedings except those that were filed supported
by affidavit, in response to the public notice.
|
2.5
|
Apart from the substantive objections, legal
objections were raised by two objectors as preliminary objections on the maintainability
of the tariff proceeding. The Commission heard the views of NESCO on such objections. It
was decided with the consent of the respective objectors that they would be dealt with by
the Commission in the final order.
|
2.5.1
|
The preliminary
objections raised by the General Secretary, Orissa Consumers Association,
Cuttack and President, Nagarika Adhikar Surakshya O Durniti Nibarana Sangha,
Balasore are as follows :-
|
2.5.1.1
|
The RST determined by the Commission by its
Order dt.21.11.98 in Case No.19/98 which has come into force
from 01.12.98 cannot be revised or amended within a period of 3 years as envisaged u/s
57-A (1)(e) of the Electricity (Supply) Act, 1948 (the Act, 1948, for short) and therefore
the present application for RST is not maintainable and liable to be rejected outright. (O.C.A.) |
2.5.1.2
|
The RST determined by the
Commission (in Case No.19/98) cannot be amended within one
financial year unless warranted for adjustment of Fuel Surcharge.
(O.C.A.) |
2.5.1.3
|
OERC has not framed any
regulation by notification in official gazette for determination of tariff u/s 29 of the
Electricity Regulatory Commission Act, 1998 (the Commission Act, 1998, for short) and sub-section (2) of Section 26 of the Reform Act, 1995
and as such it lacks authority and power to consider the application of the licensee, be
it for determining a new tariff or revising or amending the existing one.
(O.C.A.) |
2.5.1.4
|
OERC has not yet specified
the methodology and procedure for calculating expected revenue from the charges and
therefore, it cannot consider the application of the licensee which is based on imaginary,
vague, and manipulated statement of facts and accounts in the absence of statutory audit
reports for the years 1997-98 and 1998-99.
(O.C.A.) |
2.5.1.5
|
Licensee has failed to comply
with the conditions of the Licence to improve its efficiency, standard of service and
reduce its losses and as such, it should not be allowed to make good the losses
attributable to mal-administration, inefficiency, corruption, mismanagement, and
unwarranted expenses by way of penalising the consumers in the form of a tariff hike.
(O.C.A.) |
2.5.1.6
|
Since the application for RST
has not been filed prior to the commencement of the FY 1999-00 and has been filed in the
middle of the aforesaid FY, it cannot be entertained for setting a tariff for the balance
or remaining part of the FY.
(O.C.A.) |
2.5.1.7
|
As the OERC has not consulted
Commission Advisory Committee (CAC, for short) prior to the admission of the tariff
application and issue of public notice, it would not be legal and proper to proceed with
the case.
(O.C.A.) |
2.5.1.8
|
As the Commission, at
present, is only a two member Commission instead of three and the member of the Commission
who shall be an electrical engineer having experience of generation, transmission &
distribution or supply of electricity in terms of Section- 5
(1)(a) of the Reform Act, 1995 having not been appointed as yet, the Commission now
comprising of two members lacks quorum to undertake and dispose of the tariff proceeding
because of the bar created u/s 9(4) of the Reform Act,
1995.
(O.C.A.) |
2.5.1.9
|
Since the notice issued by
the Commission in the daily newspapers inviting objections was in English, the same was
not intelligible to the consumers. As the notice was not in Oriya language and also not
intelligible, the dateline fixed for filing of objection was improper and illegal.
(Nagarika Adhikar Surakshya O Durniti Nibarana Sangha) |
2.6
|
The first objection raised by
Shri K.N. Jena, General Secretary of the Orissa Consumers Association, Cuttack is
that when the provisions of Sec.57-A of the Act, 1948 r/w the provisions of the Reform Act, 1995 contemplate that charges for the supply of
electricity, once fixed, shall be in operation for three years, revision of tariff within
one year would be without the authority of law. |
2.6.1
|
The objection is purportedly
based on Section 57-A of the Act, 1948. We have considered the provision of Section 57-A
of the Act, 1948 and particularly sub-clauses (c) and (e) of sub-section (1) of Section
57-A quoted by Shri Jena. We find that these provisions are applicable to charges for
electricity recommended by a Rating Committee and approved by the State Govt. and
stipulate that such charges recommended by a Rating Committee for supply of electricity
shall be in operation for such period not exceeding three years as the State Govt. may
specify in the order. Sub-section (7) of Section 26
of the Reform Act, 1995 repeals the constitution of a Rating Committee making the
provisions of the Act, 1948 quoted Shri Jena inapplicable in this case. We hold that the
preliminary objection by the learned counsel citing the provisions of Section 57-A of the
Act, 1948 is without merit as the said provision is inapplicable in tariff proceeding
under Section 26 of the Reform Act, 1995. |
2.7
|
With regard to the second
objection that the RST determined in Commissions Order dated 21.11.98 (in Case No.19/98) cannot be amended within one financial year unless
warranted for adjustment of fuel surcharge, we would like to say that apparently there is
some misunderstanding about Section 26 of the Reform
Act, 1995 which is relevant to the determination of tariff by the Commission. We would
like to clarify that in this section of the Reform Act, 1995, the
procedure for determination of a fresh tariff or amendment of tariff is the same. There is
no vacuum or even interregnum in operation of a tariff which has been defined as a
schedule of standard prices or charges. This has been amply made clear in Clause 116 of Regulation, 1996. Depending on the gap
between estimated revenue requirement and the aggregate revenue which a licensee is
permitted to recover by the tariff in operation, the Commission may approve modification
to the tariff or any part of tariff. Whether the resultant determination is called a
tariff or an amendment of tariff is not of any consequence. The Commission cannot refuse
to entertain an application if the Commission finds that the licensees filing of
revenue requirement and expected revenue from charges is reasonably complete. It has to
process it and take a decision within ninety days of the complete filing. Sub-sec. (6) of Section 26 of the Reform Act, 1995
lays down that except in terms of fuel surcharge formula, no tariff or part of tariff can
be amended more than once in any financial year. The natural corollary is that tariff or
part of any tariff can be legitimately amended once in a financial year. The current RST
was set in November98 within the financial year 1998-99. Therefore an amendment to
RST during financial year 1999-00, if found justified, cannot be termed as illegal. |
2.8
|
The third objection relates to lack of authority
and power of the Commission to consider the present application of the Licensee, be it for
fixing a new tariff or revising or amending an existing one on the ground that the
Commission has not framed any regulation for fixation of tariff u/s 29 of the Commission
Act, 1998 and under sub-sec. (2) of Sec. 26 of the
Reform Act, 1995, by notification in the official gazette.
|
2.8.1
|
In fact, this objection has two parts. The first
part of the objection is that OERC has not framed any regulation for determination of
tariff u/s 29 of the Commission Act, 1998 and as such, it lacks authority and power to
consider the application of the licensee. In view of the above objection, the point for
consideration is if Sec. 29 of the Commission Act, 1998 is applicable to determination of
tariff in the State of Orissa.
|
2.8.2
|
We understand that Shri K.N.
Jena, General Secretary of the Orissa Consumers Association has, in OJC No.6999/99,
challenged the procedure adopted by the State Govt. for appointment of a member of the
Commission which has fallen vacant on the ground that the State Govt. has not followed
procedure provided under the Commission Act, 1998 for such purpose. The aforesaid writ
application is yet to be disposed of laying down the law on the issues involved. |
2.8.3
|
Meanwhile, we are of the opinion that the Reform Act, 1995 holds good in all matters provided therein for OERC
including determination of tariff by the Commission in view of the special provision
relating to the Reform Act, 1995 and Haryana Electricity Reform Act,
1997 contemplated u/s 41 of the Commission Act, 1998. Sec. 41 of the Commission Act, 1998
clearly provides that the provisions of the said Act, in so far they relate to the State
Commissions, shall not apply to the Commissions established under the Reform
Act, 1995 or the Haryana State Electricity Reform Act, 1997.
|
2.8.4
|
The subject "electricity" is in the
Concurrent List of the Constitution of India. Therefore, the State of Orissa has a right
to enact law on electricity as it did in the Reform Act, 1995. The Reform Act, 1995 has
been assented to by the President of India on the 3rd January, 1996. Further,
Sec.41 of the Commission Act, 1998 is in the nature of a built-in provision to safeguard
the State Acts enacted earlier from the overriding effect of a Central Act enacted later
than the State Acts on the same subject of "Electricity" and in the same field
of establishing Electricity Regulatory Commission. To sum up, we hold that the Commission
Act, 1998 in so far as it relates to State Commissions is not applicable to OERC.
|
2.8.5
|
The second part of the objection is that the
OERC has not framed any Regulation by notification in the official gazette for
determination of tariff under sub-section (2) of
Sec.26 of the Reform Act, 1995 and therefore it has no authority or power to consider
the application of the Licensee whether it is for a new tariff or revision or amendment of
the existing one. Before we deal with the factual aspect of this objection, we may point
out that while it is stated in the first part of the objection that tariff should be
determined by OERC in accordance with the provisions of Sec. 29 of the Commission Act,
1998, it is also contended in the second part of the objection that OERC has not framed
regulations for fixation of tariff u/s 26(2) of the
Reform Act, 1995 and, therefore, OERC has no authority or power to consider the said
application of the Licensee. It appears to us that Shri Jena is challenging the Reform
Act, 1995 in so far as it relates to the OERC and at the same time he is relying on the
same Reform Act, 1995 to challenge the alleged omission on the part of OERC.
|
2.8.6
|
The plea taken by Shri Jena
that OERC has not framed any regulation to determine tariff u/s 26(2) of the Reform Act, 1995 has no basis in
fact. Chapter-V of the Regulations, 1996 deals with regulations on tariff as envisaged in
Chapter-VIII of the Reform Act, 1995. The provisions contained in Chapter-V of the
Regulations, 1996 has conferred upon the Commission a measure of discretion in the matter
of evolving its working procedure so long as these procedures conform to the principles of
natural justice. Accordingly, we are of the opinion that there is no merit in this
objection. |
2.9
|
With regard to the fourth
objection, it may be pointed out that upon filing of the application for RST by NESCO on
July 30, 1999, the Commission in its letter No.2269 dt.13.08.99 pointed out certain
omissions to be supplied by the applicant and raised certain queries for clarification.
The applicant filed a fresh application and supplied the omissions and clarifications to
the queries on 27.09.99 raised by the Commission in its letter dt.13.08.99. After scrutiny
of all the filings including a large number of documentary evidence, the Commission
treated the filings to be generally in order and the tariff application in question was
treated as complete. |
2.9.1
|
It may be stated here that
regulatory proceeding cannot be treated at par with proceedings before common law courts.
The Commission is empowered under Clause-111 (Chapter-V) of the
Regulations, 1996 to lay down methodologies and procedures for calculating the
expected revenue from charges and for determining the tariffs from time to time with the
further enabling provisions to add, amend, alter, revise, substitute or otherwise change
such methodologies and procedures at any time the Commission desires. Clause 113 of the said Regulation further provides that the
Commission may issue orders from time to time giving details of the manner in which
licensees revenue and tariff will be determined consistent with the provisions of
the Act and Regulations framed for the purpose. Even, where no Regulation has been framed
to deal with any matter or exercise any power under this Act, the Commission is free to
deal with such matters, powers and functions in the manner it thinks fit. |
2.9.2
|
We would also like to
emphasise that in accordance with Section 10(5) of
the Reform Act, 1995, this Commission, in discharge of its function, shall be entitled
to and may consult to the extent it considers appropriate from time to time such persons
or group of persons who may be affected or likely to be affected by the decisions of the
Commission. This provision read with Sec. 26 of the
Reform Act, 1995 makes it clear that the Commission has wide discretion to evolve its
own methodology, procedures and mechanism, subject, however, to the fact that they are
just and reasonable and to carry on its activities in cases where there is no provision in
the Reform Act, 1995 or Regulations
framed thereunder. |
2.9.3
|
We have examined the
objection that the filing should not have been admitted in the absence of audited accounts
for 1998-99. It may be mentioned that the licensee has filed audited accounts for the year
1997-98 alongwith the application. The audited accounts for the year 1998-99 have not been
filed. In the normal course, the revenue requirement for 1999-2000 alongwith request for
amendment of tariff if any should have been filed in December, 1998. If the application
would have been filed by the prescribed date, the licensee was in a position to file only
the audited account for 1997-98. It appears that in view of the unsettling effects of
transition involving formation of new distribution companies, disinvestment of government
shares and issue of fresh license etc. the revenue requirements were not filed in
December, 1998 which ought to have been the case. This was filed in August99 when
audited accounts for 1998-99 were not yet due . |
2.10
|
Therefore, we are unable to agree that the
tariff application of the Distribution & Retail Supply Licensee is defective,
incomplete and not maintainable.
|
2.11
|
The fifth preliminary objection relates to
debarring the licensee from revising the tariff until and unless it fulfilled the
conditions of Distribution & Retail Supply Licence as amended from time to time and
complied with the order of the Commission.
|
2.11.1
|
Non compliance or inadequate
compliance of the licence conditions, if any, is a separate issue which cannot hold up the
process of determination of tariff. The Commission is bound by law as in Section 26 (6) of the Reform Act, 1995 to determine the
tariff within 90 days from the date the application was treated by the Commission as
complete. Elaborate provisions exist in the Reform Act, 1995 to deal
with non-compliance or violations of licence conditions. Filing of the revenue requirement
and expected revenue from charges is a statutory duty of the licensee as provided in s/s (4) of Sec.26 of the Reform Act, 1995 and
therefore this function must not be mixed up with other issues like non-compliance or
inadequate compliance of the licence conditions. The Commission is, therefore, of the
opinion that this objection has no merit and is accordingly overruled. |
2.12
|
The sixth objection that the
application cannot be entertained in the middle of the financial year 1999-00 has no basis
in law. The Commission would have liked strict adherence to the due date of filing of the
revenue requirement i.e. by 31st December, 1998 but the Commission is persuaded
to accept the delay caused due to the transitional problems. The Commission has also noted
that there is no statutory time schedule for application for tariff and hence the
Commission cannot refuse to consider the application if it is otherwise in order. |
2.13
|
The seventh objection is that the Commission
Advisory Committee was not consulted by the Commission before admitting the application. Sub-section (6) of Sec.26 prescribes; "If the
Commission considers that the proposed tariff or amended tariff of a licensee does not
satisfy any of the provisions of sub-section (5), it shall, within 90 days of the date of
receipt of all information which it required, and after consultation with the Commission
Advisory Committee constituted u/s 32 and the licensee, notify the licensee the proposed
tariff or amended tariff." It is clear from the language employed in sub-sec. (6)
that the question of consultation arises only before the Commission actually seeks to
notify the licensee the proposed tariff or amended tariff. Consultation with the
Commission Advisory Committee, therefore, is not a pre-requisite for admission of the
licensees application. It may be further mentioned that the Commission had already
scheduled the meeting of the CAC by the time the public hearing was taken up.
|
2.14
|
In order to dispose of the penultimate
objection, we may point out that Sec.9(4) of the
Reform Act, 1995 stipulates a quorum for review of any previous decision taken by the
Commission. This stipulation for quorum is applicable only if there is an explicit prayer
for review of any previous decision of the Commission. We have already stated earlier that
the present application is not a prayer for review of the RST. It is an application u/s 26(6) of the Act. We therefore hold that there
is no bar to or infirmity in the Commission proceeding to determine the RST as prayed for
by the applicant.
|
2.15
|
Reference can be made to Clause 39 of the Regulations, 1996 with a view to dispose of
the last objection raised by the President of Nagarika Adhikar Surakshya O
Durniti Nibarana Sangha, Balasore. It provides, inter alia, that where any petition is
required to be advertised, it shall be advertised in one issue each of a daily newspaper
in the English language and two daily newspapers in Oriya language having circulation in
the area. Compliance to Clause 39 of the Regulations, 1996
has been indicated in para 2.1.2. It will appear from what has been stated in para 2.1.2
that the Commission having asked the Licensee to bring out the salient features of the
application on two consecutive days, in one issue each of a daily newspaper in English
language and two daily newspapers in Oriya language having circulation in the licensed
area has, in fact, ensured a wider circulation of such notice for the purpose of consumers
without committing any breach of the requirements stipulated in Clause 39 of the Regulations 1996. Clause 39 of the Regulations, 1996 does not require the
Commission to resort to transliteration of the petition and/or application (as in this
case) into Oriya language and to advertise the same in one issue each of a daily newspaper
in English language and two daily newspapers in Oriya language. All that is necessary to
be done in order to fully comply with Clause 39 is that the petition and/or application
(as in this case) is to be advertised, inter alia, in one English daily and two Oriya
daily newspapers having circulation in the area specified by the Commission. We are,
therefore, of the opinion that not only Clause 39 has been fully complied but also the
application has been put to wider circulation as indicated above. |
2.16
|
In the light of our observations in the above
paragraphs, we have to hold that there is no validity in any of the preliminary
objections, most of which were due to inadequate appreciation of regulatory procedure. We,
therefore, proceed to examine NESCOs proposal and give our findings on the same.
|
3.0
|
NESCOS
PROPOSAL
|
3.1
|
NESCO has submitted calculation of its expected
revenue from charges & its revenue requirement for the year 1999-00 along with a
proposal for amendment of the existing tariff.
|
3.2
|
Considerations requiring amendment of the
existing tariff which have been advanced by NESCO are given below :-
|
3.2.1
|
Revenue from the existing tariff is insufficient
to meet the estimated cost for the financial year 1999-00 and, therefore, there is a need
to increase tariff in line with the revenue requirement proposal to preserve the financial
viability of NESCO.
|
3.2.2
|
Insufficient tariff increase
of the previous tariff order has resulted in a higher requirement for the financial year
1999-00 and the energy consumption assumed in the retail tariff application of 1998-99 and
approved by OERC was in excess of the actuals. |
3.2.3
|
The tariff structure
inherited by the company is a distorted one with an in-built high dose of subsidy to
certain groups of consumers which continues inspite of the rationalisation of tariff
structure by OERC and GRIDCO. A higher tariff increase in the case of subsidised
categories is, therefore, required to achieve a rational tariff level. |
3.2.4
|
Revenues must be sufficient to cover all the
costs to ensure viability of NESCO and to enable it to raise funds critical for system
improvement.
|
3.2.5
|
OSEB and its successor GRIDCO being state-owned
undertakings had the benefit of getting subsidy from the State Govt which is not available
to NESCO and hence all costs have to be recovered from the consumers.
|
3.3
|
NESCO has considered the following main inputs
for the calculation of revenue requirement :- Power Purchase Expenses
Employees Cost
Administration & General Expenses
Repair & Maintenance Expenses
Provision for bad and doubtful debts
Depreciation
Interest on loan
Interest on working capital
Statutory appropriation
Cost of stores & spares
Reasonable Return on Capital Base |
3.4
|
NESCO estimates power purchase of 2060 million
units with an average of monthly maximum demand of 360 MVA during 1999-00. Demand has been
estimated on the basis of power purchase bills of April, May and June, 1999. NESCO
estimates an energy sale of 1235.86 million units which is an increase of 8% over the
billed units for the year 1998-99.
|
3.4.1
|
NESCO has stated that the
Distribution loss as worked out from the management information system is 43% for the year
1998-99 & feels that a loss reduction of 2% to 3% in the year 1999-00 would be
realistically achievable. It has targeted to reduce the energy loss to 40% during 1999-00.
|
3.4.2
|
Total expenditure including the power purchase
cost for the year 1999-00 is estimated at Rs.409.62 crores which comprises Employees
Cost, Cost of Materials, Administration & General Expenses, interest on loans borrowed
from different organisations, bad debts, depreciation less capitalisation on account of
interest expenses. There is a proposal for special appropriation of Rs.0.99 crores to
cover contribution to contingency reserve. NESCO estimates to earn reasonable return of
Rs.11.72 crores on its capital base of Rs.68.94 crores. The revenue requirement and
estimated reasonable return for the financial year 1999-00 proposed by NESCO is at Table :
1. Table : 1
Revenue requirement of NESCO for 1999-00
(Rs. in crores)
Purchase of energy |
279.26 |
Distribution and sale of energy |
130.36 |
Special appropriation |
0.99 |
Sub-total |
410.61 |
Reasonable return |
11.72 |
Total |
422.33 |
|
3.4.3
|
The financial projection made
by NESCO for 1999-00 is given in Table : 2.
Table : 2
Estimated Revenue from Charges for 1999-00
(Rs.in crores)
|
Revenue |
Surplus/Deficit |
For FY 00 based on existing tariff |
299.45 |
(-) 122.88 |
For FY 00 based on proposed tariff for
full year |
378.15 |
(-) 44.18 |
For FY 00 based on proposed tariff for 4
months |
325.68 |
(-) 96.65 |
|
3.4.4
|
NESCO has stated that the existing tariff is
inadequate to meet the estimated total revenue requirement of Rs.422.33 crores for the
financial year 1999-00.
|
3.4.5
|
NESCO has stated that if the shortfall in the
revenue requirement is to be met, it requires revision of tariff by 46.8%. However, NESCO
has proposed an average rise of 31.4%.
|
3.5
|
NESCO has stated that while a
differential tariff based on cost differences for different zones would be more efficient,
a sudden shift across the regions would create significant discontinuity in tariffs. NESCO
has accordingly suggested a uniform tariff for all the three utilities under the
management of BSES, namely, WESCO, NESCO and SOUTHCO. It has been explained that excess of
revenue earned by WESCO may be transferred to SOUTHCO and NESCO. The revenue transferred
from WESCO to SOUTHCO and NESCO may be treated as a special category capital or
alternately OERC may consider treating the surplus transferred from WESCO as a revenue
subsidy to SOUTHCO and NESCO. |
3.6
|
The tariff proposal does not
envisage any subsidy from the Govt of Orissa or any other source. It has adopted the
principle of cross subsidization and a self balancing mechanism within various classes of
consumers. |
3.7
|
NESCO has stated that in case OERC or Govt. of
Orissa desire to further subsidise any consumer category, the difference between the
proposed revenue and the subsidised tariff should be provided to NESCO either by
consequent increase in tariff for other consumers or in the form of subsidy from Govt. of
Orissa d by a monthly letter of credit or a combination of both.
|
3.8
|
In proposing the tariff, NESCO is stated to have
acted on the following principles:- Lower tariff for consumers supplied
at higher voltage level
Reduction in cross subsidy
Reduction in multiple rates for consumers at same voltage level |
3.9
|
As per the tariff proposal
suggested by NESCO no consumer is to pay less than 50% of the cost of supply requiring
significant increase in LT supply for domestic and irrigation a L.T. At the same time,
NESCO proposes that no consumer should pay more than 150% of the cost of supply. |
3.10
|
As a measure of incentive for HT and EHT
consumers, it has been proposed that on consumption beyond the load factor of 60%, a
discount of 10% may be given on the energy charge for the applicable category.
|
3.11
|
As a number of aluminum manufacturing industries
plan to set up CPP, NESCO proposes that consumers with a contract load of 100 MVA and
above and a guaranteed monthly load factor of 80% would qualify for a special tariff with
no demand charge but a consolidated energy charge and back to back arrangement with the
bulk supplier.
|
3.12
|
NESCO intends phasing out of cross subsidies
while proposing amendment to this tariff.
|
3.13
|
NESCO states that the principle of marginal
costing is more efficient but due to shortage of accurate data, historical cost method has
been used to assign cost to revenue.
|
3.14
|
NESCO has stated that about 33% of its power
purchase bill relates to fixed cost while less than 20% of its revenue have been earned
from the demand charge. NESCO proposes to increase the demand charge so that a higher
level of fixed cost would be recovered through the demand charge.
|
3.15
|
On the aforesaid grounds, NESCO has sought for
approval of :-
-
The proposed amendment to the existing retail tariff and charges.
-
Revenue requirement for the year 1999-00.
-
The expected revenue from the charges for the year 1999-00.
-
The mechanism proposed for cash flow to NESCO and SOUTHCO from WESCO.
-
Moratorium of three years in setting captive power plants.
|
4.0
|
OBJECTIONS DURING HEARING
Fourteen objectors were admitted for personal hearing. |
4.1
|
Chief Electrical Engineer, S.E. Railway,
Calcutta
|
4.1.1
|
Shri Madhukar Mishra, Chief Electrical Engineer
(Distribution) appeared on behalf of C.E.E., S.E. Railway. He stated that the proposed
hikes in the Demand and Energy charges in the range of 25% to 30% for HT and EHT supply is
abnormally high and may cause severe financial burden on the Railways. Hence the Demand
and Energy charges may be maintained at the existing level.
|
4.1.2
|
Shri Mishra pleaded that railways load
fluctuation is due to exogenous factors like accidents and public agitation etc. and hence
the proposed penalty on overdrawal may be withdrawn. Alternatively, the prevailing
facility of no penalty upto 120% of contract demand during off-peak period may be extended
to peak period. He also submitted that Monthly Minimum Fixed Charge (MMFC) may be deleted.
The fixed charges are already in-built in the two-part tariff for Railways and, therefore,
the proposal of a MMFC may be dropped.
|
4.1.3
|
It was argued that traction
tariff should have some relationship with cost of power purchased from NTPC/NHPC. NTPC
sells power at Rs.1.92/Kwh whereas Railways pay Rs.3.79/Kwh to the DISTCOs. Such
distortions should be rectified. Shri Mishra requested that a rebate of 2% of the total
bill may be allowed to the Railways for timely payment of bills and that along the line of
a penalty on low power factor, a rebate may be granted in the event of power factor over
90%. |
4.1.4
|
Power supply interruption and unreliable supply
cause lots of hardship to the Railways in the form of additional operational expenditure
for train services and hence compensation should be paid to Railways in case of power
supply interruptions or poor quality of power supply by the licensee.
|
4.1.5
|
It was further submitted that traction tariff
should be reasonable for developmental projects and that TOD meters should be provided at
the traction substations. He further pleaded that in case of defective meters, average of
last three months consumption should be taken for billing.
|
4.2
|
M/s. Jayshree Chemicals
Ltd., Ganjam |
4.2.1
|
Shri B.K. Mohanty, Senior
Advocate submitted the objections on behalf of M/s. Jayshree Chemicals Ltd. He argued at
length that the Special Agreement proposed by NESCO to EOUs to provide tariff at a special
rate is contrary to the principles laid down in Section 26(5) of the Reform Act, 1995. He
explained that even though Section 26(5) of the Reform Act, 1995 states that tariff of the
licensee shall not show undue preference to any consumer, it is clearly stated that tariff
may be differentiated depending on consumer's load factor or total consumption or the
timing of supply of power. Thus the proposed special tariff may be made applicable to all
those (including the objector) who conform to the said condition of consumption. |
4.2.2
|
Shri Mohanty submitted that the special category
of bulk consumers of electricity are categorised as "Power Intensive Industries"
under the regulation and not as EOUs and the special tariff should therefore be made
applicable to Power Intensive Industries in general and not for EOUs alone. He further
suggested that period from 1800 hours to 2200 hours may be considered as peak hours and
the rest of the day as off peak hours.
|
4.3
|
M/s. Ispat Alloys Ltd.,
At/Po : Balgopalpur, Dist : Balasore |
4.3.1
|
Shri S.K. Sharma, President
of M/s. Ispat Alloys objected to the proposal. He stated that EOUs should not be charged
any Demand Charge as there is already a clause of 40% Load Factor during Peak hours to
avail the concessional rate of Energy Charges in Off-Peak hours. |
4.3.2
|
Shri Sharma submitted that the tariff for EOUs
suggested for only off-peak hours should be made available for all the 24 hours and that
there should be no increase in the colony consumption tariff which should not be more than
the power rate for the industry. He further argued that as there is a penalty for low
power factor, there should be an incentive for maintaining better power factor than 90%.
|
4.3.3
|
Shri Sharma further submitted that the over
drawal may be allowed on 24 hours basis subject to technical clearance and there should be
no customer service charge.
|
4.3.4
|
Among other requests were for payment of a
rebate of 20 paise/Kwh for timely payment and for special consideration of low tariff for
Ferro Alloys to make it competitive in international market. It was claimed that like
Andhra Pradesh and West Bengal power may be supplied at cheaper rate to Ferro Alloys
industries.
|
4.3.5
|
Shri Sharma argued that just as there was no
justification for industry to be burdened because of cross subsidy it should not also be
burdened with higher tariff due to growing loss levels and inefficiency of the supplier.
|
4.4
|
M/s. Emami Paper Mills Ltd.
|
4.4.1
|
Shri M.B.S. Rao appearing for M/s Emami Paper
Mills Ltd. stated that if the proposed hike is made effective their monthly cost of
production would go up by around Rs.20 lakhs. This additional burden of Rs.2.4 crores
annually will make the industry unviable thereby rendering the 1100 persons presently in
employment, jobless. He explained that production cost may go up by 6% if the proposed
tariff is implemented and this burden can be crippling for the paper industry which is
going through a recession.
|
4.5
|
Orissa Assembly of Small
& Medium Enterprises, Balasore Chapter, Balasore |
4.51
|
Shri Devashish Mohanti, District President
represented Balasore Chapter of Orissa Assembly of Small and Medium Industries. He
objected to increase in tariff on grounds of poor service standards of supply and adverse
impact on the viability of small and Medium Industries. He complained that no steps have
been taken by NESCO to completely isolate industrial feeders from rural or urban feeders,
prior information is not given about power cuts and that newly installed meters are
recording high Kwh during low voltage.
|
4.6
|
Shri Maheswar Bag,
President, Nagarik Adhikar Surakshya Committee, Balasore |
4.6.1
|
Shri Ananta Kumar Das, General Secretary of
Nagarik Adhikar Surakshya Committee objected on many counts. He had a litany of complaints
against the licensee company which is allegedly operating only on profit motive and taking
no steps either to reduce loss or improve supply service.
|
4.6.2
|
He stated that increase in tariff was
necessitated due to avoidable reasons such as increase in establishment expenditure,
unrealised dues, bad debts, exit of industrial consumer from grid, uneconomic purchases
and inefficiency of staff. He objected to installation of high sensitive meters and
claimed that since OERC notification was in English, not comprehensible to common man, the
notice was illegal.
|
4.7
|
Shri Rajkishore Mohanty, Grahak Swarth
Surakshya Parisad, Balasore
|
4.7.1
|
Shri Rajkishore Mohanty
representing Grahak Swarth Surakshya Parisad took exception to the fact that the public
notice of 6.10.99 in 'Sambad' was in 'English' and has not been understood by most
consumers of Balasore. He objected to the proposed tariff which, he alleged, compared
unfavourably with those in the neighboring states and was in excess of the rate of
inflation of 1999. |
4.7.2
|
He stated that the licensees
and the consumers are like sellers and buyers and hence both parties should discuss and
that tariff should be determined after fresh notification in local language for the
understanding of all. He also stated that the proposed revision of tariff within one year
of last tariff revision is arbitrary and should be rejected. He wanted the Commission to
note that West Bengal purchases power from Orissa and sells it to its domestic consumers
at lower rate. |
4.8
|
President, East Coast Rice Millers
Association
|
4.8.1
|
Shri Jatikanta Nayak, authorised representative
of East Coast Rice Millers Association objected to repeated increases in tariff and
to the fact that NESCO has given proposal to enhance tariff within a few months of taking
over charge. The reason for enhancement as given by NESCO that existing tariff is
insufficient to meet the estimated cost for the ensuing year is not a satisfactory reason.
|
4.9
|
M/s. FACOR, D.P. Nagar,
Randia, Bhadrak |
4.9.1
|
Shri V.S.S. Rao, General
Manager represented M/s. Facor. He submitted that EOU industries should be supplied power
at competitive tariff not only for off-peak hours but also for peak hours so that those
industries will form as base load for the distribution companies assuring certain
guaranteed revenues. He reiterated the reasons of objection given by M/s. Ispat Alloys and
strongly pleaded for special consideration for international competitiveness of EOU
industries whose power consumption constitutes 50% of the total cost. He claimed that
other states provide cheaper power to EOUs and power intensive industries and hence this
practice should be followed in Orissa. |
4.10
|
Bhadrak Bar Association
|
4.10.1
|
Shri Nirakar Jena, Secretary of Bhadrak Bar
Association stated that the reasons submitted by NESCO for tariff hike are not sufficient
and hence the application of the licensee should be rejected. He submitted that the
Commission's notification should be in Oriya. He objected to installation of sensitive
meters by the licensee allegedly to record high Kwh.
|
4.11
|
Shri K. N. Jena, Orissa
Consumers Association, Cuttack |
4.11.1
|
Shri K. Acharya represented
Orissa Consumers Association. He objected on a variety of grounds as below :-
(a) The tariff amendment application for the year 1999-00 is not
maintainable.
(b) The Commission has not framed any regulation by notification in Gazette determining
terms and conditions for the fixation of tariff.
(c) The DISTCOs have not completed their functioning for even a year and as such their
accounts are not audited. Thus their standards of performance and financial position etc.
are not known.
(d) The licensees have not improved their efficiency and standards of service and they
have not made any effort to reduce T&D losses.
(e) The Commission has not consulted the CAC prior to admission of tariff application.
(f) The licensee purchases high cost power instead of cheap power.
|
4.11.2
|
In addition to aforesaid objections he
complained of irregularity in billing, metering and in consumer service and suggested that
loss reduction and installation of new meters etc. should form part of the licence
conditions. He opined that increasing the load factor is no alternative for metering as
the former encourages the consumer to increase losses by resorting to unfair means.
|
4.12
|
Utkal Chamber of Commerce
& Industry (UCCI) |
4.12.1
|
Shri M.V. Rao representing Utkal Chamber of
Commerce and Industries strongly objected to tariff increase on various grounds. He
submitted that retail tariff application of DISTCOs may be taken up after finalizing BST.
|
4.12.2
|
He argued that there is scope
to reduce the BST and hence the retail applications of DISTCOS should be rejected and that
yearly tariff revision harms industrial planning. He submitted that since the Super
Cyclone devastated most part of coastal Orissa, the Commission should not change the BST
and RST during 1999-00. |
4.12.3
|
GRIDCO's sale of energy is projected less
because 70% of total meters were not in working condition and because of inaccurate
computation method. This is allegedly done deliberately to hide GRIDCO's inefficiency. He
wanted tariff to be fixed keeping in view rates charged to industrial consumers in other
states.
|
4.12.4
|
NESCO should not have applied for tariff
revision without having the audited accounts of 1998-99. The MIS data supplied by the
company is erroneous.
|
4.12.5
|
It is unfair that NESCO prays for not granting
permission to CPPs which means the private licensees want to be monopolists.
|
4.12.6
|
NESCO should need total power drawal of only
2060 MU with a simultaneous maximum demand of 360 MVA. At the existing BST, expected
revenue should be Rs.1343.29 crores as against a revenue requirement of Rs.1193.85 crores.
Hence Bulk Supply Tariff should reduce rather than increase. Consequently, NESCO should
reduce the tariff.
|
4.12.7
|
The overall T&D loss was approved at 35%
which included 4% of EHT loss with effect from 01.04.97. By now OERC should reduce the
benchmark of distribution loss from 31% to 28% for 1999-00.
|
4.12.8
|
Shri M.V. Rao objected to increased claims under
employee expenses, bad debts, auditor fees etc. He suggested that depreciation, PF
contribution, gratuity may be taken as proposed by NESCO. According to him the revenue
requirement of NESCO works out to Rs.357.53 crores as against the proposed figure of
Rs.422.32 crores. Since the total expected revenue with existing tariff may be Rs.354.62
crores, no tariff hike is necessary for NESCO.
|
4.12.9
|
The new reform regime has created five
monopolies in lieu of one monopoly. Since there is no competition, the purpose of reforms
to encourage competition cannot be realised.
|
4.12.10
|
Multiplicity of agencies has resulted in
multiplying costs. The poor consumer only pays for it.
|
4.12.11
|
The revenue requirements of the licensees have
been inflated due to the govt. increasing the book value of assets 2 to 3 times,charging
higher rate of depreciation etc. The cost of electrical energy should have been one of the
three lowest among the Indian states due to availability of 45% of energy from hydro.
|
4.12.12
|
The proposed increase in tariff shall enhance
cross-subsidy burden for EHT consumers.
|
4.13
|
Tata Iron & Steel Company
|
4.13.1
|
Shri P.K. Das appeared on behalf of M/s. Tata
Iron and Steel Company. He claimed that NESCO's application for retail tariff should be
considered only after GRIDCO's BST is finalised.
|
4.13.2
|
The voltage and load factor and minimal
transmission loss justify that the tariff for power intensive industry should be a little
over the bulk supply tariff rate. Thus, the Commission may direct NESCO to provide special
tariff to EOUs.
|
4.13.3
|
He submitted that the T&D loss should be
fixed at 31.5% (28% for distribution + 3.50% transmission), the tariff rate for all EOUs
should be same in Orissa, the incentive offered by all DISTCOs should be uniform for a
particular category of consumer, the demand charges may be reduced to Rs.150/KVA from
Rs.200/KVA and incentive tariff should continue.
|
4.13.4
|
In the present cyclonic situation, there should
be no upward revision of BST and RST.
|
4.13.5
|
MMFC is proposed by NESCO in respect of
consumers having contract demand of less than 100 KW/110 KVA. Therefore, the MMFC should
be deleted for items 10 to 12 in LT.
|
4.13.6
|
He objected to NESCOs request for
disallowing CPPs for a period of three years which if agreed would increase monopoly and
allow NESCO to cover up its inefficiency.
|
4.14
|
Shri R.C. Padhi
|
4.14.1
|
Shri R.C. Padhi reiterated objections on grounds
of absence of audited accounts for 1998-99, high distribution loss, unduly high expenses
on employees cost, A&G, bad debts and interest etc.
|
4.14.2
|
He urged that depreciation should be allowed
only after the NESCO maintains a depreciation register and since revenue requirements are
based on prudent costs, costs due to inefficiency should not form part of revenue
requirement.
|
4.14.3
|
The licensee may so fix industrial tariff that
CPPs may become uneconomical.
|
4.14.4
|
Shri Padhi made numerous observations,
objections and suggestions as below:-
-
If a contingency fund is created with the collection through tariff, then any
expenditure from this reserve should not be claimed from consumers as capital development
expense.
-
Tariff fixation should have been made after a socio-economic survey on the lower income
group's need for electricity and its ability to pay.
-
Reform has added to costs by unbundling institutions.
-
Kutir Jyoti consumers pay a fixed minimum price for consumption of 30 units/month. All
other consumers whose consumption is equal to or below 30 units should be charged at he
same rate.
-
Application of marginal costs may amount to over collection of revenue. The excess
collected should be returned back in tariff to the weaker groups by subsidised tariff.
Hence there is no specific advantage of marginal cost pricing.
-
Studying the voluminous reports submitted to OERC and making suggestions for change
within a very limited time is difficult for a lay consumer. Instead, simpler formats may
be prescribed for the licensee and more time may be given to consumer to give his
comments.
-
A forum of electricity consumers may be formed and the licensee may discuss various
issues with them from time to time to obtain valuable suggestions.
-
Audits done by private firms are not reliable. Audit of accounts of the licensees may,
therefore, be conducted by the A.G.(Orissa).
-
The MIS data are unreliable.
-
The connected load of consumers with CL above 1.0 KW can in no case be less than 150% of
the number of such consumers (P.29,30 & 31).
-
BST should be finalised by 1st December every year and RST by 1st April.
-
It is illegal on the part of NESCO not to deduct the amount of security deposit
(Rs.27.70 crores) to determine the capital base.
-
The calculation of reasonable return is also not in accordance with the notification of
the Govt. of India on 5th May, 1999.
-
Providing tariff incentive to EOUs as forex earner is the responsibility of the GOI and
not of electricity consumers.
-
Special tariff proposed for the EOUs is substantially lower than the normal tariff for
similar power intensive industries.
-
The arrangement of supply of NTPC power to EOUs may be allowed to continue. The EOUs and
the GoO may take up with the GoI to reduce cost of NTPC off-peak power.
-
The special tariff for EOUs be rejected or allowed subject to confirmation of payment of
subsidy by the GoO. In the case of rejection of special tariff, NESCO should allow drawal
of NTPC power.
|
4.15
|
During hearing Director (Tariff), OERC sought
clarification from NESCO on the following issues :-
|
4.15.1
|
The details of capital investment NESCO proposed
to carry out during the year 1999-00 and the approval of competent authority to execute
such capital works.
|
4.15.2
|
Charging of interest to revenue in excess of
those which are capitalised during the year.
|
4.15.3
|
Method of determination of maximum demand,
calculation of losses in HT and the status of HT and EHT metering.
|
4.15.4
|
The impact of hike in diesel price on the cost
of CPPs running with DG sets.
|
4.15.5
|
The increase in the quantum of energy expected
to be sold as a result of introducing incentive tariff.
|
4.15.6
|
Regarding signing of the special agreement
between M/s. Ispat Alloys Ltd. and NESCO which is filed in OERC for favour of approval and
the consequential effects of such agreement on expected revenue which is being calculated
on the basis of the existing tariff i.e. of 1st Dec., 1998.
|
5.0
|
NESCOS
REPLY TO THE OBJECTIONS The Managing Director of NESCO replied to the various
issues raised by the objectors. |
5.1
|
In its rejoinder to the above objections NESCO
stated that the proposed increase in tariff is based on a reasonably accurate estimate of
the revenue requirement of 1999-00 and would be applicable only for a part of the year
resulting in a huge loss for the DISTCOs. For maintaining the viability of the power
sector a balance need be struck between the interest of the licensee and the interest of
the consumers. The proposal of the licensee aims at that. NESCOs application has
been submitted basing on the present BST tariff and the question of the licensee resorting
to high cost power does not arise.
|
5.2
|
T&D loss as reflected in the management
information system of the previous financial year indicates a higher level of loss than
what has been projected by GRIDCO. NESCO is carrying massive metering plan and adopting
other measures for reduction of losses like installation of LT less transformers and
strengthening the distribution system. The benefits of loss reduction measures now being
undertaken will take time to fructify. NESCO is committed to reduce distribution losses
and has targeted at 40% during 1999-00.
|
5.3
|
A large number of LT Consumers continue to pay
tariffs significantly lower than their cost of supply. Elimination of cross subsidy would
be essential to undertake substantial measures towards further tariff reforms where tariff
could be differentiated on the basis of time of use, extent of use, and manner of use. For
avoiding sharp increases in tariff, OERC recognises the gradual process of elimination of
cross subsidy over a period of time. Hence cross subsidy would have to continue till such
time and that licensee will not be in a position to bring down cost for HT and EHT
consumers.
|
5.4
|
It is stated that the calculations made by the
UCCI regarding revenue requirements of NESCO are not based on facts and, therefore, are
not correct. NESCO's application has been submitted basing on the present BST tariff and
the question of the licensee resorting to high cost power does not arise. Employee Cost
and Administration & General Expenses have been computed based on the company's actual
for the early months of the fiscal year. With regard to bad debts, it is submitted that
the arrears from the State Government Departments and undertakings as on 31.03.99 have
been transferred to GRIDCO and have not been transferred to NESCO's account. The remaining
opening debtors as on 01.04.99 have been inherited from GRIDCO. A large chunk of arrear
appears to be doubtful. It is proposed to write off such bad and doubtful debts during a
period of three years. The interest component of the total expenses is estimated correctly
and the provision of contingencies reserve has been made as per the Act, 1948.
|
5.5
|
With reference to objections of Small Scale
Industrial consumers, NESCO in its rejoinder said that several measures were being taken
to improve the supply system after taking over the charge and the benefits of the same
shall be visible over a period of time. Load surveys are being made and steps have been
taken to provide meters to all classes of consumers. NESCO has continued the incentive for
consumption beyond 60% load factor by proposing a discount of 10% on such consumption.
|
5.6
|
NESCO in its rejoinder to the objections raised
by Railways stated that it purchased power from GRIDCO who in turn purchases the same from
different generators including NTPC. The selling price of power to the ultimate consumers
like railway is bound to be higher than the NTPC rate due to additional cost of
transmission.
|
5.6.1
|
Over drawal by a consumer places additional
financial burden on the system as the incremental power purchase cost is always high. It
puts additional burden on system stability and reliability and thereby affects other
consumers apart from disturbing the power procurement planning. Thus the levy of over
drawal charge is justified. Regarding defective meters, NESCO stated that the rules and
procedure prescribed in the OERC Distribution Code, 1998 have to be implemented and those
issues cannot be settled in a tariff proceeding.
|
5.6.2
|
Referring to the structure of tariff, NESCO said
that consumers having more than 100 KW connected load were charged on the basis of a
two-part tariff consisting of demand and energy charges. The Monthly Minimum Fixed Charge
is being charged in respect of consumers having contract demand of less than 100 KW/110
KVA. NESCO further clarified that there was no such proposal for a MMFC in respect of the
Railways. The retail tariff order of 1998-99 permits either a rebate for timely payment or
the levy of delayed payment surcharge and not both for a particular consumer category and
the same has been followed by NESCO in its tariff proposal.
|
5.6.3
|
There is no proposal to bring in changes in the
existing tariff with regard to power factor penalty or introducing incentive for improved
power factor.
|
5.6.4
|
The Railways avail supply at HT voltage where
the interruptions are negligible. Besides the frequency and voltage of supply depends upon
the system voltage and frequency and the retail licensee has no control over the same.
|
5.7
|
As regards the EOUs suggestion for not levying
any demand charge, NESCO has stated that the cost structure of the DISTCO's consisted of a
fixed and a variable portion. The structure of revenue of DISTCO's should also resemble
their cost structure. Thus a total withdrawal of fixed charges would affect the fixed
revenue stream of the DISTCOs their cost structure remaining the same.
|
5.7.1
|
The proposal to levy energy charge to EOUs is as
per the agreement signed between them and NESCO which has been filed with OERC for favour
of approval.
|
5.7.2
|
Regarding penalty for an inferior power factor
NESCO stated that improved power factor resulted in reduction in the recorded demand of
the consumer bringing in lower demand charges. However, a drop in the power factor affects
the system reliability and stability and thereby affects other consumers also.
|
5.8
|
NESCOs rejoinder covered a number of other
issues. It was explained that customer service charge is levied to partially compensate
the licensee towards providing services like metering, billing, complaint handling etc.
|
5.8.1
|
Tariff order of 1998-99 permits either a rebate
for timely payment or a levy of delayed payment surcharge and not both for a particular
consumer category. NESCO's proposal continues with this principle.
|
5.8.2
|
The monthly minimum fixed charge (MMFC) is being
levied in respect of consumers having contract demand of less than 100 KW/110 KVA in line
with the levy of demand and energy charges on consumer having connected load having more
than 100 KW/110 KVA.
|
5.8.3
|
The procedure of allowing only 10% of the total
consumption by a HT industry as housing colony consumption at a reduced tariff is a
liberal concession. The proposed colony consumption tariff is still lower than the
proposed tariff charges for consumption during peak hours by EOUs.
|
5.9
|
In its rejoinder NESCO also clarified its stance
on Captive Power Plants. NESCO advocates that industry is inclined to set up CPPs due to
the prevailing distorted tariff structure where the industrial consumer subsidises the
domestic consumer. The GoO had given a boost to CPPs by permitting third party sale of
power under Section 28(1) of the Indian Electricity Act, 1910. This has resulted in a
reduction in consumption of Grid power by the industrial consumers and a corresponding
increase in the burden of tariff on the consumers who continue under the grid. The OERC
has discussed the issue of captive generation and of third party sale on various
occasions. Third party sale would be allowed if the permission had been obtained from the
GoO under the said section before the enactment of the Reform Act, 1995. After the
enactment of the Reform Act, 1995, third party sale is not permitted. Orissa is a power
surplus state and therefore does not require installation of additional capacity at this
time. Obviously large power plants are economical compared to CPPs. Thus allowing CPPs
would mean uneconomical allocation of scarce resources. What is therefore needed is a
necessary correction in the distorted price structure which would be more difficult if
further addition is made to captive capacity. If CPPs are allowed, it would mean lower
generation from the large power plants which would increase the average cost of
generation. The IPPs already have take-or-pay conditions in the PPAs and the introduction
of availability based tariff is currently under consideration which would result in higher
cost/unit.
|
5.10
|
While certain industrial consumers have the
option to set up captive generators a large number of consumers do not enjoy that choice.
Therefore encouragement of captive generation would adversely affect consumers like
households, small industries, public lighting and public water works etc.
|
5.11
|
NESCO replied to the issues raised by Director
(Tariff), OERC and submitted that the company has not charged the interest cost of the
loan availed for the capital investment to revenue. The funding for these projects would
be through World Bank finance to be availed through Government of Orissa. Further they
submitted that only 60% of the rural electrification works would be completed during the
ensuing year and interest cost on these works has been charged to revenue only to the
extent of 60%.
|
5.12
|
Maximum demand of NESCO is calculated by GRIDCO
on simultaneous arithmetic sum of demand recorded every half an hour.
|
5.13
|
HT feeders are supplying to HT and LT consumers
and hence estimating HT loss separately is not possible.
|
5.14
|
Regarding status of HT and EHT metering, the
Licensee stated that quarterly report regarding installation of meters is regularly
submitted to OERC and over a period of time TOD meters will be inserted wherever
necessary.
|
5.15
|
The additional quantum of sale after offering
incentive tariff would be 36 MU and the incremental annual contribution to be earned by
NESCO would be Rs.36.25 crores.
|
6.0
|
COMMISSIONS
OBSERVATIONS
|
6.1
|
We have noted that vital issues have been raised
by the objectors and the Commission had the benefit of many useful suggestions. We have
given careful consideration to each one of the issues raised by the objectors and have
analysed the submissions made by the Licensee in the light of these issues. However, we
must note that some of the objections raised during the hearing were not relevant to the
present tariff proceeding.
|
6.1.1
|
As has been observed in the Commissions
Order in Case No.19 of 1998 the issues like reform, restructuring, privatisation,
revaluation of assets on transfer to GRIDCO and OHPC are not within the scope of this
Commission since such issues are matters of public policy and legislation. Hence these
aspects need not be dealt in this Order on tariff. Similarly recurring complaints on
consumer service has to be dealt in appropriate proceedings. The Commission is monitoring
the performance of the licensees as required under law. Therefore, such issues are not
being dealt with by the Commission while examining the present tariff proposal.
|
6.1.2
|
We do not find it necessary to specifically
comment on each one of the objections. The objections with regard to financial aspects and
with regard to tariff design as well as various suggestions on these aspects shall be
dealt by us in the later part of the order while dealing with the revenue requirement and
determination of tariff. However, we may record out observations specifically on a few
issues which do not conveniently fit into the module of either revenue requirement or
tariff.
|
6.1.3
|
The licensee has suggested uniform tariff for
the three utilities under the management of BSES like WESCO, NESCO and SOUTHCO. In view of
substantial difference in consumer composition, distance from the generating stations,
levels of efficiency and other factors, the financial viability will have to be widely
different in case of these three companies. In this background, NESCO has suggested that
excess revenue from WESCO may be permitted to flow to NESCO and that amount may be treated
as special category capital or alternately OERC may consider treating the surplus as a
revenue subsidy from WESCO to NESCO. This request by the Licensee has wider implication.
The Commission carefully considered and has come to a decision that while differential
tariff for different companies will be eventually inevitable, at the present stage of
transition it is desirable to have uniform tariff for all the four distribution companies
in Orissa. However, we are unable to accept the request of any adjustment and financial
flow between different companies through innovative method such as special category
capital or revenue subsidy. Each companys finance and tariff has to be examined
independently in accordance with Sixth Schedule and other provisions of the Act, 1948. The
Commission does not approve of inter-linkings in financial matters between different
companies. Therefore, the request of NESCO in this regard cannot be acceded to.
|
6.1.4
|
With regard to the Licensees request that
captive generation should not be permitted for a period of three years, we have noted the
rationale of the request as given in the tariff application as well as in the rejoinder.
We have also noted that representatives of industry and others have vehemently opposed to
the request mainly on the ground that any prohibition in setting up captive power plant
will retard industrial progress and that it will result in monopolistic environment not
compatible with the aims and objectives of the Reform Act, 1995. We would like to record
that determination of tariff has to be in the background of existing regulatory
environment and that tariff proceeding is not the appropriate occasion for taking a
decision in this matter for which the views of all concerned as well as the government
which has the responsibility for framing policy for the power sector have to be taken into
account.
|
6.1.5
|
In course of the pleadings, consumers of
different category have highlighted the impact of tariff with reference to financial
viability, commercial consideration and ability to pay. While we have taken into account
the overall interest of the consumers we have also given equal consideration to the
financial viability of the Licensee and the necessity of the State for fostering a healthy
electricity industry. Ability to pay, lack of funds or competitiveness of any particular
industry either in the domestic or in international market cannot be the guiding
consideration in designing tariff. The Commission does not find it desirable to move
beyond the considerations incorporated in Section 26(2) and Section 26(5) of the Reform
Act, 1995.
|
6.1.6
|
The Reform Act, 1995 envisages a tariff
structure that would bring about efficiency and economy in the supply and consumption of
electricity. The Reform Act, 1995, also aims at a tariff that would reflect cost, would be
linked to efficiency and would eliminate inter-class and intra-class subsidies.
|
6.1.7
|
The Commission is also deeply aware of its role
in balancing the conflicting interest of various stakeholders, bringing about efficiency
and economy in the use of electricity and designing a tariff structure that should be
just, fair and reasonable. The low voltage consumers expect a tariff that is affordable
and the high and extra high voltage consumers are pleading for a tariff that should reduce
their burden of cross-subsidy. While taking note of these factors, we have also to go by
the mandate in law to allow reasonable return to the investors in the electricity industry
in the State.
|
6.1.8
|
During the course of hearing, some of the
objectors made a strong plea that since the super cyclone has completely destroyed the
agricultural and industrial infrastructure of the State and has affected large number of
consumers, there should be no increase in tariff and the proposal should be kept on hold.
|
6.1.9
|
The Commission is not only aware of but deeply
sensitive to the ground conditions in the State in the aftermath of the super cyclone.
Much as the Commission would have liked to do the contrary, it would not be reasonable for
the Commission to deny any increase whatsoever in tariff because such denial would impinge
not only on the financial viability of the Licensee but would also affect its operational
efficiency.
|
6.1.10
|
We, therefore, proceed to examine the revenue
requirement and expected aggregate revenue from charges of NESCO for 1999-00 and
subsequently to examine the tariff proposed by NESCO to give our findings and orders
thereon in accordance with the extant law.
|
7
|
REVENUE
REQUIREMENT
|
7.1
|
After its formation and obtaining licence for
distribution and retail supply, NESCO has submitted its revenue requirement for the year
1999-00 for which no comparative figure for the last Financial Year is available. The
Commission has for the purpose of analysing the revenue requirement relied on the
disaggregated audited accounts submitted by GRIDCO for the Financial Year 1997-98 and the
data & records presented to the Commission by NESCO as well as the facts and arguments
placed by the objectors before it.
|
7.2
|
Quantum
of Power Purchase
|
7.2.1
|
The quantum of power purchase is dependent on
the quantum of energy sold to the consumers and the transmission and system loss. While
estimating energy sale for 1999-00, NESCO has analysed the pattern of consumption of
various groups of consumers for the year 1997-98, 1998-99 and projected this figures for
the financial year 1999-00 in the format prescribed by OERC. According to the analysis of
energy sale mix between LT, HT, EHT consumers for the FY 1999, LT consumption accounted
for 44.40% while HT & EHT consumption accounted for 24.21% and 31.37% respectively.
NESCO has reported that for the purpose of estimation of sale of energy for FY 1999-00, it
has evaluated the past billing information for each category, compared the consumption for
the first quarter of 1999-00 over the corresponding period of the financial year 1998-99,
studied the loss reduction initiatives and their impact on billing, analysed energy
off-take consumers in HT & EHT category and used realistic assumptions and current
economic situation.
|
7.2.2
|
The Commission analysed the consumption of
various groups of consumers and studied the consumption of all HT & EHT consumers. A
detailed analysis of the billed units of the LT consumers particularly the domestic and
commercial consumers without meters or with defective meters was also carried out.
Consumers with correct meters are billed on the basis of actual meter reading whereas
others with defective meters or no meters at all are billed on the basis of a load factor.
The Commission has prescribed detailed formats to determine the consumption for all such
consumers. NESCO has requested the Commission to accept data on consumption of LT
consumers based on the meter readings of the months of April, May & June99 in
respect of Domestic, Commercial, Irrigation, Small Industries of all consumers throughout
NESCO. Treating the meter readings of April, May & June99 as sample consumption
for a period of 12 months of entire NESCO has been estimated through a computer model.
While accepting, in the absence of complete data, this method of sampling for the purpose
of the present application, the Commission enjoins upon NESCO that for future applications
it must maintain the required information for calculation of consumption by various
classes of consumers in the format prescribed by OERC.
|
7.2.3
|
For the year 1999-00, the
break up of energy sale forecast by NESCO is as follows :-
Category Consumption in MU
LT
|
548.83
|
HT
|
299.27
|
EHT
|
387.76
|
Total
|
1235.86
|
|
7.2.4
|
This is an increase of about
8% over the sale in FY 1998-99. This aspect was examined at the Commissions end. A
comparative picture of the consumption of the previous two years along with projection of
1999-00 is given below :-
Consumption in MU
|
97-98
|
98-99
|
99-00
|
LT
|
404.81
|
482.00
|
548.83
|
HT
|
194.90
|
196.74
|
299.27
|
EHT
|
562.46
|
463.01
|
387.76
|
Total
|
1162.17
|
1141.34
|
1235.86
|
|
7.2.5
|
NESCO has reported that there has been increase
in consumption by consumers of LT category and HT industries and decrease in consumption
by heavy industries availing power at EHT during the first quarter of 1999-00 over the
corresponding period of the year 1998-99. There has also been a substantial decrease in
consumption by the power intensive category. Decrease in consumption in the first quarter
of the year has been observed by the consumers covered under general purpose tariff and
large industries at 132 KV. The Commission on examination of the above figures of NESCO
approves the energy sale forecast by NESCO in para 7.2.3.
|
7.3
|
Transmission & Distribution Loss
|
7.3.1
|
NESCO has estimated T&D loss as 40% in
1999-00. It has stated that as per MIS figure for the year 1998-99, the estimated loss
figure is 43%.
|
7.3.2
|
NESCOs estimation of the overall loss
percentage of 40% does not include the loss at EHT which is being recovered by the
Transmission and Bulk Supply Licensee i.e. GRIDCO, through the Bulk Supply Tariff. In
effect, therefore, the end-use consumers of NESCO would have to bear the EHT loss passed
through in the BST in addition to 40% loss proposed by NESCO. A large majority of the
objectors have questioned the high percentage of system loss proposed by NESCO and have
suggested bringing it down to 28%. Most of the objectors were unanimous in their opinion
that this high level of T&D loss has remained uncontrolled during the past three years
and no tangible achievement has taken place in this area of loss reduction and the
consumers are again being burdened with this high loss. The objectors are of the opinion
that the change from OSEB to GRIDCO and subsequently to separate distribution licensees as
a part of the reform process for rendering efficient and economic service to the consumers
have been totally belied. Unauthorised use of electricity by dishonest persons is largely
responsible for T&D loss which is proposed to be passed on to the honest consumers.
Similar is the case of replacement of defective meters or installation of new meters which
should have encouraged correct recording of energy consumption and consequent billing to
the consumers. They have stated that during the last three financial years while there is
a progressive rise in the quantum of purchase, there is no commensurate growth in sales.
Increase in billed revenue is largely attributable to the higher load factor billing
approved by the Commission. One of the objectors pointed out that load factor billing is
misutilised by many consumers with defective meters who pay a fixed amount but consume far
in excess including selling it to third parties covertly. Many objectors drew pointed
attention to the mismanagement and complete negation of the Commissions direction on
loss reduction and insisted that the Commission should not allow the high percentage of
system loss proposed by the Distribution Licensee. They said that under no circumstances,
the percentage of T&D loss should be allowed at a level higher than 31%.
|
7.3.3
|
NESCO has claimed that recognizing the energy
losses at 35% compared to actual losses of 40% to 43% is a wide departure from the Sixth
Schedule to the Act, 1948. Since the present loss level has been inherited by NESCO from
GRIDCO, it has requested OERC to reconsider the benchmark of 35% fixed by OERC and to fix
a reasonable target of 40% for the year 1999-00.
|
7.3.4
|
In its rejoinder during hearing for Retail
Supply Tariff, it has explained that it is committed to reduce distribution losses. It is
stated to have already embarked on a massive metering plan the progress of which is being
reported to OERC. Additionally several other projects are being undertaken to strengthen
the distribution system. However, the benefit of all the above would accrue only over a
period of time. For the distribution loss during the financial year 1999-00, NESCO has
suggested to OERC to propose a mechanism of sharing the revenue loss between other
constituents like GRIDCO and the Government of Orissa which is prescribing policy issues
for the sector. The extent of loss to be shared should be in consonance with the
partys ability to bear the loss so that the consumers are insulated from a sharp
increase in tariff.
|
7.3.5
|
NESCO has stated that a significant portion of
electricity consumed in Orissa is not metered making it difficult to accurately establish
the extent of energy loss. The most reliable data for the actual energy loss is the energy
audit carried out in 1996 as a part of reform programme. In the information memorandum
circulated at the time of inviting bids for privatisation, the distribution loss for
1996-97 for NESCO was shown as 40.00%. The memorandum also projected an ambitious loss
reduction targets. Contrary to the expectation of the Information Memorandum the
distribution loss for the year 1998-99 based on the MIS figure of GRIDCO shows a loss
figure of 43% which NESCO believes is a conservative estimate.
|
7.3.6
|
NESCO has stated that based on its experience a
loss reduction of 2-3% will be possible for 1999-00. Accordingly, it has targeted to
reduce the loss to 40%.
|
7.3.7
|
The Commission has very carefully considered the
position stated by NESCO about its short period of operation in the business of
distribution since 01.04.99. The Commission has taken note of the loss reduction measures
proposed by NESCO and would like to be apprised of the progress achieved in implementing
them at the end of each quarter. The Commission has also taken note of the objections to
NESCO assuming a T&D loss of 40% almost three years after the Commission determined
the benchmark of 35%. While NESCO insists on the T&D loss of 40% in addition to the
transmission loss of 4% in GRIDCOs system, the objectors want this loss to be as low
as 28%. NESCO has not presented any detailed data to the Commission justifying its claim
of a T&D loss as high as 40%. We must make it clear that data furnished by the
Licensee to claim revision of benchmark of T&D loss is without solid basis. It has not
completed a year of operation and has, therefore, made its analysis and projections on the
basis of data handed down by GRIDCO whose accounts for 1998-99 have not been audited yet.
The additional sampling of two months does not reflect a reliable picture mainly because
the figures are also based on load factor billing. We also agree with the objectors that
no perceptible steps have been taken for checking pilferage and other illegal abstraction
of energy. In the circumstances, particularly in the absence of any credible evidential
data, the Commission does not find it desirable to revise its benchmark of 35% of T&D
loss for tariff determination.
|
7.3.8
|
Since NESCO proposes to sell
1235.86 MU, power to be purchased by GRIDCO for supply to NESCO, after adding 35% loss, is
determined as 1901.32 MU (1235.86/0.65). NESCOs purchase from GRIDCO should be
limited to 4% (being the approved transmission loss in EHT) less than what is purchased by
GRIDCO for supply to NESCO. For the purpose of revenue requirement, NESCO has to purchase
only 1901.32 MU to meet its sale requirement of 1235.86 MU for the year 1999-00. The
system loss in NESCO is 1825.27 MU 1235.86 MU = 589.41 MU. This loss of 589.41 MU
expressed as a percentage of input to the NESCO system is (589.41/1825.27) 32.29%.
Therefore, the distribution loss allowed to NESCO for the purpose of revenue requirement
is 32.29%. The loss of 589.41 MU in NESCOs system expressed as a percentage of units
purchased for NESCO by GRIDCO is (589.41/1901.32) 31%. Thus, out of the energy purchased
for NESCO by GRIDCO, 4% is lost in the EHT system of GRIDCO and 31% is lost in the
distribution system of NESCO. The end use consumer has to pay through tariff a loss of 35%
of energy purchased by GRIDCO for supply towards the T&D loss. For simplicity of
presentation, we have abstracted the above calculation in Table : 4.
Table: 4
Sale projected by NESCO |
1235.86 MU
|
Power to be purchased by GRIDCO for NESCO
applying a loss level of 35% |
1235.86/0.65 = 1901.32 MU
|
Power to be purchased by NESCO from GRIDCO
less loss of 4% at EHT |
1901.32X0.96=1825.27 MU |
Energy loss in NESCOs system |
1825.271235.86 = 589.41 MU |
Distribution loss of NESCOs system |
589.41/1825.27 = 32.29% |
|
7.4
|
Cost of Power
|
7.4.1
|
NESCO has to purchase 1901.32 MU from GRIDCO at
the Commissions approved rate of Rs.200/KVA/month + 80.70 paise/unit. The Commission
has examined the power purchase bills of NESCO for April, 1999 to July, 1999. The bill
details have been supplied by NESCO in its clarification submitted to the Commission in
Table : 7 of the clarification on Retail Supply Tariff of 1999-00. The average cost per
unit of power purchased from GRIDCO for the months of April, 1999 to October, 1999 is
129.05 paise/unit. Since there would be a decrease in the energy charge by 4.80 paise/unit
according to the BST determined by the Commission now, the rate/unit payable by NESCO
would be 124.25 paise/unit. The cost of power @ 124.25 paise/unit for purchase of 1825.27
MU would, therefore, be Rs.226.79 crores instead of Rs.279.26 crores proposed by NESCO.
|
7.5
|
Operating
Expenses The operating expenses for distribution and retail
supply may be considered under the following heads :-
Employees Cost
Administration & General Expenses
Repair & Maintenance Expenses
Less expenses capitalized |
7.5.1
|
Employees Cost
|
7.5.1.1
|
NESCO has proposed Rs.41.94
crores for the FY 1999-00 towards Employees Cost. The claim is said to be based on audited
accounts for 1997-98 and revised budget estimates for 1998-99. It is seen that this does
not include other employee related expenses such as Rs.4.92 crores towards contribution to
Provident Fund, Staff Pension and Gratuity and Rs.0.10 crores towards training which have
been shown separately. Employees cost for NESCO in the disaggregated and audited accounts
for the year 1997-98 was Rs.35.06 crores which included salaries, wages, allowances,
benefits, staff welfare expenses and terminal benefits. NESCO, in response to the
Commissions query, has submitted comparative item wise details for the FY 1997-98
(audited accounts), estimated figure for FY 1998-99 and projected amount for FY 1999-00.
The number of employees on roll as on 01.09.1999 is in Table : 5.
Table : 5
|
Technical
|
Non-Technical |
Total |
Executive |
-- |
203 |
203 |
Non-executive |
-- |
4368 |
4368 |
Total |
-- |
4571 |
4571 |
|
7.5.1.2
|
We have examined the data
furnished by the Licensee. The Commission considers it reasonable to adopt a 3% annual
increase on account of normal increment in salaries & house rent allowance and a 6%
annual increase in order to factor in inflation for other expenses (including dearness
allowance) on base figure of FY 1997-98 as reasonable. However, in regard to staff welfare
expenses the base has been taken at a reduced figure of Rs.0.20 crores allocated on the
basis of percentage of employees allotted to NESCO from the undivided GRIDCO. Accordingly,
the total estimated expenses under this head is approved at Rs.39.84 crores. The Employees
cost proposed by the Licensee and the Commissions decision on Employees Cost are
indicated in Table : 6.
Table : 6
(Rs. in crores)
Sl.No |
|
Disaggregated account of
1997-98 |
Estt. by Licensee
1998-99 |
Projected by Licensee
1999-00 |
Approved
by Commission |
1 |
Salaries |
16.59 |
23.20 |
23.90 |
17.59 |
2 |
Over time |
-- |
-- |
-- |
-- |
3 |
Dearness Allowance |
10.05 |
5.34 |
8.84 |
11.98 |
4 |
Other Allowance |
0.19 |
0.24 |
0.33 |
0.21 |
5 |
Bonus |
0.27 |
-- |
-- |
-- |
6 |
Total Emoluments (1 to 5) |
27.10 |
28.78 |
33.07 |
29.78 |
|
Other Staff Cost |
|
|
|
|
7 |
Reimbursement of Medical
Expenses |
0.41 |
0.87 |
1.11 |
0.46 |
8 |
Leave Travel Concession |
0.01 |
0.11 |
0.33 |
0.12 |
9 |
Reimbursement of H.R. |
2.12 |
3.94 |
4.06 |
2.25 |
10 |
Interim Relief of Staff |
0.02 |
-- |
-- |
-- |
11 |
Encashment of earned leave |
0.01 |
1.17 |
1.34 |
1.23 |
12 |
Honorarium |
-- |
0.01 |
0.01 |
0.01 |
13 |
Payments under Workmens Compensation Act |
-- |
0.07 |
0.12 |
0.12 |
14 |
Ex-gratia |
-- |
1.68 |
-- |
-- |
15 |
Other cost |
-- |
0.01 |
0.03 |
0.03 |
16 |
Total Other Staff Cost (7 to 15) |
2.57 |
7.86 |
7.00 |
4.22 |
17 |
Staff Welfare Expenses |
0.33 |
0.40 |
0.52 |
0.22 |
18 |
Terminal Benefits |
5.06 |
5.56 |
6.27 |
5.62 |
19 |
Total (6+16+17+18) |
35.06 |
42.60 |
46.86 |
39.84 |
|
7.5.2
|
Administration & General Expenses
|
7.5.2.1
|
NESCO has proposed A&G expenses for 1999-00
as Rs.4.77 crores. These expenses include expenses on communication, travel, training and
other charges. NESCO has also separately proposed of Rs.0.08 crores and Rs.0.08 crores
towards legal charges and audit fees, respectively. For the year 1999-00, NESCO expects a
significant increase in A&G expenses on account of increase in infrastructure and
consumable requirement.
|
7.5.2.2
|
The Commission has examined the Licensees
proposal on A&G Expenses. A&G expenses as per the disaggregated accounts of GRIDCO
for 1997-98 was Rs.4.05 crores excluding bad debt. This included legal expenses, rent,
rate, taxes and audit fees. The Commission considers it reasonable to allow an annual
increase of 6% over audited figure of 1997-98 to factor in inflation. Accordingly, A &
G Expenses for 1999-00 is approved at Rs.4.55 crores against Rs.4.93 projected by NESCO.
|
7.5.3
|
Repair and Maintenance Expenses
|
7.5.3.1
|
The R&M expenses proposed by NESCO is
Rs.14.22 crores for the FY 1999-00. This has been calculated as 5.4% of the gross fixed
assets at the beginning of the year indicated in the transfer notification dtd. 25.11.98.
The Commission considers the proposal reasonable and approves Rs.14.22 crores as R&M
expenses for the FY 1999-00.
|
7.6
|
Interest on Loan
|
7.6.1
|
NESCO has proposed an amount of Rs.18.33 crores
to be charged to revenue on account of interest including a sum of Rs.0.23 crores towards
interest on working capital. It is seen that interest amounting to Rs.18.10 crores is
attributable to loan of Rs.139.25 crores allocated to NESCO and does not relate to any
fresh loan taken by NESCO for major investment. Out of this interest, amount of Rs.18.10
crores indicated earlier Rs.13.73 crores is on account of subsidiary loan from GRIDCO
(based on the transfer notification dtd.25.11.98) on an outstanding loan of Rs.104.84
crores as on 01.04.99 and Rs.4.21 crores on the World Bank Loan of Rs.32.41 crores as on
01.04.99. Balance of interest amounting Rs.0.16 crores is on account of loan of Rs.2.00
crores taken during the year for sundry capital expenditure. The Commission approves the
figure of Rs.18.10 crores to be charged to revenue for 1999-00.
|
7.6.2
|
The Commission also finds the interest of
Rs.0.23 crores towards working capital projected by the Licensee as reasonable and hence
chargeable to revenue for the FY 1999-00. Thus the total expenses on interest chargeable
to revenue is as follows :- Interest on long-term loans -
Rs.18.10 crores
Interest of working capital -
Rs. 0.23 crores
-------------------
Total - Rs.18.33 crores |
7.7
|
Depreciation
|
7.7.1
|
NESCO has proposed
depreciation of Rs.20.40 crores calculated on the basis of Government of India
notification. The Commission accepts the figure of Rs.20.40 crores on account of
depreciation for the year 1999-00. |
7.8
|
Bad and Doubtful Debt
|
7.8.1
|
NESCO has proposed Rs.25.52 crores as Bad &
Doubtful Debt during 1999-00. In the audited accounts of GRIDCO for 1997-98, NESCO has
been allocated Rs.NIL on this account.
|
7.8.2
|
In order to estimate the provisioning towards
bad debts NESCO has categorised the debtors into two categories (a) Debtors on account of
sales made during the ensuing year (b) Opening debtors for the ensuing year. For the debt
created on account of sales made during the ensuing year the provisioning towards bad
debts has been considered to be equal to 3% of sales for the year. In case of the opening
debtors for the ensuing year, it has estimated that at least 75% of these would be bad or
doubtful. This in its opinion is due to overestimation of gross receivables. In order to
phase out the impact on tariffs, it has proposed to provide for accumulated debts over a
period of three years.
|
7.8.3
|
The Commission is of the view
that allowing bad debt as a percentage of outstandings as on the last day of the year when
the outstanding are galloping from year to year without handling more energy would be
putting a premium on inefficiency in realisation of dues. The Commission endorses the view
that the Licensee must improve its billing and collection efficiency so that provision for
bad and doubtful debt is reduced from year to year. The Commission does not consider it
appropriate to allow 1/3rd of 75% of the opening debtors for passing on to tariff. In the
tariff order of 1998-99 a reasonable assumption of 15% of the differential between gross
book debt as on 31.03.98 and 31.03.99 was assumed as bad and doubtful debts. In the
absence of even provisional figures for FY 1998-99, it will be too much of a conjecture to
arrive at a base figure for calculating provision for bad debt on lines similar to last
year. Hence provision for Bad and Doubtful Debt may be made as 15% of total outstanding as
on 31.03.2000 on the assumption that two months dues shall be receivable on that date. Two
months of the total sale as receivables at the end of the financial year has been
calculated as 16.66% of the total sale. 15% of 16.66% (16.66% x 15%) = 2.49% (of 2.5%) of
the gross annual sale can be assumed to be Bad and Doubtful Debt for being charging to
revenue against 3% claimed by the Licensee. On this basis, the Commission approves Rs.8.10
crores as provision for bad and doubtful debt. |
7.9
|
Contribution to Contingency Reserve
|
7.9.1
|
NESCO has provided Rs.0.99 crores towards
Contribution to Contingency Reserve. It is within the limit prescribed in the Sixth
Schedule to the Act, 1948 and is accepted in full.
|
7.10
|
Capital Base
|
7.10.1
|
Original Cost of Fixed Assets
|
7.10.1.1
|
NESCO has projected its
original cost of fixed assets at Rs.334.40 crores as on 31.03.2000. As the Licensee has
not completed a full financial year of its operation, the only data available are -
figures shown in transfer scheme and provisional figures supplied by the Licensee. In the
absence of audited accounts, the Commission considers it reasonable to accept the figure
given by the Licensee as it appears in the transfer scheme. |
7.10.1.2
|
Original cost of fixed assets as on 31.03.1999
and 31.03.2000 are Rs.263.40 crores and Rs.334.40 crores respectively revealing asset
addition of Rs.71.00 crores during 1999-00. This includes investment of Rs.12.44 crores
and interest capitalized thereon amounting to Rs.1.40 crores on account of rural
electrification works.
|
7.10.1.3
|
No proposal for investment in
rural electrification work has yet been approved by the Commission. Investment on rural
electrification has to be planned only when subsidy is available to bridge the gap between
the cost of investment and revenue recoverable. The Licensee should not take up investment
on uneconomic projects which will burden the consumers. Therefore, without firm commitment
of subsidy from the government and without approval of the Commission for the investment,
the capital addition on account of rural electrification work cannot be allowed to be
included in the capital base for earning return. The Commission has decided to retrench
Rs.13.84 crores (capital expenditure of Rs.12.44 crores and interest during construction
thereon of Rs.1.40 crores) from Rs.334.40 crores. Thus, fixed assets as on 31.03.2000
approved by the Commission would be Rs.320.56 crores as against Rs.334.40 crores projected
by the Licensee. |
7.10.2
|
Receipts against Consumers Contribution
|
7.10.2.1
|
The aggregated receipts against consumers
contribution at Rs.50.02 crores has been rightly deducted from fixed asset while
calculating of capital base.
|
7.10.3
|
Original cost of Work In Progress
|
7.10.3.1
|
For the purpose of Capital Base calculation,
NESCO has projected Rs.33.05 crores towards original cost of work in progress. This
includes a sum of Rs.8.29 crores towards rural electrification works for which no approval
from the competent authority has been taken. As we are adopting cost-based tariff, it is
essential to see that each and every project undertaken by the Licensee is commercially
viable. So far social projects are concerned they should be duly subsidized by the
Government through budgetary support so that the cost of any uneconomic project is not
borne by the consumers.
|
7.10.3.2
|
As observed earlier at para 7.10.1.3 the
Commission considers it unreasonable to include rural electrification projects in the
Capital Base unless these projects are proved to be commercially viable or the Govt. of
Orissa supports these schemes by providing subsidies. Accordingly, a sum of Rs.8.29 crores
has to be deleted from the original cost of work in progress which should now be Rs.24.76
crores.
|
7.10.4
|
Compulsory Investment under Para IV
|
7.10.4.1
|
NESCO has projected Rs.0.99 crores against
Compulsory Investment to form a part of the Capital Base. It has to be noted that amount
of investment compulsorily made in accordance with para IV(2) of the Sixth Schedule
of the Act, 1948, can only be included in the Capital Base. No investment has yet been
made and hence the amount is not included now. This can be allowed to be included if and
when evidence of investment out of appropriation towards contingency reserves is produced.
|
7.11
|
Working Capital
|
7.11.1
|
Average Cost of Stores
|
7.11.1.1
|
According to para XVII(e)(i) of the Sixth
Schedule of the Act, 1948, a sum equal to one-twelfth of the sum of book cost of stores,
materials and supplies including fuel on hand at the end of each month of the year of
account should be taken into account as working capital for calculating the Capital Base.
NESCO has proposed Rs.3.56 crores towards average cost of stores in the working capital
estimated on the basis of three months consumption of materials (R&M expenses),
assuming on a lead-time of three months for procurement of materials.
|
7.11.1.2
|
A stock of three months consumption of
materials at any particular point of time can be considered reasonable. Accordingly the
Commission approves one-forth of the total annual consumption of materials i.e. Rs.3.56
crores as reasonable for the purpose of working capital for stores to be included in the
Capital Base.
|
7.11.2
|
Average Cash and Bank
Balance |
7.11.2.1
|
NESCO has proposed Rs.8.64 crores constituting
two months of Employees Cost and Administration & General Expenses towards
working capital requirement in the form of cash and bank balance. As stated in para
XVII(1)(e)(ii) of the Sixth Schedule of the Act, 1948, an amount equal to 1/12th
of the sum of cash & bank balances and call and short term deposits at the end of each
month of the year of account, not exceeding the sum specified therein can be included in
the Capital Base.
|
7.11.2.2
|
As cash and bank balance at the end of each
month of the year of account for 1999-00 cannot be predicted now, a sum equal to two
months payment of Employees cost and A&G Expenses is considered reasonable ceiling for
cash and bank balance to be included in the Capital Base. We, therefore, approve a sum of
Rs.7.30 crores as cash and bank balance for meeting working capital requirements.
|
7.11.3
|
Accumulated Depreciation
|
7.11.3.1
|
NESCO has proposed a sum of Rs.73.72 crores
towards amounts written off or set aside on account of depreciation as on 31.03.2000. The
Commission accepts the amount of Rs.73.72 crores as a deduction for the purpose of Capital
Base.
|
7.11.4
|
Loans and Bonds
|
7.11.4.1
|
NESCO has stated that the loans and bonds for
its distribution and retail supply business as per the transfer scheme notification for
the period ending 31.3.99 amounted to Rs.137.25 crores. During the year 1999-00, NESCO
proposes to raise fresh loans amounting to Rs.56.32 crores. At the end of FY 1999-00, the
amount of loans and bonds will reach a figure of Rs.187.96 crores taking the due
repayments during the year into consideration.
|
7.11.4.2
|
As discussed in para 7.10.1.3
above, capital expenditure for the purpose of rural electrification during 1999-00 has not
been considered as either authorised or prudent. The Commission, therefore, has to exclude
the loan taken for rural electrification. The Commissions revised estimate is in
Table:7.
Table : 7
(Rs. in crores)
Loans and bonds |
187.96 |
Less : fresh REC loan for the year 1999-00
including interest during construction |
22.13 |
Balance |
165.83 |
|
7.11.5
|
Consumers Security Deposit
|
7.11.5.1
|
NESCO has stated that consumers security
deposit has not been considered as a long-term source of funds. It has stated that the
same has not been utilised for creation of fixed assets and the amount of consumers
security deposit has been shown as a current liability and not as a long term liability in
the provisional balance sheet given in the transfer scheme. NESCO has, therefore, pleaded
that it would be incorrect to deduct the amount corresponding to the consumers
security deposit in the computation of Capital Base.
|
7.11.5.2
|
The position taken by NESCO is not tenable under
law. Firstly, the Licensee itself has shown the amount as deductible in the calculation of
Capital Base for 1998-99. Secondly, the amount deposited in cash with the Licensee by the
consumers as security is clearly deductible for the purpose of determination of Capital
Base as per provision of para XVII of the Sixth Schedule of the Act, 1948. Accordingly, an
amount of Rs.29.09 crores appearing in the working capital schedule is deducted in the
computation of Capital Base.
|
7.11.5.3
|
Based on the forgoing observations, the
Commission finds that Capital Base for 1999-00 for the purpose of Sixth Schedule to the
Act, 1948, has to be taken as Rs.37.51 crores (vide Annex-B
to this Order) as against Rs.68.94 crores proposed by NESCO.
|
7.11.6
|
Reasonable Return
|
7.11.6.1
|
NESCO has calculated the
reasonable return by multiplying the standard rate of 16% to the Capital Base of Rs.68.94
crores in addition to 0.5% on loans approved by the State Govt. Thus, NESCO has proposed
an amount of Rs.11.72 crores towards reasonable return. We are unable to accept this
figure as we have not approved the base figure of Capital Base. Reasonable return
calculated in accordance with Govt. of India, Ministry of Power notification dated 5th
May, 1999 would be Rs.5.71 crores on a Capital Base of Rs.37.51 crores as in Table : 8.
Table : 8
(Rs. in crores)
Source
|
Proposed by NESCO
|
Commissions calculation
1999-00
|
1998-99
|
1999-00
|
Capital Base |
50.03 |
68.94 |
37.51 |
Reasonable return 16% on investment made
after 31.3.99 |
|
|
|
a) 13% on investment made upto 31.3.99 |
|
|
4.88 |
b) 0.5% of loan outstanding as at the end of year 1999-00
|
|
|
0.83 |
Total |
|
11.72 |
5.71 |
|
7.11.7
|
Miscellaneous Receipt
|
7.11.7.1
|
The Licensee has rightly
proposed an amount of Rs.0.17 crores as miscellaneous receipt from interest on investment
for the year 1999-00. This figure excludes meter rent of Rs.3.72 crores for the year
1999-00. |
7.11.8
|
Revenue Requirement,
Reasonable Return and Clear Profit
|
7.11.8.1
|
In the light of above decisions and calculation,
the Commission approves an expenditure of Rs.332.23 for the purpose of revenue requirement
for the year 1999-00 against Rs.409.62 crores proposed by NESCO i.e. a reduction of
Rs.77.39 crores approved by the Commission. At para 7.9 above, special appropriation of
Rs.0.99 crores has been approved on account of contribution to contingency reserve as
proposed by NESCO. Reasonable return has been approved (para 7.11.6) at Rs.5.71 crores
against Rs.11.72 crores proposed by NESCO. The calculation of expenditure for revenue
requirement, reasonable return and clear profit as approved have been reflected in Annexe A, B
& C respectively.
|
7.11.8.2
|
The total revenue requirement of NESCO including
special appropriation and reasonable return has been reduced by Rs.83.40 crores from
Rs.422.33 crores proposed by the Licensee, to Rs.338.93 crores. In spite of the reduced
revenue requirement, there will a deficit for NESCO on the basis of the existing tariff.
|
8.0
|
DETERMINATION
OF TARIFF
|
8.1
|
Taking all aspects of the tariff filing made by
the Licensee and the representation of the objectors, both written and oral, and after
consulting the Commission Advisory Committee, the Commission has determined the tariff and
charges to be realised by the Licensee.The Commission has been taking steps for
rationalisation of tariff i.e. bringing about a uniform rate for all consumer categories
using electricity on the same voltage of supply which is a good measure of the cost of
supply. The same concept of rationalisation is being followed for determination of the
tariff in this order. The Commission considers it reasonable to determine tariff and
charges as in the following paragraphs.
|
8.2
|
Customer charge for consumers with connected
load of 110 KVA or above
|
8.2.1
|
Customer charge is payable by a consumer for the
purpose of its connection to the power system of the licensee and is independent of the
level of consumption of the consumer. It is intended to cover (i) The cost of meter
reading
(ii) Preparation of bills
(iii) Delivery of bills
(iv) Collection of revenue
(v) Maintenance of customer accounts |
8.2.2
|
The Commission has examined
the proposal of the Licensee in regard to customer charge. The existing rate of customer
charge will continue for the following categories of consumers except with regard to
colony consumption for which there shall be no customer charge.
Table : 9
Category |
Voltage of Supply |
Public Water Works |
LT |
General Purpose |
LT |
Large Industry |
LT |
Bulk Supply (Domestic) |
HT |
Irrigation |
HT |
Public Institution |
HT |
Commercial |
HT |
Medium Industry |
HT |
General Purpose |
HT |
Public Water Works |
HT |
Large Industry |
HT |
Power Intensive |
HT |
Mini Steel Plant |
HT |
Railway Traction |
HT |
General Purpose |
EHT |
Large Industry |
EHT |
Railway Traction |
EHT |
Heavy Industry |
EHT |
Power Intensive Industry |
EHT |
Mini Steel Plant |
EHT |
Emergency Supply to CPPs |
EHT |
|
8.3
|
Monthly minimum fixed charge for consumers
with contract demand of less than 110 KVA
|
8.3.1
|
The Licensee has stated that 33% of the power
purchase cost is fixed in nature whereas less than 20% of its revenue is being realised
through fixed charge. The Licensee proposes to remove the anomaly by realising a higher
proportion of fixed cost by increasing the monthly fixed charge.
|
8.3.1.1
|
The usual mode of recovery of fixed charges from
the consumer by a utility is through recorded maximum demand in the meter which reflects
the capacity utilisation by a consumer. At present, consumers with connected load of less
than 110 KVA have been provided with simple energy meters that only records energy
consumption and not the maximum demand. The Supply Regulation provides that the contract
demand for a connected load below 100 KW shall be the same as the connected load.
Therefore connected load forms the basis for levy of fixed charge for these classes of
consumers. Application of the concept of segregation of fixed cost and variable cost is
useful as the consumer should be made aware that a component of the fixed cost is being
incurred for supplying power to him. The Commission, therefore, considers it appropriate
to continue with the existing system of monthly minimum fixed charge in lieu of both
demand charge and customer charge payable by the consumers covered under the two part
tariff.
|
8.3.1.2
|
The monthly minimum fixed
charge is thus a combination of the demand charge and customer charge payable by the
consumers with contract demand of less than 110 KVA. The Commission does not agree with
the proposal of the Licensee for enhancement of the monthly minimum fixed charge and
decides that the existing rate of monthly minimum fixed charge should continue.
Accordingly, the rates applicable to all such customers shall be as given below at Table :
10.
Table : 10
Sl.No
|
Category of Consumers
|
Monthly Minimum Fixed Charge for first KW or part(Rs.)
|
Monthly Fixed Charge for any additional KW or part(Rs.)
|
LT Category
|
1 |
Kutir Jyoti |
30 |
|
2 |
Domestic |
20 |
10 |
3 |
Commercial |
30 |
20 |
4 |
Irrigation |
20 |
10 |
5 |
Street Lighting |
20 |
10 |
6 |
Small Industry |
40 |
30 |
7 |
Medium Industry |
80 |
50 |
8 |
Public Institution |
80 |
50 |
9 |
Public Water Works <100 KW |
80 |
50 |
|
8.4
|
Demand charge for consumer with contract
demand of 110 KVA and above
|
8.4.1
|
The Licensee has proposed an increase in the
demand charge of consumers from Rs.200/KVA/month to Rs.250/KVA/month in respect of certain
categories of consumers availing power supply at LT, HT and EHT, which are listed below. LT
Category
Public Water Works
General Purpose
Large Industry
HT Category
General Purpose
Public Water Works
Large Industry
Power Intensive Industry
Mini Steel Plant
Railway Traction
EHT Category
General Purpose
Large Industry
Railway Traction
Heavy Industry
Power Intensive Industry
Mini Steel Plant |
8.4.2
|
In this connection, the
Commission also examined the prevailing demand charge for such categories of consumers
elsewhere in the country. An increase of demand charge may force the large consumers to
set up their own captive power plants, which is detrimental to both the interests of the
Licensee as well as the small consumers. The Commission decides that the rate of demand
charge for consumers with contract demand of 110 KVA and above shall be Rs.200/KVA/month. |
8.4.3
|
The Commission further directs that the demand
charge shall be payable by these consumers on the basis of actual meter reading subject to
a minimum of 80% of the contract demand to ensure recovery of a part of the fixed cost of
the installed capacity. Where the actual recorded maximum demand is less than 80% of the
contract demand, the consumer is liable to pay at 80% of the contract demand or the
actually recorded maximum demand whichever is higher. The method of billing of demand
charge in case of consumers without a meter or with a defective meter shall be in
accordance with the procedure prescribed in OERC (Conditions of Supply) Code, 1998.
|
8.4.4
|
Categories of consumers other
than those listed in para 8.4.1 like domestic, irrigation, public institution, commercial
and medium industry but availing power supply at HT are presently liable to pay the demand
charge as indicated below :-
|
(Rs./KW/Rs./KVA)
|
Domestic
|
10
|
Irrigation
|
30
|
Public Institution
|
50
|
Commercial
|
50
|
Medium Industry
|
50
|
|
8.4.5
|
The Licensee has proposed increase of demand
charge in respect of the above categories of consumers. The Commission has carefully
considered the proposal of the Licensee and has decided not to raise the demand charge
after considering the comparable charges in other States and internal relativity of the
impact of tariff among the consumers. Accordingly, bills should be raised for these
categories of consumers on the basis of their contract demand/connected load calculated in
KW
|
8.5
|
Energy Charge
|
8.5.1
|
Energy charge paid by the consumer is directly
proportional to the quantum of actual consumption. The Commission, in keeping with its aim
of rationalisation of tariff structure by progressive introduction of a cost-based tariff,
has related the energy charge at different voltage levels to reflect the cost of supply.
While determining energy charge, the principle of a higher rate for supply at a low
voltage and a gradually reduced rate as the voltage level goes up has been adopted. The
following tariff structure has been adopted for all loads of 110 KVA and above.
Voltage of supply
|
Demand Charge
|
Energy Charge
|
LT
|
Rs.200/- per KVA
|
280 paise/unit
|
HT
|
Rs.200/- per KVA
|
270 paise/unit
|
EHT
|
Rs.200/- per KVA
|
260 paise/unit
|
|
8.5.2
|
HT Supply for Domestic (Bulk) and Irrigation
: With a view to avoid steep rise in tariff in respect of domestic (bulk supply) and
irrigation availing power at HT, the energy charge is fixed at @ 200 paise/unit and @ 80
paise/unit respectively.
|
8.5.3
|
Industrial Colony Consumption : The
Commission further directs that the units consumed for the colony shall be separately
metered and the total consumption shall be deducted from the main meter reading and billed
at the flat rate of 200 paise/unit. Energy consumed in colony in excess of 10% of the
total consumption shall be billed at energy charges applicable to the appropriate class of
industry.
|
8.5.4
|
Incentive Tariff for HT and EHT Category of
Consumers
|
8.5.4.1
|
The Licensee has proposed an
incentive tariff for HT and EHT consumers i.e. giving a discount of 10% for consumption
beyond a load factor of 60% except for the power intensive industries which are classified
as export-oriented industries. In the rationalisation of tariff structure, the Commission
is entitled to differentiate the consumers on the basis of consumers load factor or
power factor and the consumers total consumption of energy during any specified
period. The nature and purpose of use becomes less important if a consumer is able to
maintain a high load factor and helps the licensee through better utilisation of the
system. Since the demand charge is same for all HT & EHT categories of consumers, a
higher consumption means a higher plant utilisation and results in a reduced fixed
cost/unit. The Commission is also conscious of the fact that the revenue requirement of
the licensee should reasonably be met while designing a tariff structure that incentivises
the consumers for a higher consumption of the Licensees purchased power and
dissuades them from switching over to captive generation. With the above objective, the
Commission decides as follows:- |
8.5.4.2
|
HT and EHT industries who do
not reduce their contract demand during the next three years will be allowed the benefit
of incentive tariff in the form of relief in energy charges if the load factor in a month
exceeds 50% of the contract demand. |
8.5.4.3
|
All consumption in excess of 50% load factor
shall be payable @ 180 paise/unit for consumers availing power at EHT.
|
8.5.4.4
|
All consumption in excess of
50% load factor shall be payable @ 200 paise/unit for consumers availing power factor at
HT. |
8.6
|
Special Tariff for Industries with
Contract Demand of 100 MVA and above
|
8.6.1
|
The Commission also considers
that industries with a load of 100 MVA and above and load factor of 80% should qualify for
a special tariff. The special tariff should have no explicit demand charge and would have
a consolidated energy charge with a similar back to back arrangement with the bulk
supplies. This has been suggested in order to give an encouraging signal to the
prospective large consumers and to ensure that such large industries do not set up captive
power plants but avail power supply from the Licensee. The Commission has therefore,
approved a rate of 200 paise/unit for consumption by industries with a contract demand of
100 MVA and above and maintaining a guaranteed monthly load factor of 80%. These consumers
will not pay a monthly demand charge and shall pay only a consolidated energy charge. They
will have to restrict their maximum demand within the contracted capacity. In case the
maximum demand exceeds the contracted capacity, demand charge as applicable to the
relevant consumer category will be payable only on the maximum demand in excess of the
contract demand. |
8.7
|
Special Agreement with
Power Intensive Industries claiming relief as EOUs |
8.7.1
|
The Commission has also
considered the proposal of NESCO for a special agreement with power intensive industries
claiming relief under EOU category. NESCO has suggested that while tariff applicable to
the relevant consumer category may apply to these industries during peak hours, energy
charge may be reduced during off-peak hours. The Commission recognises differentiation of
the consumers only on the basis of the consumers load factor or power factor and the
consumers total consumption of energy during any specified period of time. Accordingly the
Commission has decided to grant incentive to all the HT and EHT consumers with high load
factor by way of reduced rate of energy charges as described in para 8.5.4.2 The power
intensive industries claiming relief as export oriented units can avail of this incentive
tariff if they are eligible for it. Hence any special dispensation for EOUs is not
considered necessary. The Commission, therefore, does not approve of any special agreement
with retrospective effect. Further, we have to observe that OERC (Conditions of Supply)
Code, 1998 provides for a special agreement only in case a consumer cannot be classified
in any of the defined categories of consumers. It is the Commissions considered view
that this is not the case here. |
8.8
|
Tariff for consumers with connected load less
than 110 KVA
|
8.8.1
|
Domestic : It is
observed that 84% of the electricity consumers including Kutir Jyoti consumers (life-line
rates) in Orissa belong to the domestic category. The Commission has examined the tariff
for the Domestic category with particular reference to the Licensees proposal. In
consonance with the policy to gradually decrease subsidy for all categories of consumers
and yet facilitate use of electricity by small consumers, the Commission has decided to
retain the slab system. The Commission has in another step to protect small consumers
decided that consumption upto and including 100 units/month will be exempt from any tariff
rise. Keeping this in view, energy charge for supply at 230/400 V shall be as under :-
(i) Kutir Jyoti Consumers-
|
Rs.30.00 per month.
|
(ii) In case of other Domestic consumers, on the total monthly
consumption :-
First 100 Units -
|
120 paise per unit
|
Next 100 units -
|
190 paise per unit
|
Balance units of consumption -
|
280 paise per unit
|
|
8.8.1.1
|
The Commission has decided to continue the
monthly minimum fixed charge at the rate of Rs.20 for the first KW of contract load or
part thereof. This charge will be enhanced at the rate of Rs.10 per KW per month for each
additional KW or part thereof above the first KW of contract load.
|
8.8.1.2
|
In case of unmetered supply or defective meter,
the energy consumption shall be assessed and billed using a load factor of 20% on the
contract demand. For this purpose, the connected load of less than 0.5 KW shall be treated
as 0.5 KW.
|
8.8.1.3
|
For supply at 11/33 KV the energy charge shall
be payable at the rate of 200 paise/unit. The monthly demand charge for domestic consumers
availing power supply at HT shall be at the rate of Rs.10 per Kw per month.
|
8.8.1.4
|
HT customers will pay a customer service charge
of Rs.250 per customer per month.
|
8.8.1.5
|
The practice of prompt payment rebate of 10
paise/unit shall continue.
|
8.8.2
|
Commercial : The Commission has examined
the existing tariff structure of commercial category and has decided the following :-
|
8.8.2.1
|
For the total monthly consumption :-
First 100 units -
|
280 paise/unit
|
Next 200 units -
|
370 paise/unit
|
Balance units -
|
410 paise/unit
|
|
8.8.2.2
|
For supply at HT, the energy charge shall be 270
paise/unit.
|
8.8.2.3
|
In case of unmetered supply or defective meter
energy consumption shall be assessed and billed using the load factor of 30% on the
contract demand. For this purpose the connected load of less than 0.5 KW shall be treated
as 0.5 KW. The present practice of prompt payment rebate shall continue.
|
8.8.2.4
|
Monthly minimum fixed charge of Rs.30 per month
for the first KW of contract demand per month shall be payable. This charge will go up at
the rate of Rs.20/- per month for each KW of contract demand or part there of over the
first KW of contract load.
|
8.8.3
|
Small Industry : In this category energy
charge will be 280 paise/unit in place of the existing rate of 245 paise/unit. The load
factor shall continue to be calculated @ 15% on the connected load in respect of these
consumers with defective meter and unmetered supplies for the purpose of assessment of
consumption and billing.
|
8.8.4
|
Irrigation : Considering the wide-spread
damage caused to agriculture by two cyclones in the coastal districts of Orissa, the
Commission has decided to exempt Irrigation category of consumers availing power at LT
from any tariff rise. Consumers in the Irrigation category availing power supply at HT
will also be exempt from any increase in the present energy charge. In respect of
Irrigation consumers for the months of June to October, a load factor of 8% and for the
month of November to May, a load factor 15% shall be considered for assessment of
consumption and billing.
|
8.8.5
|
The rate of tariff as determined above is
reflected in Annex-D.
|
8.9
|
Other Charges : The
Commission also authorises levy of other charges as given below :- |
8.91
|
Demand Charge
|
8.9.1.1
|
The monthly demand charge will be calculated on
recorded/evaluated maximum demand or 80% of contract demand whichever is higher.
|
8.9.1.2
|
Penalty for overdrawal of
power above the contract demand : OERC (Condition of Supply) Code, 1998 provides that
consumers covered under two-part tariff shall pay a penalty in case actual maximum demand
exceeds the contract demand. The Commission is of the opinion that flattening of the load
curve is absolutely necessary for better utilisation of the system capacity. Consumers
exceeding the contract demand outside the peak hours actually help the system by
flattening of the load curve in a surplus generation situation prevailing now. The
Commission, therefore, decides that there will be no penalty for overdrawal outside the
peak hours upto 120% of the contract demand. This facility is now available to industries
drawing power at EHT with time of day (TOD) metering. The Commission has now decided to
extend this benefit to HT industries provided with TOD meters. The existing rate of
penalty will continue for overdrawal during peak hours. For this purpose, the peak
hours is defined as 0700 hours to 1000 hours and 1800 hours to 2200 hours. |
8.9.2
|
Metering on LT side of Consumers Transformer
: Transformer loss computed as given below to be added to the consumption as per
meter reading. Energy loss = 730 X KVA reading of the transformer/100.
Loss in demand = 1% of the reading of the transformer (for two part
tariff) |
8.9.3
|
Incentive for Timely
Payment : The Commission has decided to introduce incentive for prompt payment by
grant of a rebate @1% for payments made within a period of two weeks from the due date of
payment indicated in the bill. |
8.9.4
|
Delayed Payment Surcharge
: The Commission has decided that there shall be no change in the existing practice of
levying delayed payment surcharge at the rate of 2% per month which will be prorated for
the period of delay counted from the due date of payment indicated on the bill in respect
of the following categories of consumers :-
i) Large Industries
ii) Medium Industries
iii) Public Water Works
iv) Railway Traction
v) Street lighting
vi) Power intensive Industries
vii) Heavy Industries
viii) General Purpose Supply
ix) Public Institutions
x)Mini Steel Plants
xi) Emergency supply to CPP |
8.9.5
|
Incentive for improvement in power factor :
The Commission considers it desirable to introduce an incentive to encourage improvement
in power factor.
|
8.9.5.1
|
Incentive for maintenance of high power factor
shall be given as a percentage of the monthly demand charge and energy charge and shall be
applicable to the categories of consumers who are liable to pay power factor penalty. The
rate of this incentive will be 0.5% for every 1% rise above 90% upto and including 100% on
the monthly demand charge and energy charge.
|
8.9.6
|
Power Factor Penalty :
The Commission also orders for continuance of the power factor penalty as a percentage of
monthly demand charge and energy charge as given below to the following categories of
consumers :-
i) Large Industries
ii) Public Water Works (110 KVA and above)
iii) Railway Traction
iv) Power Intensive Industries
v) Heavy Industries
vi) General Purpose Supply
vii) Public Institutions (110 KVA and above)
viii) Mini Steel Plants
ix) Emergency supply to CPP
Rate of Power Factor Penalty :-
i) 0.5 for every 1% fall from 90% upto and including 60% plus
ii) 1% for every 1% fall below 60% upto and including 30% plus
iii) 2% for every 1% fall below 30% |
8.9.7
|
Adoption of load factor
for consumers with defective meter and without meter : Taking into account the
metering programme and other measures for tackling commercial/non-technical loss, the
Commission orders for continuance of the existing method of load factor billing subject to
review from time to time. If at any time the Commission comes to the conclusion that
effective loss reduction measures are not being taken up by the Licensee the Commission
will have no option but to revise the load factor downwards. |
8.9.7.1
|
The present practice of
submitting information on the status of metering and on measures taken for eradication of
unauthorised tapping from the distribution mains has to continue. The Licensee has to
submit the information at the end of each quarter for information and review of the
Commission. |
8.9.8
|
Customer Charge : As indicated in
paragraph 8.2 above and also Annex-D there shall
be no change in customer charge except with regard to industrial colony consumption for
which the customer charge is abolished.
|
8.9.9
|
Re-connection Charge :
The existing rates of reconnection charge as below shall continue :-
Single Phase Domestic Consumer
|
Rs.30/-
|
Single Phase other consumer
|
Rs.50/-
|
3 Phase line
|
Rs.100/-
|
HT & EHT line
|
Rs.500/-
|
|
8.9.10
|
Rounding off a consumer billed amount to
nearest rupee : The Commission directs for rounding off of the electricity bills to
the nearest rupees and at the same time direct that the money actually collected should be
receipted and accounted for.
|
8.9.11
|
Temporary Connection Charges : The tariff
for the period of temporary connection shall be at the rate applicable to the relevant
consumer category.
|
8.9.12
|
New Connection Charges for LT : For
prospective small consumers requiring new connections upto and including 3 KW load, there
will be a flat charge of Rs.500/-. The existing practice of preparation of estimate and
payment of charge based on the estimated amount shall continue without any change for
connections above 3 KW load.
|
8.9.13
|
Fuel Surcharge Adjustment Formula : The
Commission has already prescribed a fuel surcharge adjustment formula for the distribution
licensee which shall continue to be valid.
|
8.9.14
|
Meter Rent : Monthly meter rent as per the existing rate shall be charged
from the consumers to whom meter has been supplied by the licensee except for the three
phase static Kw meters. Rent for three phase static Kw meters is fixed at Rs.100/month
from the effective date of this tariff. Thus the scale of meter rent applicable to various
classes of consumers is given below :-
Meter
|
Rent in Rupees
|
-----------------------------------------------------------------
|
1.
|
Single phase electro-magnetic Kwh meter
|
15/-
|
2.
|
Three phase electro-magnetic Kwh meter
|
30/-
|
3.
|
Three phase electro-magnetic trivector meter
|
800/-
|
4.
|
Trivector meter for Railway Traction
|
800/-
|
5.
|
Single phase Static Kwh meter
|
35/-
|
6.
|
Three Phase Static Kwh meter
|
100/-
|
7.
|
Three phase Static Trivector meter
|
800/-
|
8.
|
Three phase Static Bivector meter
|
800/-
|
|
8.10
|
The Commission
has approved NESCOs revenue requirement for the year 1999-00 as Rs.338.93 crores.
The expected revenue from charges approved by the Commission over a 12 months period is
estimated as Rs.323.96 crores. The Licensee will get Rs.3.89 crores on account of
miscellaneous receipts and meter rent over a 12 months period. The revenue requirement and
expected revenue of NESCO, approved by the Commission for the FY 1999-00, are given below
:-
|
(Rs. in crores)
|
Total Revenue Requirement
|
338.93
|
Less Miscellaneous Revenue
|
3.89
|
Net Revenue Requirement
|
335.04
|
Expected Revenue
|
323.96
|
Deficit
|
11.08
|
|
9.0
|
In
the light of our findings, the Commission orders as follows with reference to the prayers
of the applicant :-
-
While the Commission does not approve the amendments suggested by NESCO for tariffs and
charges it directs that the Licensee implements the tariffs and charges as determined by
the Commission in this Order effective from 1st February, 2000.
-
The revenue requirement for 1999-00 as projected by the Licensee does not meet with the
approval of the Commission. The Licensee is directed to adopt the revenue requirement
figures for 1999-00 as calculated by the Commission.
-
The proposal for cash flow from WESCO to NESCO and SOUTHCO does not meet with the
approval of the Commission
-
The tariff proceeding is not the appropriate occasion for decision on the proposal for
moratorium on addition of captive generation.
The application of M/s. NESCO is disposed of accordingly.
-Sd-
|
-Sd- |
D.K. Roy |
S.C. Mahalik |
Member
|
Chairman
|
|