3.0

CESCO’S PROPOSAL

The Central Electricity Supply Company of Orissa Ltd. (CESCO) is carrying out the business of distribution and retail supply of electricity in the eight coastal Districts and a part of one district of state of Orissa namely Puri, Khurda, Nayagarh, Cuttack, Denkanal, Jagatsinghpur, Angul, Kendrapara and a part of Jajpur. The company receives bulk supply from GRIDCO at several interconnected points at HT and EHT.

3.1

The profile of the company as on 31st March 2001 gives a pen picture about the current activities.

Total Consumer 

-

689220

Total Input in MU 

-

4023.37

Total Billing in MU

-

2218.53

Total Billing in Rupees Lakhs

-

58736.74

33 KV Lines

-

2174 CKT Km.

11KV Lines

-

13008 CKT Km.

LT Lines

-

17938 CKT Km.

33/11KV Transformers 

-

263 nos.(976 MVA)

11/0.4 KV Transformers

-

1254 nos.(1078.77 MVA)

3.2

CESCO in its RST application of FY 01-02 in para 2.1 and in para 1.1.of the RR application of FY 02-03 has furnished the category-wise consumption details at various voltage levels for the past period as well as projected for the year ending 02-03. An extract of the same is given below.

Table-1 : Energy Sale

Segment

FY 99 Billing MU

FY 00 Billing MU

FY 01 Billing MU

FY 02 Billing MU

FY 03 Expected Billing MU

LT Category

1173

1332

1379

1552

1735

HT Category

367

338

387

394

402

EHT Category

435

320

453

266

322

Total Sales

1975

1990

2219

2212

2459

Energy Purchase

3821

3607

4023

4204.56

4314

3.3

CESCO has stated in its RST application of FY 01-02 and RR application of FY 02-03 that the sale in EHT and HT is likely to remain static during the FY 02-03 leading to a shift in their energy sale mix towards LT segments. The licensee has given a comparative picture of category-wise sale mix at different voltage levels in para 2.2 of the RST application for the FY 02 and para 1.1.2 of the RR application for FY 03 application and stated that the system loss is on the increase due to high percentage of consumption in LT. The sale mix variation as projected by CESCO is given in the table below.

Table-2 : Sale Mix Variation

Segment

CESCO FY 99

CESCO FY 00

CESCO FY 01

CESCO FY 02

CESCO FY 03

 

% of Total

% of Total

% of Total

% of Total

% of Total

LT Category

59.1%

69.3%

63%

71%

71%

HT Category

18.7%

17.6%

17%

18%

16%

EHT Category

22.2%

13.2%

20%

12%

13%

Total

100.0%

100.0%

100%

100%

100%

3.3.1

The change in sale mix impacts the loss levels perceptibly and hence the revenue requirement e. g. a shift in demand of 10% from EHT to LT increases the total losses by 3.1% by itself.

3.3.2

CESCO estimates the LT, HT and EHT sales in FY 02 to go up by 12%, 2% and minus 44% respectively as compared to FY-01 giving rise to a negative overall load growth of the order of 0.7%.

3.3.3

During FY 03, CESCO projects higher energy sale in EHT category and static energy sales in HT category leading to shift in the energy sale mix towards LT segment.

3.3.4

CESCO estimates the LT, HT and EHT sales to go up by 11.79%, 2.03% and 21.05% respectively giving rise to overall positve load growth of the order of 11.17% during FY 03.

3.4

REVENUE REQUIREMENT

The licensee is required to meet the cost of power purchase from GRIDCO, the cost of distribution covering expenses on account of employees, administration and general expenses, repair and maintenance expenses, depreciation, interest on loan, appropriation to contingency reserve and provision for bad and doubtful debts. In addition to this, the licensee is expected to earn a reasonable return on its capital base based on the methodology prescribed in the Sixth Schedule to the Supply Act, 1948. The cost of power purchase covers not only the cost of power required to meet the need of the end users but also it covers the cost of energy lost on account of technical and commercial losses of the distribution system. The licensee also is required to meet the cost of capital of new investments needed to improve system reliability and quality of power supply.

3.5

The licensee earns its only source of revenue through retail supply tariff from the consumers of electricity within its area of license. A summary of proposals of its revenue requirement and the expected revenue at the present tariff for the year 2001-02 and 2002-03 as taken from the filings before the Commission is given in the table below.

Table-3
Rs. in Crore

Sl. No.

Financial year

Revenue Requirement including reasonable return

Expected Revenue at the present tariff

Surplus/ (Deficit)

1.

2000-01 (Actual)

963.26

552.26

(635.36)

2.

2001-02

1223.79

608.73

(615.06)

3.

2002-03

1619.37

688.27

(917.34)

The details of the components of the revenue requirement and the expected revenue at the present tariff for the year 2001-02 are furnished below :

Table-4
Rs. in Crore

Power Purchase Cost

535.12

Distribution Cost

702.72

Contribution to Contingency Reserve

0.0

Total Revenue Requirement

1237.85

(-) Misc. Receipts

20.30

Reasonable Return

6.24

Net Revenue Requirement

1223.79

Net Revenue Receipt from Sale of Power to DISTCOs

608.73

Deficit

615.06

3.6

CESCO in its application of 2001-02 has submitted that the gap between revenue from sale of power and the actual expenditure is increasing with every passing day making it difficult to fulfil its obligation as a licensee. The continued financial constraints threaten to jeopardize the very existence of the organization.

3.7

The ground realities are vastly different from the benchmarks that are considered in the tariff setting process which are seriously affecting the extent of cost coverage. In addition to this, delay in tariff filing due to factors beyond its control such as the delayed finalization of FY 99 GRIDCO accounts has put an extra burden on the licensee. Therefore, the licensee requests the Commission to relax its benchmark to revise the existing tariff rates as early as possible keeping in view the financial stress under which the company is operating.

3.8

The licensee prays that to avoid a rate shock the deficit in revenue may be treated as regulatory asset and be allowed to recover over the next three years i.e. FY 02-03, 03-04 and 04-05. The interest cost on account of regulatory asset may please be allowed to recover as pass through. The rate of interest for carrying its asset may be set as applicable after each year.

3.9

The licensee has stated that apart from the first tariff order of the Commission which came into effect from 1.4.97 and was applicable for full year, all subsequent tariff revisions have been enforced in the last few months of the financial years depriving the licensee for revenue recovery for ten months in each year. This has adversely affected the finances of the licensee.

3.10

The financial losses suffered in FY 00 and 01 were enormous and CESCO presently stands on the brink of liquidation with its networth of Rs.727.2 crore eroded several times. CESCO has further stated that it is one of the few utilities in the world that have borne the brunt of nature’s furry in quick succession like the devastating super-cyclone and floods.

3.11

CESCO has stated that the initial adoption of 35% as the maximum T&D loss allowed in tariff order 1997 and the subsequent lowering to 34% vide tariff order 2001 does not bode well for the licensee. The ground realities are total different and the licensee humbly requests the Commission to adopt a benchmark i.e. within the achievable limits.

3.12

TARIFF PROPOSAL

3.12.1

Main Features of CESCO’s Proposal

CESCO has proposed a tariff to reduce the gap between revenue requirement and expected revenue from existing tariff and charges for the FY 2001-02. Based on the concept of rationalisation of tariff structure of the previous years, CESCO proposes a tariff that is just and reasonable and the same principle is also adopted for proposing the fixed charges also. The fixed charges proposed is only 24% of the total revenue generation proposed and therefore is less than 33% of fixed costs that should be recovered as fixed charges. Main features of tariff proposal of CESCO are as follows:

  • Demand charges are proposed at Rs.200 per KVA except for the following categories:

    • All Domestic, Commercial, Small Industry, Medium Industry, Irrigation, Street Lighting, Public Institution, PWW <100 KW.

  • MFC for Street Lighting and Small Industry were proposed at Rs.100 per KVA for the first KW and Rs 80 for the rest.

  • Demand charge for HT Irrigation is proposed at the existing level of Rs.30 per KVA. The MFC for LT Irrigation is proposed at Rs.50 for the first KW and Rs.30 for the rest.

  • In respect of Public Water Works<100 KW, Public Institution and Medium Industry, MFC is proposed at Rs.150 per KVA for the first KW and Rs 120 for the rest.

  • Customer Service Charge is proposed at Rs 200 for LT consumers like PWW>100KW, General Purpose and Large Industry. The same is proposed at Rs 500 and Rs 700 in respect of HT and EHT consumers respectively.

  • Energy charges in respect of EHT consumers with various load factors (LF) except Power Intensive Industry, Colony Consumption and Emergency Supply to CPPs is proposed as follows:

LF

Rate (P/U)

Upto 50%

350

50 to 60%

300

Above 60% 

250

  • Energy charge in respect of colony consumption is proposed at 350 p/u at HT and 340 p/u at EHT.

  • Energy charge for emergency supply to CPPs is proposed at 4.50 paise/KWH.

  • Tariff for all HT categories except Irrigation, Bulk Supply Domestic is proposed at 450 p/u.

  • Irrigation tariff at HT is proposed at 250 p/u.

  • Bulk supply domestic tariff is proposed at 350 paise/unit

  • Tariff for all LT categories except for Domestic, Irrigation, Commercial and Street Light is proposed at uniform 480 p/u.

  • Irrigation tariff at LT is proposed at 275 p/u.

  • Commercial tariff is proposed as follows:

Units 

Tariff(p/u)

<=100

475

Above 100

500 for all units.

  • Domestic tariff is proposed as follows:

Units 

Tariff(p/u)

<=100

275

100-200

360

Above 200 

425

  • CESCO proposes that rebate may be allowed on current bill only when the entire bill including the arrears and current charges are paid in full.

  • Delayed payment of bills should attract DPS @2% in case of all consumers.

  • Power Intensive Industries with various load factors(LF) should pay the following tariff :

LF

Rate (P/U)

Upto 40%

205

Above 40%

180

  • CESCO proposes the continuation of the present rebate structure.

  • The reconnection charges are sought to be revised as follows:

Connection Type

Charges(Rs)

Single Phase Domestic

60

Single Phase Other Consumer

100

3 Phase Line

200

HT & EHT Line

1000

  • CESCO requests to reintroduce PF penalty in case of Medium Industries and Bulk GP consumers.

The existing and proposed tariff schedule of the licensee is given as an annexure.

3.13

Institution of Purchased Power Price Adjustment Clause (PPPAC)

CESCO has stated that its power purchase costs were directly affected by GRIDCO’s proposed bulk supply tariff as approved by OERC. Since these costs were beyond the control of CESCO, the proposal was to insulate CESCO from such risk through institution of a Purchased Power Price Adjustment Clause (PPPAC). The proposed formula does not provide an automatic pass through of cost. The change in retail tariff would need the Commission’s approval. Therefore a simple interest at the rate of 16% per annum would be made applicable to the delay between the new BST coming into effect and the adjustment coming into force. CESCO proposes that to insulate the retail licensee from the risk involved in variation in the bulk supply tariff , the Commission may permit to institute PPPAC to cover all changes in costs.

3.14

Prayer for 2001-02

CESCO has made the following prayers to the Commission:

  • Approve the Retail Supply Tariff and Charges as proposed.

  • Approve the revenue requirements as proposed.

  • Confirm revenue requirements, calculation of capital base and calculation of clear profits for the year 2001-02.

  • Approve previous year’s deficit of Rs.51.04 Crs to be recovered through special appropriation in 2001-02.

  • Allow a voltage-wise loss stipulation for computing revenue requirement.

  • Institute PPPAC to cover all changes in the cost of power purchase.

  • Approve the proposed tariff to be effective from 1st January, 2001.

3.15

Prayer for 2002-03

  • For FY 02-03, CESCO prays to approve the proposed revenue requirement at Rs 1619.37 crs.

Previous

Contents page

Next


Our Address:
Bidyut Niyamak Bhavan, Unit-VIII, Bhubaneswar - 751 012
Ph.:+91-674-2413097, 2414117. Fax.:+91-674-2413306, 2419781
e-mail- info@orierc.org

Revised on February 10, 2003

Site Designed and Maintained by
Luminous Infoways Pvt. Ltd.