CASE NO. 4 of 1997
T. R. - 97 - 007
14.02.97 A letter dated 05.02.97 from
Orissa Consumar's Association has been placed before the commission.
The said letter is with reference to a Public Notice issued by the OERC
and published in newspapers on 2nd February ,1997 inviting objection to the proposal for
tariff for the year 1997-98 filed by Gridco before the commission. The Public Notice has
called for objections to be filed by 18.02.97 in person or through registered post after
perusing the details of the tariff proposal in the office of Gridco at Bhubaneswar.
The Commission has noted that the language used and the insinuation
made in the letter are not proper. However this aspect of the letter is being ignored for
the purpose of order as it appears that the applicant has not briefed himself with the
laws and procedure with regard to the composition and functioning of the Orissa
Electricity Regulatory Commission. The commission has been vasted with the powers of a
civil court under the code of civil procedure 1908 with regard to enquiry or proceedings
under the Orissa Electricity Reform Act, 1995. Hence the Commission
is obliged by law to take up procedure accordingly.
It is neither prescribed by law nor it is feasible for the Commission
dealing with the matter of public utility to issue notices either individually or to
representatives of interest groups and therefore in accordance with the prescribed
procedure, a public notice has been given with reasonable time to enable genuinely
interested parties to take note of the details and to file objections. The procedure
adopted with regard to public utility matters is new and possibly therefore, there is some
misapprehension and inadequate appreciation of the legal issues as well as procedure
adopted. the commission is bound by the statute and regulations to proceed in the time
bound manner so as to ensure that the proceeding for the electricity tariff for the year
1997-98 is completed and notified before the end of the financial year. Keeping this in
view, the Commission has carefully charted out its proceedings making provision for
resonable opportunity to be given to the interest groups and ensuring open hearing for the
sake of transparency in the decision making .The Commission has also noted that a number
of genuinely interested groups and individual have already collected information and have
submitted/are submitting their objections indicating their objection and wishing to be
heard in person on the appointed day of hearing,. The commission has carefully considered
all aspects and does not find it possible to grant any time in the matter.
(D.K.ROY)
( A.R. MOHANTY )
Case No.4 of 1997
T. R.-97-007
Order No. 007 dated 21st February, 1997
21.02.97 At the initial stage of hearing today with
reference to the tariff application, preliminary objections were raised by three objectors
who expressed the desire that the formal order of the Commission on these issues should be
delivered before the Commission proceeds with the hearing on the merits of the tariff
application. The Commission heard Mr. K.N. Jena, speaking on behalf of Orissa Consumers
Association, Sri L. Pangari representative of IPI Steel Limited and Sri Rajat Kumar Rath,
Advocate representing Orissa Sponge Iron Ltd. These objections had also been indicated in
the written submissions submitted in response to the public notice of the hearing. These
have, therefore, received the attention of the Commission. Further, the arguments and
objections advanced before us have been heard. These have been carefully considered. The
issues raised and orders of the Commission on them are as follows.
2. The first objection is that Commission has not been
properly constituted. In support of this objection, it was stated that the Commission is
presently composed of two members and is without a Chairman and therefore, it is not a
full-fledged Commission. It was argued that in the absence of the Chairman, the Commission
was not entitled to conduct its proceedings.
The Commission is unable to find any validity in this objection in view
of clear and specific provisions of the law at sub-sections (4) and (5) of Section 3
which are as under:
Sub-section (4) of Section 3: When the Chairman of the Commission is
unable to discharge the functions owing to absence, illness or any other cause, the senior
most member of the Commission shall discharge the functions of the Chairman, until the day
on which the Chairman assumes the charge of his functions.
Sub-section (5) of Section 3 : No act or proceedings of the Commission
shall be invalid by reason only of the existence of any vacancy among its members or any
defect in the constitution thereof.
It is also noted by the Commission that sub-section (4) of Section 9 stipulates that quorum
for the meeting of the Commission shall be two. In view of these provisions, the
Commission considers that there is no bar for holding proceedings of the Commission with
two members including the senior member Sri A.R. Mohanty acting as Chairman and
discharging the functions as the Chairman under sub-sections (3) and (4) of Section 3 of
the OER Act, 1995.
3. The second objection was that sufficient notice has
not been given to the affected parties and therefore, the proceedings should not be
continued. In this connection, it was argued that giving only seven days time to peruse
the papers and making it obligatory to come to Gridco's office for perusal of the
application was a hindrance for the affected parties to get sufficient notice. It was also
argued that all papers, documents, statistics and references in respect of the tariff
proposal were not made available and therefore the affected parties did not get sufficient
opportunity. Two weeks time for submitting objections was also stated to be not
sufficient.
The Commission has carefully considered all aspects regarding granting
of sufficient opportunity for all the affected parties. The Commission is bound by the
statute to confirm to certain time limit. In this particular tariff proceeding for the
Financial Year 1997-98 all the legal requirements, proper scrutiny and analysis have to be
completed and decision of the Commission has to be conveyed to the Gridco well in time, so
as to enable it to give a public notice of tariff seven days before the end of current
Financial Year. Keeping these statutory requirements and other activities of the
Commission in view, total time of sixteen days allowed for perusal and submission of the
Objection is considered adequate.
4. The third preliminary objection is with regard to
infirmity of the proceeding due to non-notification of the Regulation for conduct of
proceeding and for laying down the parameters for tariff proposal. In this connection, it
was claimed that the Commission has not discharged its function in framing Regulations for
conduct of its proceedings and discharge of its functions as required by sub-section (2) of Section 9 read with Section 54 of the OER Act, 1995.
It was also claimed that the tariff proceeding is illegal because the Commission has not
yet prescribed the terms and conditions for determination of the licensee's revenues and
tariff as required under sub-section (2) of Section
26 of the OER Act, 1995.
The Commission finds no validity in this objection in view of the fact
that the Orissa Electricity Regulatory Commission (Conduct of
Business) Regulation, 1996 has been framed, notified on 28th November, 1996 and has
been published in the Orissa Gazette No. 1413 dated December 30, 1996. The said Regulation
includes the methodology of tariff proposal.
5. The next objection relates to the locus standi of
Gridco and the validity of its application for tariff. On the basis of sub-section (4) of Section 14 of the OER Act, 1995, the Gridco had been issued a provisional license by the
Govt. of Orissa vide letter dated 31.03.96. For all purposes, therefore,
Gridco is a licensee under the OER Act, 1995. Further, the
Commission observes that it is not only that Gridco has to be considered a licensee but,
Gridco is bound by law under Section 26 (4) to
submit details of calculation for the ensuing Financial Year regarding revenue and tariff.
This provision of the law enables Gridco to submit the tariff proposal for 1997-98 and
obliges the Commission to consider the same for taking its decision.
6. Another objection raised was that Gridco is not
entitled to submit proposal of tariff within one year.
The Commission has noted that the present tariff proposal relates to Financial Year
1997-98 and therefore, the proposal is in order. The provisions of law refer to Financial
Year and does not refer to a period of twelve months.
7. Objections were raised with regard to consultations
with the Commission Advisory Committee on tariff matters.
The Commission Advisory Committee has been duly constituted as required
under Section 32 of the OER Act,
1995 and the Commission has already initiated the process of consultation with the
Commission Advisory Committee.
8. Another issue raised by the objectors is with
regard to the status of the Commission. It was stated that the Commission was a Court in
view of the provisions of OER Act, 1995 and therefore the Commission
has to observe all the formalities and obliged to grant unlimited time to objectors for
presenting the facts before it. In this connection, it was also claimed that copy of
Gridco's application and all details should have been served on the parties and in this
view of procedure, the objector could not be asked to peruse files and collect the
information from the GRIDCO.
The Commission cannot agree with the above interpretation of the law.
Under Section 10 (1) of the Act,
the Commission has been given powers of a Civil Court under the code of Civil Procedure,
1908 only with regard to six specified areas. Similarly under the provision of Section 52, the proceeding of the Commission shall be
deemed to be judicial proceeding only for specified provisions of the Code of Criminal
Procedure. The Commission has no doubt in its mind that it is a quasi-judicial body which
is obliged to observe the procedure and formalities of legal procedure so as to the afford
reasonable opportunity and to make final finding of facts and at the same time it has the
authority to lay down its own procedure so as to avoid needless legal trappings. The
legislature in its wisdom has constituted a Commission which is designed to have certain
trapping of the Court and yet the flexibility of a quasi-judicial body so that it can get
into all relevant issues and take a decision on legal, technical and accounting issues in
an objective manner without delay but keeping in mind the interest of the Consumers, the
Electricity Industry and the overall interest of the State. The Commission has accordingly
prescribed its own procedure for which it has been authorised by the Act to do so. The
essential distinction between a Civil Court as a part of regular hierarchy of judiciary
and quasi-judicial tribunal entrusted with adjudicatory function outside that hierarchy
emphasised in a number of pronouncement of the apex court has not to be lost sight of.
9. Objection has been raised with regard to adequacy
of information supplied. It has been claimed by learned objector Sri K.N. Jena that the
proceeding should not be continued without supplying the documents listed by him.
The Commission has gone through the elaborate list and finds that it is
neither practicable nor essential for GRIDCO to make all the listed documents available to
the Objectors. The Commission will go through all relevant documents and accounts as
considered necessary. The Commission is aware of its responsibility in this regard. The
objection cannot be admitted.
10. The Commission, therefore, does not admit any of
the above preliminary objections raised by the objectors the Commission orders that the
proceeding should continue.
Typed to my dictation and corrected by me.
(D.K. ROY)
MEMBER
I agree
(A.R.MOHANTY)
MEMBER
Back to "Orders" |