CASE NO. 2 of 1998
Present:
Shri S. C. Mahalik, Chairman
Shri A. R. Mohanty, Member
Shri D. K. Roy, Member
M/s. Birla Tyres, At/P.O. Chhanpur, Dist.
Balasore -Petitioner
|
Vrs.
|
M/s. Grid Corporation of Orissa Ltd.,
Janpath, Bhubaneswar -Affected Party
|
For Petitioner:
Shri Milan Kanungo, Advocate,
Shri M.R. Das, Sr. General Manager(Engg.)
Shri S.K. Nanda, Chairman of the Energy panel of CII(Eastern Region)
For Affected party:
Shri B.P. Rekhani, General Manager
(Regulatory Affairs Unit), GRIDCO.
Date of argument: 18.05.98
Date of Order : 27.05.98
ORDER
M/s. Birla Tyres, a manufacturing unit of rubber tyres, tubes,
flaps, situated at Chhanpur, Via. Kuruda, Dist. Balasore has applied for permission u/s 44
of the Electricity (Supply) Act, 1948 (hereafter, for short, the Act, 1948) read with Sec. 21 (3) of the Orissa Electricity
Reforms Act, 1995 (hereafter, for short, the Act, 1995) to set up an additional 6.25
MW Turbo Generator set to run as a co-generation captive power plant.
2. On 3rd March'97, the petitioner made an application
to this Commission for granting consent under the above provisions of law for installation
of an additional 6.25 MW T.G. Set furnishing therewith major specification (vice
Annex.-I), detailed specification (vice Annex.-II) of the T.G. Set and a statement showing
loss of production (vice Annex.-III) due to severe power interruptions over the last 2
years (1995 and 1996).
2.1 According to the application and data furnished, the petitioner
wanted to install a co-generation captive power plant of the above capacity (6.2 MW T.G.
Set) at its factory site at Chhanapur to run in isolation i.e. on stand-alone mode for
production of automobile tyres, tubes and flaps. It further transpires from its
application that while the peak requirement of the industry is 12.5 MW, it required
annually 7.9 million units for its consumption. Further, according to the petitioner, it
has already installed a 6.25 KW Captive T.G. Set and a 2X2270 KVA stand-by D.G. Set to
meet their power requirement, permission for which had since been accorded by the Chief
Engineer (Comm.), of the then Orissa State Electricity Board (OSEB) vice its letter
No.10084 dt.7.7.93.
2.2 The petitioner has further pleaded that due to increase in
production capacity from 118 MT/day to 143 MT/day at present, the peak demands of power
having consequently increased to 12.5 MW, they require another T.G. Set of 6.25 MW to be
installed at their work site, which the petitioner intends to run in stand-alone mode.
2.3 It further transpires from the pleadings that the unit cost of
generation of power would come to Rs.1.48 without taking into consideration the cost of
the boiler and Rs.1.66 even though, the proportionate additional cost (56% steam being
used for power) of the boiler is taken into account; nevertheless the unit cost is much
cheaper than the rate at which Gridco can supply power to them. At any rate, the increased
steam demand can only be met by a 35 TPH boiler and cheaper power can be generated through
co-generation if it is allowed to set up a 6.25 MW T.G. Set.
2.4 It is further averred by the petitioner that it was, at present,
drawing 2 MW power from Gridco but the same was never stable and reliable. In support of
this averment, a statement as per Annexure-III has been filed showing the number of power
trippings and its duration (in minutes) from January'95 to December '96.
2.5 Mainly on these grounds, the petitioner prayed that consent to be
accorded to them for installation of a 6.25 MW Co-generation T.G. set.
3. Gridco (Affected Party) in its letter
No.Com-XV-3/93-RAU-7 dt.14.1.98 stated, inter alia, that a 220 kV line from Duburi to
Balasore and auto transformers at Balasore Sub-station had already been commissioned
augmenting the power supply and therefore it was in a position to meet the entire power
requirement of the petitioner. It further averred that in the meanwhile, the petitioner
has reduced its contract demand from 7.5 MW to 4.9 MW. Lastly it contended that the
petitioner has not furnished accurate and proper cost calculation so as to justify its
unit cost of generation as projected and as a result thereof, it is not comparable to
Gridco's tariff.
4. Responding to the objections raised by the Affected
Party in its letter dt.l4.1.98, the petitioner sent its parawise report on 16.2.98 by way
of rejoinder.
4.1 In the first place, the petitioner asserted that it still continued
to suffer on account of power failures and variation in the voltage and frequency
resulting in huge loss whereas stable and reliable power supply was inevitable in a rubber
industry like theirs, not only to avoid loss but also to obviate damage to its machines
like PLC and Servo Amplifiers etc. In support of this assertion, the petitioner filed a 4
page annexure (vide Annex.I of the letter dt.l6.2.98).
4.2 Reiterating its earlier stand, it further asserted that the unit
cost of generation of power from their T.G. Set would be a lot cheaper than the tariff
fixed by the Gridco because of installation high pressure fluidised bed combustion boilers
using "F" grade coal generating at 43 Kg/cm2 as per Govt. of India Guidelines
and thereby reducing the pressure to meet the process requirement and co-generating
required power from the-steam before use for process industry.
4.3 Finally, the petitioner reasserted with further facts & figures
that the supply of power by the Gridco had never been stable and reliable because of
interruptions and variation in voltage and frequency. The petitioner also pointed out, at
any rate, Gridco can not supply steam which is required for their manufacturing process
and therefore installation of one additional turbine is imperative.
5. On the first day of hearing (dt.23.2.98) on the
objection raised by the Affected Party, the petitioner was directed to file a detailed
cost calculation statement by 5th March'98 endorsing a copy thereof to Gridco. Eventually,
the petitioner filed a Report on Co-generation Plant on 17.3.98 for installation of the
Turbo Generator prepared by its consultant, M/s Development Consultants Ltd. (DCL),
Calcutta.
5.1 In view of the above development, the Affected Party was allowed to
file its response to the Report on the Co-generation Plant prepared by M/s D.C.L.,
Calcutta.
5.2 The first objection (vice letter No. Com.XV-3/93-RAU-26 dt.28.3.98)
to the report on Co-generation Plant prepared by M/s D.C.L., Calcutta was that it did not
indicate that the existing 3 boilers would not meet the steam requirement of the
petitioner for production of 143 MT/day. At any rate, the cost of the additional boiler
(4th boiler) and associated equipments have not been included to find out the unit cost of
generation of power from the proposed co-generation captive power plant in shape of a T.G.
Set.
5.3 The Affected Party further pleaded that when the estimated capital
cost of the project has been worked out at Rs.1402.35 lakhs for a 6.25 MW CPP, the unit
cost of generation would be in the neighbourhood of Rs.2.24 crores per MW which was very
low. The petitioner has further pointed out that the auxiliary power consumption, the
return on equity and rate of depreciation have been respectively estimated at 8%, 10% and
3.5% which should normally be fixed at 10%, 16% and 7.84%.
6. Finally, the Affected Party pointed out that
although the power available from the addl. Turbo Alternator has been shown as 63,900
Units per day, yet the same figure has not been taken into consideration for calculating
the fixed cost per unit.
6.1 After the above exercise, the next date of hearing of the Case was
fixed to 18.4.98. On the appointed day, arguments were heard in part from both sides. Mr.
Rekhani, the General Manager (RAW) on behalf of the Affected Party highlighted certain
inconsistencies found in the application of the petitioner on one hand and its report on
Co-generation Plant prepared by the DCL, Calcutta on the other, which are referred to
hereinabove. Director (Tariff) and Director (Engg.) of the Commission while offering their
views pointed out similar defects.
7. Since. the issues involved in this application, are
of technical nature and the petitioner had no opportunity of meeting the objections raised
by the Affected Party in its letter dt.28.3.98 and that of the Director (Tariff) &
Director (Engg.), the Commission directed that the learned Counsel as well as the team of
the officers appearing on behalf of the petitioner may hold a conference with the Director
(Tariff) and Director (Engg) with regard to the queries raised by them so as to narrow
down the same, if not to completely eliminate the same by way of mutual discussion and
clarification. The petitioner was also permitted to file its replies to the objections
raised by the Affected Party in its letter dt.28.3.98 as well as the queries of the
Commission's staff on or before 30.4.98 separately.
7.1 Pursuant to this direction on 18.4.98, the petitioner through its
authorised representative held discussion with the Commission's staff [Director (Engg.)
& Direct (Tariff)] on 23.4.98 to meet the queries raised by them. The Commission's
staff in their joint note on 16.5.9X recommended that subject to the approval of the
Commission, consent may be given for setting up of a Co-generation Captive Power Plant,
keeping in view of its power requirement and the unit cost of generation which is cheaper
compared to Gridco's tariff.
7.2 In addition to this effort, the petitioner has also filed its reply
supported by affidavit to the objections raised by the Affected Party on 28.3.98. It
explained that in order to meet its production target of 143 TED 57 TPH steam is required
and to comply with the statutory requirement of inspection necessitating approximately one
month shutdown for each of the existing three nos. 25 TPH boilers, one additional boiler
of 35 TPH FBC was essentially required to be installed to avoid reduction in production.
It further pleaded the cost of the boiler has been included in the cost of the expansion
project of the main plant as steam was required mainly for manufacturing process, while
power generation is a side advantage, as the turbine is used for reducing steam pressure
and therefore. the cost of boiler is not included in the project cost of the co-generation
plant. The petitioner also clarified that the auxiliary power consumption and depreciation
normatives have been considered as per the CEA Guidelines which is acceptable by all
national and international financial institutions.
8. Once the petitioner complied with the directions
given in the Order dt.18.4.98, the proceeding was finally heard on 18.5.98.
8.1 At the hearing, Mr. B.P. Rekhani, who represented the Affected
Party, raised only one issue relating to the unit cost of generation of power as projected
by the petitioner. But his objection was on a very limited point. While he urged that the
unit cost of production of power projected at Rs. 1.66 by the petitioner was wrong and
incorrect, he conceded that unit cost from co-generation plant will be cheaper compared to
the Gridco's tariff. This is otherwise evident because the Commission's staff has
calculated the unit cost of generation of power by the petitioner to be Rs.2.01 having
taken into consideration the fixed cost of the project and crediting the second T.G. Set
of producing power to a tune of only 2.8 MW instead of 4.3 MW as has been shown by the
petitioner in its heat and mass balance diagram. Therefore, in the worst view of the
matter, the unit cost of generation will be in the neighborhood of Rs.2/which is far
cheaper than the Gridco's tariff.
8.2 Mr. Rekhani has not raised any other objection to the granting of
consent as applied for by the petitioner. Even otherwise, there is credible material on
record to show that the supply of power from Gridco to the petitioner was neither stable
nor reliable. Undoubtedly, it suffered from interruption and variation in voltage and
frequency since January, 1995 onwards. Be it further mentioned that there is no denying
the fact that the process for tyre manufacturing needs an uninterrupted supply of power as
any failure of the power will not only result huge loss by way of scrap, but may also
damage the manufacturing equipments.
9. Thus, in the final analysis, as there is virtually
no serious challenge to the application of the petitioner from the side of the Affected
Party and also taking into consideration the pleadings of the parties, the submissions
made at the time of hearing and the feasibility of the project with a Co-generation CPP
unit in shape of a 6.25 M W T.G. Set, the Commission is of the opinion that consent should
be given to the petitioner to set up a T.G. Set as has been applied for on 3.3.97 subject
to the certain terms & conditions. Hence ordered :
O R D E R
That the petitioner is allowed to set up a Co-generation
Captive Power Plant of 6.25 M W (T.G. Set) on stand-alone mode of operation and is given
consent therefor u/s 44 of the Act, 1948 read with Sec.
21(3) of the Act, 1995 on the following terms & conditions.
-
All statutory provisions related to installation & safety in this regard are to be
fulfilled and compliance obtained from Chit Electrical Inspector, Govt. of Orissa.
-
The energy generated shall not be sold to others.
-
The installation should be so arranged that there will be no risk of accidentally back
feeding into or running in parallel with the power system of GRIDCO.
-
The installation should be subject to inspection by the respective field Superintending
Engineer (Elect)., E.E. (Elect.)/ Electrical Inspector, Orissa, Bhubaneswar or their
authorised representatives and should comply with the requirements as indicated by them.
-
An energy meter duly tested should be installed near the TG set for recording the energy
generated and consumed. The meter should be duly sealed by the concerned A.E. Inspector.
-
The installation shall be energised only after written permission of Chief Electrical
Inspector, Orissa/Electrical Inspector, Orissa or his authorised representatives.
-
Actual installation of the set should be in conformity with the installation drawing
furnished by the petitioner.
-
The electricity duty as due to the State Government shall be paid within the prescribed
time.
-
The permission granted may be withdrawn at any time if any one or more of the conditions
are violated.
-
The Turbo Generating Set shall conform to the specifications as stipulated in your
application.
-
The consent for installation shall remain valid for a period of 24 months from the date
of issue and shall lapse automatically, if the unit for which permission now granted is
not installed during that period.
Back to "Orders" |