Case
No.8 of 1999
|
Present : 1)
Shri D.K. Roy, Chairman
2) Shri H.S. Sahu, Member
|
In the matter of |
:
|
Transmission System Planning
|
M/s Grid Corporation of Orissa Ltd.
|
|
Petitioner
|
|
- Vrs. -
|
|
M/s OHPC Ltd. and others.
|
|
Respondents
|
For Petitioner
|
:
|
Mr. S.P. Ghosh, Director (Comm.)
|
For Respondents
|
:
|
-
Mr. A.L. Rao, Director (O), OHPC Ltd.
-
Mr. N.D. Chawla, M.D., WESCO
-
Mr. M.N. Joglekar, M.D., NESCO
-
Mr. P.K. Patnaik, Dy. Manager (Power), OPGC.
-
Mr. P.K. Mohapatra, Sr. Manager, Ferro Chrome Plant
|
Date of argument
|
:
|
13.10.2000
|
Date of order
|
:
|
17.02.2001
|
|
PRELIMINARY:
|
1.
|
The issue arose out of condition
20 of the Orissa Transmission & Bulk Supply License which requires the licensee i.e.
Grid Corporation of Orissa Limited (Thereinafter to be referred as GRIDCO) to
|
a) |
Prepare and submit every year to
the Commission for approval long term demand for power or load forecasts for the power
system in Orissa for succeeding 10 years and in particular provide to the Commission
details of the demand forecasts and the data, methodology and assumptions on which those
forecasts are based; and
|
b) |
Prepare and submit to the
Commission at such intervals as decided by the Commission for approval of its long term
plan for power procurement and transmission expansion so as to meet load forecast as in
(a) above.
|
2.
|
GRIDCO failed to submit its long
term transmission system planning in response to Commissions directions contained in
letter No.1352 dated 30.05.1997.
|
3.
|
The Commission decided to take up
the matter of transmission system planning through a proceeding and Case No.8/1999 was
initiated requiring GRIDCO to appear before the Commission on 30.04.1999 and make a
comprehensive presentation covering all aspects of transmission system planning. No
material hearing of the case could be taken up as GRIDCO repeatedly failed to present
their case on some plea or other. The Commission during hearing of the case on 29.01.2000
ordered that GRIDCO may be transposed as petitioner and all the four Distribution
Companies, industries having Captive Power Plants and Generating Companies should be
impleaded as opposite parties/respondents in the case. Notices were accordingly issued to
the concerned parties to appear before the Commission on 25.02.2000.
|
4.
|
GRIDCO, in the meanwhile, had
submitted their first Transmission Planning Report on 09.07.1999 and (Revised)
Transmission Planning Report on 07.01.2000. These planning reports relied on load forecast
data submitted to the Commission during 1996 which were not updated till submission of
these reports. Loads projected three years before would no longer hold good. Transmission
system planning on the basis of these reports would result in a gross under utilisation of
capital investment and capacities of the system. These reports were, therefore not
considered for approval as such. The Commission called for fresh data on long term demand
for power to be submitted by the Distribution Companies for proper assessment of the
situation.
|
5.
|
In the course of hearings
conducted on 25.02.2000, 09.05.2000, 16.05.2000, 14.07.2000 and subsequent mutual
discussions between GRIDCO AND Distribution Companies under the auspices of the office of
Commission, the Distribution Companies were urged to submit the demand forecast in respect
of their areas of supply. GRIDCO in their submission on 04.09.2000 confirmed receipt of
load forecast reports from all the four distribution companies. Notices were issued to all
parties to appear before the Commission on 13.10.2000.
|
O R D E R
:-
|
6.
|
The Commission heard the
petitioner on 13.10.2000 presenting the load forecast report for the Orissa Power System
for the year 2000 to year 2010. Replies filed by such of the respondents in this case,
were taken into record and are dealt with separately in subsequent paragraphs of the
order. The petitioner filed later on 24.10.2000, Load Flow Study 2005
Condition in connection with transmission planning, which was taken into record for
further analysis and order.
|
7.
|
The forecasts of demand as
prepared by the Distribution Companies and incorporated in their report by GRIDCO have not
met any or some of the following requirements of license condition and Distribution System
Planning and Security Standards.
-
Methodology and assumptions on which these forecasts are
based
-
Forecasts should take into account consumption pattern of
consumers
-
Specific references of contract loads of 5 MW and above.
|
8.
|
There is no indication in the load
forecasts to bring down substantially the existing level of transmission and distribution
losses, which are reported to be as high as 46 %.
|
9.
|
Reduction of transmission and
distribution losses which is a major factor determining the quantum of power to be
purchased and ultimately the economics of power supply have not been addressed adequately
and satisfactorily by the licensees. It has been stated that during the base year
(1999-00) 45% of the losses are due to technical reasons while 55% of the losses are due
to non-technical reasons. Substantial reduction in overall losses would result if
effective time bound measures are initiated to minimize the non-technical losses which are
mostly due to pilferage, defective meters and wrong billing. The Commission is of the
view, that it should be possible to bring down the non-technical losses substantially by
taking stringent administrative measures for eliminating unauthorised connections,
launching massive drive for replacement of defective meters and such other measures
required to remove difference in meter reading and billing. It is expected that in future
load forecasts, sufficient care should be exercised by the licensees to address to this
problem. Similarly the technical losses should also be brought down to a reasonable level
by upgrading and optimising the distribution system as required.
|
10.
|
While furnishing their forecasts
of peak demand and energy demand it is imperative that the Distribution Companies shall
take into account the impact of demand side management measures, on the net demand of
consumers.
|
11.
|
The overall annual average
percentage energy and demand growth in the areas of supply of the licenses in the period
from year 2000 to 2010 computed from GRIDCOs submission dt.13.10.2000 has been
estimated to vary from 2.6% to 7.3%. The rationale behind such varying rates of growth in
contiguous regions has not been explained. The licensees would be well advised to work out
load forecasts assuming low, high and probable growth rates on the basis of characteristic
consumption pattern of consumers in different categories in the different scenarios and
come out with a most probable load forecast.
|
12.
|
The load forecasts should give due
weightage to the industrial loads which constitute a major portion of the total demand.
Procedure of dealing with applications of industrial consumers with contract demand of 5
MW and above is given in Distribution (Conditions of Supply) Code and
Distribution System Planning and Security Standards. It would be erroneous to
prepare a load forecast ignoring major industrial loads in the area that might materialise
in the next five years. It would therefore, be incumbent on the licensees to collect data
and information regarding probable setting up of industries with loads of 5MW and above in
their respective areas by contacting Government Department (Industries Deptt., IPICOL,
IDCO, etc), Railways, Coal Fields, Mining, Financial institutions, Banks, Prospective
industrial consumers, etc, for including such loads in their load forecasts.
|
13.
|
We find that GRIDCO have not
furnished historical data of aggregate energy demand and peak demand of the Orissa Power
System. This would have provided a better insight to the load factor of the system,
diversity factor of zonal demand and facilitated projection of load factor over the years.
It is expected that this may be taken into account by GRIDCO in their future load
forecasts.
|
14.
|
GRIDCO have submitted a load flow
study for 2005 condition vide their letter No.2715 dated 24.10.2000, which the Commission
wishes to comment upon. Load flow study is one of the studies which the licensee is
required to conduct for the transmission system planning. The other studies are short
circuit study and transient stability study. At the outset, the Commission wishes to place
on record that the load flow study, as submitted, is incomplete, as the study is not made
under both the High Hydro and High Thermal Conditions and under Single Outage conditions,
as provided in Transmission Planning and Security Standards. Without complete power
system studies, the adequacy of the proposed transmission network both under steady state
(normal), steady state (outage) and transient state cannot be judged.
|
15.
|
The study reveals that many of the
proposed lines are under utilised (they carry 10% or even less of their rated capacity).
This phenomenon has apparently been the consequence of considering all the lines that were
envisaged for implementation to match the earlier load forecasts of GRIDCO in 1996. A
comparative study of 1996 load forecasts and present load forecasts reveals that while the
earlier load forecast projected a load of 3938 MW in the year 2005 the present projection
is only 2405 MW. Evidently the licensee have not applied their mind to this situation.
This situation would have been averted, had the licensee been reviewing the long term load
forecasts every year as required under license conditions. This calls for an immediate
review of the implementation programme of the various ongoing transmission schemes by
GRIDCO to explore possibility of deferring/dropping such of the schemes which cannot be
technically and economically justified. Views of Central Electricity Authority in this
regard may be obtained.
|
16.
|
VAR generation to the extent of
259.86 MVAR has been indicated in the Load Flow Study 2005 condition through installation
of shunt capacitors at various places. GRIDCO may submit a report for information of the
Commission on the status of installation of capacitors.
|
17.
|
Due to transport of bulk power
between different regions through inter-state lines, effect of outage of such lines on the
grid assumes importance. In this context, power system studies should take into account
outage and fault conditions on the 400 KV AC and HVDC inter-state lines (both existing and
upcoming).
|
18.
|
The Commission finds that some of
the objections filed before the Commission in this case have not been addressed to by M/s
GRIDCO. These are referred to below and GRIDCO directed to consider the objectors
requirement, in their future planning under intimation to the Commission.
-
Letter No.OHPC/329/2000/7164 dated 11.5.2000 from Director
(Operation), OHPC, Bhubaneswar.
-
Letter No.IR/AAP/PROJ/2905 dated 8.5.2000 from M/s Aditya
Aluminium, Bhubaneswar.
-
Letter No.FCP/CPP/ELE/32/2040 dated 8.6.2000 from G.M.,
Ferro Chrome Plant, IDCO, Bhubaneswar.
- Action by GRIDCO
-
With regard to item 18 (i)
OHPC had argued for
-
Completion of at least one no. of 220 KV DC line for Upper
Indravati to Theruvali before August 2000 to evacuate power from UIHEP as 3rd
unit is scheduled to be commissioned by the end of August 2000 . Further, augmentation of
Theruvali sub-station and beyond is also necessary.
-
Strengthening the 132 KV Chiplima Bargarh Transmission line
by making necessary changes in the equipment like CTS etc. at both ends since it is
already over loaded.
-
Providing a 220 KV s/s at Burla and shifting all 132 KV, 66
KV and 11 KV feeders from P/H switch yard to this sub-station.
GRIDCO, responding to above arguments of OHPC has submitted that -
220 KV D.C. line from UHIEP to Theruvali-
Presently, to the extent of 500 MW power from Indravati can be evacuated through the 400
KV PGCIL line . 220 KV DC line from Indravati to Theruvali would be completed by March
2001 in ADB scheme. The other 220 kv dc line under World Bank Scheme is scheduled to be
completed by September 2002. GRIDCO has not commented any thing regarding augumention of
Theruvali s/s and at its down stream strengthening for effective evacuation of UIHEP
power. Commission directs GRIDCO to examine this aspect and implement the needful change.
132 KV Bargarh-Chiplima line-
The deficiencies observed while thermo vision scanning of the 132 KV Bargarh-Chiplima line
at Chiplima switch yard was communicated by GRIDCO to Manager, Operation, Chiplima P/H and
E.E., E&MR, GRIDCO on 15.03.2000 for rectification. It was further reminded on
12.05.2000. 132 KV CT of higher capacity at Bargarh switch yard for Chiplima feeder has
since been installed.
The line can now transmit up to 50 MW. 220/132 KV Bolangir S/S is expected by Sept. 2002.
This will off load 132 KV Chiplima-Bargarh. line. As short term measures, the
Burla-Bolangir 220 KV DC line which is expected by March 2001 can be charged at 132 KV to
feed Bolangir from Burla. Shifting
of feeders from Burla Power House-
WESCO has been advised by GRIDCO to take measures by drawing 33 KV lines from
Chiplima P/H to Burla proposed s/s and then extend the same to Hirakud S/S on existing 66
KV line. This will relieve Burla PH from existing 66 KV, 11 KV & 0.4 KV S/Ss. WESCO is
expected to complete it by March 2001.
-
With regard to item (ii)
There was no representative from M/S-Aditya
Aluminum to present their objection.
GRIDCO may separately communicate their views to the Commission in this regard.
-
With regard to item (iii)
There was no representative from M/s Ferro Chrome Plant to present their objection.
GRIDCO may separately communicate their views to the Commission in this regard.
Thus, above three objections are disposed
of.
|
19.
|
M/s NESCO in their letter No.2580
dated 17.5.2000 brought to the notice of the Commission for early completion of some of
the schemes by GRIDCO for improvement of power supply in their area. These have already
been referred to by GRIDCO in their letter No.SGM(PS)-PL-GC-19/2000/2715 dated 24.10.2000.
A copy of this correspondence may be furnished to NESCO. Application of M/s NESCO is
hereby disposed.
|
20.
|
With the above remarks and
observations, we hold that load forecasts as submitted by GRIDCO for the period 2000 to
1010 may be partly accepted up to the year 2005 only, as of now. The Distribution
Companies namely M/s CESCO, M/s NESCO, M/s WESCO and Ms/ SOUTHCO shall submit load
forecasts for the respective areas of supply in terms of condition 19.2 of the license by
31st December, 2001 taking into account the Commissions observations made in
this order and any other guide lines that may be issued by the Commission in this regard,
in the meanwhile.
|
21.
|
M/s GRIDCO shall submit to the
Commission for approval, long term load forecasts for the power systems in Orissa for
succeeding 10 years (i.e. from year 2002 to 2011), long term plans for power procurement
and transmission expansion in terms of condition 20 of the license by 31st
March, 2002.
|
22.
|
Commission directs that the
Distribution Licensees and GRIDCO shall exercise caution in preparing the load forecasts
and the plan having due regard to the technical and economical complexities involved and
if necessary to induct appropriate expertise for successful handling of their
responsibilities in this regard.
|
|
(H.S. SAHU)
MEMBER |
(D.K. ROY)
CHAIRMAN |