CASE NO. 23 of 1999
Present
:
Shri S. C. Mahalik, Chairman
Shri A. R. Mohanty, Member
Shri D. K. Roy, Member
M/s.
Grid Corporation of Orissa Ltd., Janpath, Bhubaneswar751 007.
Petitioner
|
Vrs.
|
M/s.
Steel Authority of India Ltd., Rourkela Steel Plant, Rourkela. Respondent No.1
M/s.Ferrochrome Plant, Jajpur Rd. Dist. Jajpur
Respondent No.2
M/s.Indian Aluminium Company Ltd., Rourkela.Respondent No.1
|
For
Petitioner
Shri N.G. Nath, Chief Engineer(PP) Gridco.
For
Affected Party
Shri J.C. Patra, Ferro Chrome Plant
Shri B.N. Das, INDAL
Shri Rabindra Misra, INDAL
Shri A.K. Kar, INDAL
Date of argument : 09.04.1998
Date of Order : 15.05.1998
O R D E R
This proceeding relates to an application filed by
M/s Grid Corporation of Orissa Ltd., (for short, GRIDCO) seeking
approval of the Commission with regard to separate special agreements
entered with three corporate consumers namely, M/s Rourkela Steel Plant
(RSP), M/s Indian Aluminum Company Ltd., (INDAL) and M/s Ferro Chrome
Plant (Ferro Chrome).
2.
The application was heard on 04.11.97 and on 09.04.98. In the
meanwhile, the Commission had sought for clarification on a number of
points arising out of the application and replies were received from M/s
Gridco.
3.
M/s Gridco was represented by Shri N. G. Nath, Chief Engineer,
(P&P), Shri B. P. Rekhani, General Manager, Shri T. S. Rama Rao,
S.E. (Comm.), Shri M. K. Sircar, E.E.(E), and Shri M. N. Mohapatra,
E.E.(Comm.). While no one appeared on behalf of M/s RSP, Rourkela, M/s
INDAL was represented by Shri A. K. Kar, General Works Manager and Shri
Rajesh Mishra, Works Manager and Mr. B. N. Das whereas M/s Ferro Chrome
Plant was represented by Shri Jagadish Chandra Patra, Manager. The
counters and rejoinders filed by M/s Gridco were considered and the
representatives were heard.
4.
All the three industrial consumers have their own Captive Power
Plants. Major part of their requirement of power was met from their own
power stations. However, they have taken connection from OSEB/Gridco to
meet the gap between the demand and the capacity of their own CPP and to
meet additional demand during planned maintenance/breakdown of their
generating units. Instead of standard agreement as prescribed in
Regulation 6, Gridco has entered into special agreements with these
three consumers under the authority of Regulation 28 of the Orissa State
Electricity Board (General Condition of Supply) Regulations, 1995 (for
short GCS Regulations).
5.
Essential facts of the case may be outlined at the outset.
Aforesaid three consumers who have their own CPPs and
have been consumers of Gridco to meet the gap between their need
and the power generated by their CPPs and to meet demands during
breakdown of CPPs as well as during plant shutdown for maintenance have
been treated by Gridco as distinctive cases calling for special
agreements regarding supply and tariff. M/s RSP is in the category of
'Heavy Industries' whereas M/s INDAL and M/s Ferro Chrome are in the
category of 'Power Intensive Industries'. The special agreement with M/s
INDAL was entered into on 20.03.95 effective from 01.08.94 till 31.07.95
for supply of maximum demand of 30,000 KVA and energy demand of 3 MU per
month. The agreement with M/s Ferro Chrome was entered on 12.11.96
effective from 16.11.96 for one year. The contracted maximum demand is
7,000 KVA and energy demand is 9.07 lakh KWH per month. The agreement
with M/s RSP was entered on 14.01.97 effective for a period of three
years retrospectively from 16.09.96 for supply of maximum demand of
30,000 KVA and energy demand of 5 MU per month at 33 kV & 95000 KVA
with 15 MU per month at 132 kV. While M/s RSP and M/s Ferro Chrome have
only one connection each M/s INDAL has an additional connection for
emergency power supply. The conditions of supply and the tariff
prescribed in the special agreements are more or less similar in all the
cases. Each of the three consumers have taken connection for a given
contracted demand.
6.
The nature of special agreements as outlined by Gridco is as
under.
"Out of the three Special Agreements
stated above, RSP falls in the category of Heavy Industry, and M/s INDAL
and M/s Ferro Chrome Plant fall in the category of Power Intensive
Industries. All of them have taken connections for a given Contract
Demand. Conditions of Minimum Load Factor has been relaxed in all the 3
cases and minimum quantum of energy has been incorporated in the
agreement which relates to Load Factor of 0.15 to 0.2 approximately. In
lieu of the above relaxation, Demand Charges are applicable on the
Contract Demand, or the actual demand, which ever is higher, on monthly
basis with settlement period of 30 minutes . In this case, the benefit
of 80% of the Contract Demand for billing purpose available to normal
consumers is not available to them. Other conditions are almost the same
as applicable to the relevant category of consumers.
7.
The implication of above is that the three industrial consumers
covered under separate special agreements are to pay considerably lower
amount than the other consumers in the category of Heavy Industries and
Power Intensive Industries. Shorn of inessentials, Gridco's case is that
each of these three consumers owning Captive Power Plants cannot be
brought under any of the classes specified under Regulation 27 and hence
there is justification for special agreement under authority of
Regulation 28 of OSEB (General Conditions of Supply) Regulations, 1995.
8.
Before indicating the issues that emerge from the case it is
necessary to refer to relevant provisions of law.
i)
A licensee is entitled to charge tariff only as approved by the
Commission under Chapter VIII of the OER Act,
1995.
ii) Any tariff
implemented in the said Chapter shall not show undue preference to any
consumer of electricity but may differentiate according to the customer
load factor or power factor, the consumers total consumption of energy
during any specified period or the time for which supply is required.
iii) The licensee may
classify the consumers into categories specified in Regulation 27 of GCS
Regulation for the purpose of fixing tariff and conditions of supply. In
such cases the licensee has to enter into an agreement in the format
prescribed under Regulation 6.
iv) For reasons to be recorded
and having regard to the nature of supply and purpose for which supply
is required, special tariff and conditions of supply may be fixed for
consumers not covered by the classification enumerated in Regulation 27.
In such cases the licensee may enter into special agreement with
suitable modification in the standard agreement form.
9.
In this background of legal provisions, M/s.GRIDCO has entered
into special agreement with the aforesaid three corporate consumers on
the ground that these cases do not come under any of the clauses
specified under Regulation 27 and has charged tariff on a different
basis than the one provided in Commission's Tariff Order No.009 dt.
12.03.97. From the facts of the case the issues that have emerged are as
below :
a) Whether the three
industrial consumers could be covered under any of the classes specified
under Regulation 27?
b) Whether having regard
to the nature of supply and purpose for which the power is required,
there is justification for invoking provisions for Regulation 28 and for
entering into special agreements stipulating special tariff and
conditions of supply in
these cases?
c)
Whether the tariff charged by GRIDCO
as per the special agreement were in conformity with the tariff
prescribed by the OERC?
d) Whether the special
agreements submitted to the Commission are
liable to be approved and if so, from which dates?
10.
Reasons stated by GRIDCO for the justification of special
agreement in case of INDAL and Ferro Chrome are that the use factor for
these two industries have fallen below 80% due to installation of
Captive Power Plant. Definition of P.I. industries as per GCS Regulation
is "the industries where power is substantially utilised as raw
material electro-chemical and/or electro-metallurgical
processes with a contract demand of and above 2000 KVA having a monthly
use factor of 80%". Gridco's representative explained the use
factor" as the ratio of average energy drawn (M.U.) by the consumer
from Gridco to the total energy (M.U.) consumed by the Industry. Since
the aforesaid ratio after captive installation has come down to less
than 80%, these two do not fall under 'Power Intensive Industries' and
as such a special agreement is called for as contemplated in Regulation
28 of GCS Regulation. According to Gridco the drawal of P.I. industries
from Gridco after installation of Captive Power Plant has become more
demand oriented than energy based as their energy component is quite low
compared to their demand. The salient departure of the special agreement
from the approved tariff order is the change of load factor for
estimating minimum charges. Present approved tariff provide 40% load
factor to be used for estimating minimum charges for P.I. and Heavy
Industries whereas the special agreement provides for charging at 20%
while enhancing demand charges to be levied at 100% of M.D. or C.D.
whichever is higher instead of 80% used in the approved tariff order
keeping in mind the pattern of drawal of the consumer.
11.
Further it is claimed that, by GRIDCO and its predecessor OSEB
have been guided by Govt. of Orissa Policy Resolution to grant
incentives to the industries having CPPs. In this connection, GRIDCO has
quoted the Dept. of Energy Resolution No.20396/E dt.09.11.92 and
the recommendation of the Sunderrajan Committee. In order to combat
power shortage and to attract private investment in power generation
Govt. of Orissa encouraged the industries state to put up their own CPPs.
This has been made to enable the industries to be self-reliant and
to depend upon the State Electricity Board only for emergency
assistance, or operational power during plant breakdown or during
capital maintenance and for backup power. According to GRIDCO the backup
power agreement was entered into with M/s.INDAL and subsequently with
others only in pursuance of Govt. Policy. This argument was elaborated
by GRIDCO as below :
a) The high demand
component and the low energy component for these type of consumers
equipped with its own CPPs call for execution of special agreement as
this is not covered under tariff prescribed for different categories of
consumers by OERC in Order No.009 dt.12.03.97.
b) In case of M/s.INDAL
the agreement was for supplementing backup power drawn from the state
grid in conjunction with its own CPPs as a result of which the energy
requirement for operational power is very much less and hence, M/s.INDAL
do not fit into appropriate clause of consumers define in Regulation 27.
c) There is no supply of
power to such consumers at lower rate as the only relaxation for these
three industries were with regard to load factor.
12.
Shri B. N. Das, authorised represents of M/s INDAL augmented the
arguments of M/s Gridco. He stated that Gridco derived a lot of
advantages and benefit from its commercial contract with the three
industrial units having the CPPs. Consequent on availability of surplus
power from these CPPs the unit power cost of electricity is reduced for
Gridco. Further, the CPPs have helped Gridco to meet demand of other
consumers. It was argued that industries having CPPs requiring power
during maintenance/breakdown could not be fitted in any of the
categories specified in the Regulations 27 and therefore, they could not
be fitted into any of the categories covered in the tariff regulation.
The tariff notifications dt.20.03.97 had prescribed rate for emergency
power supply to CPPs with regard to supplying startup,
essential, auxiliary and survival power in the event of failure of CPPs.
This rate could not be made applicable for supply of operational power
in case of maintenance low generation CPPs. Basically argument was that
tariff should be different for operational power for industries having
CPPs and for emergency power supply to CPPs. Mr. Das also referred to
the average cost of energy for backup and for emergency power supply and
supported the justifications for special agreements in pursuance of the
Govt. policy for encouragement to the industries for setting up CPPs.
13.
The first issue to be decided is
whether the three corporate consumers fall in any of the
categories specified under Regulations 27. M/s RSP falls under the
category of Heavy Industries as its contract demand is 100 MVA at 132
kV. Electricity is utilised substantially as a motive force and hence,
it clearly falls within the
category of Heavy industries. Gridco has not given any reason as to how
and why RSP cannot be categorised as 'Heavy Industries'. RSP has neither
recorded its presence nor has responded in any manner to the notices
given to it as an affected party. On the facts before us, we do not find
any reasons for treating RSP on a different footing than any other
'Heavy Industries' and hence there is no justification for a special
agreement under Regulation 28.
Both M/s INDAL and
M/s Ferro Chrome substantially use power as raw material for
their electric metallurgical process. The contract demand of M/s INDAL
and M/s Ferro Chrome Plant are 30 and 7 MVA. Even the special agreements
stipulate that the demand charges and energy charges shall be payable at
the rate applicable to Power Intensive Industries category. Hence, it is
clear that these two consumers fall under a specified category under
Regulation 27 and Gridco itself had no doubt about it. Hence, there can
be no justification for attracting the provisions Regulation 28.
However, before putting this at rest, it may be relevant to examine one
aspect, namely, the "operational use factor" which has been
laboured for too much and to find out whether on this ground these two
Power Intensive Industries defy classification under Regulation 27.
14.
It has been argued at length that in case of INDAL and Ferro
Chrome, monthly operational use factor have fallen below 80% and
therefore, they do not come under the category of "Power Intensive
Industries" and have to be treated as special cases. Gridco and
INDAL have tried to differentiate between the load factor and
operational use factor. On a careful reading of the definition of load
factor as at Regulation 3 (XVII) and classification of power intensive
industries as at Regulation 27 (XIII), we find that load factor and
operational use factor are one and the same thing. Load factor refers to
the ratio of the total number of units consumed vis-a-vis
maximum contract demand/maximum demand and similarly, operational use
factor refers to use of Gridco's power for operational purposes vis-a-vis
contracted demand. Whether the industrial unit depends on Gridco for
less than 80% of its total power requirement is extraneous to
calculation of load factor/operational use factor. The regulation is
with regard to commercial relationship between the Gridco and the
consumer and hence, it is not concerned with the total demand of
industrial unit from all sources. The regulation is concerned with the
quantum of consumption vis-a-vis the quantum of contracted
demand. Calculation of operational use factor with reference to total
demand of the consumer company seems to be an ingenious argument devoid
of merit. It has not been proved before us that the power drawn from
Gridco for operational use was less than 80% of the contract
demand/maximum demand. Thus, the reasoning given by Gridco and supported
by Mr. B. N. Das falls to ground. Hence, we hold that INDAL and Ferro
Chrome are liable to be categorised as power intensive industries under
XIII of the Regulation 27. No case has been made out with regard to RSP
and by any consideration it has to be categorised as Heavy Industries as
at XIV of Regulation 27.
15.
We would like to briefly deal with some of the other arguments
with the observation that these are not relevant for the issues before
us in the light of the position in law. During the annual tariff hearing
in February/March'97 neither Gridco nor any other affected party
had put forth a case for special tariff treatment to the industrial
consumers having CPPs on the ground of operational use factor. Such
special agreements virtually creating a special category is not tenable.
Secondly, we have noted that during tariff proceeding Gridco had asked
for special rate for CPPs who have contracted only for emergency supply
whereas no case was made out for separate classification for industries
who had contracts with Gridco for operational power. Thirdly, issues
such as implementation of Govt. Policy for incentive to industries,
discrimination, hardship and rationalization on tariff etc. raised by
Gridco and by the authorised representative of INDAL Shri B. N. Das are
issues which can be settled only in a general tariff proceeding. The
present proceeding on a limited issue with regard to specific case
cannot provide a scope and forum to settle general tariff issues. It is
not open for Gridco to enter into special agreement or to take any other
decision on the ground of Govt.'s policy regarding incentives to
industries or for setting of CPPs.
16.
Special Agreements stipulating
different basis for calculating demand charge and energy charge
has the effect of reducing the financial impact on the consumers and
adversely affecting the revenue potential of Gridco. In any case Gridco
was not authorised to go ahead with any agreement which had the effect
of modifying or diluting the tariff order No.009 dated 12th March'97 and
Gridco's own notification dated 19.03.1997. The impugned special
agreements were obviously not in conformity with the tariff order.
17.
Having given our findings, we have to finally observe and order as
follows. The Special Agreements are irregular and Gridco should not have
entered into any such agreement without prior approval of the Commission.
However, taking note of various factors we would allow the subsisting
special agreements to run their course and to order that in cases where
the special agreements have already lapsed the tariff has to be charged
and basis of charge has to be calculated as in case of any other consumer
of appropriate category effective from 1st July 1998. Appropriate steps
for cancellation of agreement/intimation to consumer and for levying
tariff and charges in consonance with the tariff order dated 12th March,
1997 have to be taken by Gridco and an action taken report sent to
Commission by 30.06.98.
(S.C. MAHALIK)
CHAIRMAN
(A.R. MOHANTY)
MEMBER
(D.K. ROY)
MEMBER
Back to "Orders" |