| 
  
    | CASE NO. 4 of 1997Shri A.R.Mohanty, MemberDATED BHUBANESWAR THE 12th MARCH, 1997
 ORDER NO. 009, DATED 12th MARCH, 1997
 Shri D.K.Roy, Member
    ORDER UNDER SECTION 26 OF OER ACT. 1995
 This order relates to application filed by The Grid Corporation of
    Orissa Limited (GRIDCO, for short) with regard to determination of revenue requirements
    for the financial year 1997-98 and fixation of tariff. 2.0 PROCEDURAL
    HISTORY:2.1 Chapter VIII of the Orissa Electricity
    Reform Act, 1995 deals with tariff. Section 26
    in the said Chapter not only lays down a fairly elaborate procedure but also outlines the
    parameters within which the licensee will have to calculate its expected aggregate revenue
    from charges for the ensuing financial year. Gridco is the only licensee and hence
    guidelines for calculation of tariff for financial year 1997-98 were issued from the
    office of the Commission to Gridco by a letter dt. 23.11.96. The guideline included
    formats for filing tariff proposal. These formats interalia related to important financial
    parameters like O&M expenses, establishment expenses, administrative and general
    expenses, working capital, depreciation, interest on borrowing, capital base as per the
    sixth schedule of Electricity Supply Act, 1948. The Commission also notified on 28th
    November '96 the Orissa Electricity Regulatory Commission
    (Conduct of Business) Regulation in which procedure regarding tariffs were
    incorporated at Clauses
    111 to 117. The Regulation was subsequently published in the Orissa Gazette
    No. 1413 dated December 30, 1996. The Commission had also issued a procedural
    guideline to the Gridco. The said guideline indicated methodology and procedure as well as
    prescribed the terms and conditions for determination of the licensee's revenues and
    tariffs.
 2.2 A proposal under Sub-section
    4 of Section 26 of the OER Act, 1995 was received on 26.12.96
    from Grid Corporation of Orissa Limited giving details of calculation of estimated revenue
    requirements for 1997-98 and charges proposed to be collected from various categories of
    Consumers of Electricity. Subsequently some additional information were also furnished by
    Gridco. After preliminary examination of the aforesaid papers certain clarifications and
    additional information was called for from Gridco who were specifically informed that the
    Commission would take up the tariff proposal for final processing only after all the
    information was furnished. The Gridco sent a revised proposal through letter dated
    28.01.97 from the Director (Transmission and Distribution). 2.3 A notice was published by the Commission in three local newspapers
    on two consecutive days outlining the tariff proposal and calling for objections from
    interested persons. The objectors were required to submit their objections in 4 copies to
    the Commission with the 5th copy of the said objection to be served on Sri B.P. Rekhani,
    S.E. (Commerce) of GRIDCO. The notice called on the interested parties to peruse further
    details of the proposal in the office of the Gridco so as to enable them to submit their
    objections by 18th February, 1997. It also stipulated that objectors, if they so wish,
    should indicate their desire to be heard in person. All 41 objectors who expressed desire
    for personal hearing by stipulated date were admitted for hearing. In addition to the said
    41 admitted for personal hearing, written objections were received from 22 persons by the
    stipulated date. 2.4 Commission in its Order No. 352 dt. 03.02.97
    published a notice informing that a hearing on the proposal of tariff would take place on
    21st February'97. The notice also stated that the subsequent dates of hearing would be
    declared by the Commission in course of the hearing on 21st February. 2.5 The public hearing was held on 21st February in the office of the
    Commission. At the outset, the unique and unprecedented nature of a hearing with regard to
    a public utility matter was outlined. It was explained that the hearing had been fixed for
    the purpose of consultation with consumer groups in accordance with Section 10 (5) of the Act. The
    Gridco as well as objectors were requested to confine themselves only to issues relevant
    for tariff proceeding so that the Commission would be able to arrive at a just and proper
    decision on the tariff proposal. Some preliminary objections were raised mainly on the
    grounds that sufficient opportunity had not been granted to objectors and full details
    have not been furnished by the Gridco. The objectors demanded that all papers,
    calculations and evidence given to the Commission by Gridco should be furnished to them
    and sufficient time should be allowed thereafter so that objectors could place all the
    facts. 2.6 The Commission heard the learned Advocates, Mr. K.N. Jena, Mr. L.
    Pangari and Mr. Rajat Kumar Rath who claimed that the Commission could not go ahead with
    the hearing. After listening to the submission made by these objectors, the Commission
    declared that it would deliver its judgment on the preliminary objection in the afternoon
    of the same day. 2.7 When the Commission met in the afternoon, an order of the
    Commission was read over holding that there was no substance in the objections made by the
    aforesaid three distinguished representatives and that the hearing would have to be taken
    up. The said order read as under: "At the initial stage of hearing today with reference to the
    tariff application, preliminary objections were raised by three objectors who expressed
    the desire that the formal order of the Commission on these issues should be delivered
    before the Commission proceeds with the hearing on the merits of the tariff application.
    The Commission heard Mr. K.N. Jena, speaking on behalf of Orissa Consumers Association,
    Sri L. Pangari representative of IPI Steel Limited and Sri Rajat Kumar Rath, Advocate
    representing Orissa Sponge Iron Ltd. These objections had also been indicated in the
    written submissions submitted in response to the public notice of the hearing. These have,
    therefore, received the attention of the Commission. Further, the arguments and objections
    advanced before us have been heard. These have been carefully considered. The issues
    raised and orders of the Commission on them are as follows. The first objection is that Commission has not been properly
    constituted. In support of this objection, it was stated that the Commission is presently
    composed of two members and is without a Chairman and therefore, it is not a full-fledged
    Commission. It was argued that in the absence of the Chairman, the Commission was not
    entitled to conduct its proceedings. The Commission is unable to find any validity in this objection in view
      of clear and specific provisions of the law at sub-sections (4) and (5) of Section 3 which
      are as under : Sub-section (4) of Section 3: When the Chairman of the
      Commission is unable to discharge the functions owing to absence, illness or any other
      cause, the senior most member of the Commission shall discharge the functions of the
      Chairman, until the day on which the Chairman assumes the charge of his functions. Sub-section (5) of Section 3: No act or proceedings of the
      Commission shall be invalid by reason only of the existence of any vacancy among its
      members or any defect in the constitution thereof. It is also noted by the Commission that sub-section (4) of Section 9 stipulates that quorum
      for the meeting of the Commission shall be two. In view of these provisions, the
      Commission considers that there is no bar for holding proceedings of the Commission with
      two members including the senior member Sri A.R.Mohanty acting as Chairman and discharging
      the functions as the Chairman under sub-sections (3)
      and (4) of Section 3 of the OER Act, 1995. The second objection was that sufficient notice has not been given to
    the affected parties and therefore, the proceedings should not be continued. In this
    connection, it was argued that giving only seven days time to peruse the papers and making
    it obligatory to come to Gridco's office for perusal of the application was a hindrance
    for the affected parties to get sufficient notice. It was also argued that all papers,
    documents, statistics and references in respect of the tariff proposal were not made
    available and therefore the affected parties did not get sufficient opportunity. Two weeks
    time for submitting objections was also stated to be not sufficient. The Commission has carefully considered all aspects regarding granting
      of sufficient opportunity for all the affected parties. The Commission is bound by the
      statute to confirm to certain time limit. In this particular tariff proceeding for the
      Financial Year 1997-98 all the legal requirements, proper scrutiny and analysis have to be
      completed and decision of the Commission has to be conveyed to the Gridco well in time, so
      as to enable it to give a public notice of tariff seven days before the end of current
      Financial Year. Keeping these statutory requirements and other activities of the
      Commission in view, total time of sixteen days allowed for perusal and submission of the
      objection is considered adequate. The third preliminary objection is with regard to infirmity of the
    proceeding due to non-notification of the Regulation for conduct of proceeding and for
    laying down the parameters for tariff proposal. In this connection, it was claimed that
    the Commission has not discharged its function in framing Regulations for conduct of its
    proceedings and discharge of its functions as required by sub-section (2) of Section 9 read with Section 54 of the OER Act, 1995.
    It was also claimed that the tariff proceeding is illegal because the Commission has not
    yet prescribed the terms and conditions for determination of the licensee's revenues and
    tariff as required under sub-section (2) of Section
    26 of the OER Act, 1995. The Commission finds no validity in this objection in view of the fact
      that the Orissa Electricity Regulatory Commission (Conduct of
      Business) Regulation, 1996 has been framed, notified on 28th November, 1996 and has
      been published in the Orissa Gazette No. 1413 dated December 30, 1996.
      The said Regulation includes the methodology of tariff proposal. The next objection relates to the locus standi of Gridco and the
    validity of its application for tariff. On the basis of sub-section (4) of
      Section 14 of the OER Act, 1995, the Gridco had been issued a
      provisional license by the Govt. of Orissa vide letter dated 31.03.96. For all purposes,
      therefore, Gridco is a licensee under the OER Act, 1995. Further,
      the Commission observes that it is not only that Gridco has to be considered a licensee
      but, Gridco is bound by law under Section 26 (4)
      to submit details of calculation for the ensuing Financial Year regarding revenue and
      tariff. This provision of the law enables Gridco to submit the tariff proposal for 1997-98
      and obliges the Commission to consider the same for taking its decision. Another objection raised was that Gridco is not entitled to submit
    proposal of tariff within one year. The Commission has noted that the present tariff proposal relates to
      Financial Year 1997-98 and therefore, the proposal is in order. The provisions of law
      refer to Financial Year and does not refer to a period of twelve months. Objections were raised with regard to consultations with the Commission
    Advisory Committee on tariff matters. The Commission Advisory Committee has been duly constituted as required
      under Section 32 of the OER Act,
      1995 and the Commission has already initiated the process of consultation with the
      Commission Advisory Committee. Another issue raised by the objectors is with regard to the status of
    the Commission. It was stated that the Commission was a Court in view of the provisions of
    OER Act, 1995 and therefore the Commission has to observe all the
    formalities and obliged to grant unlimited time to objectors for presenting the facts
    before it. In this connection, it was also claimed that copy of Gridco's application and
    all details should have been served on the parties and in this view of procedure, the
    objector could not be asked to peruse files and collect the information from the GRIDCO. The Commission cannot agree with the above interpretation of the law.
      Under Section 10 (1) of the Act,
      the Commission has been given powers of a Civil Court under the code of Civil Procedure,
      1908 only with regard to six specified areas. Similarly under the provision of Section 52, the proceeding of the Commission shall be
      deemed to be judicial proceeding only for specified provisions of the Code of Criminal
      Procedure. The Commission has no doubt in its mind that it is a quasi-judicial body which
      is obliged to observe the procedure and formalities of legal procedure so as to the afford
      reasonable opportunity and to make final finding of facts and at the same time it has the
      authority to lay down its own procedure so as to avoid needless legal trappings. The
      legislature in its wisdom has constituted a Commission which is designed to have certain
      trapping of the Court and yet the flexibility of a quasi-judicial body so that it can get
      into all relevant issues and take a decision on legal, technical and accounting issues in
      an objective manner without delay but keeping in mind the interest of the Consumers, the
      Electricity Industry and the overall interest of the State. The Commission has accordingly
      prescribed its own procedure for which it has been authorized by the Act to do so. The
      essential distinction between a Civil Court as a part of regular hierarchy of judiciary
      and quasi-judicial tribunal entrusted with adjudicatory function outside that hierarchy
      emphasized in a number of pronouncement of the apex court has not to be lost sight of. Objection has been raised with regard to adequacy of information
    supplied. It has been claimed by learned objector Sri K.N. Jena that the proceeding should
    not be continued without supplying the documents listed by him. The Commission has gone through the elaborate list and finds that it is
      neither practicable nor essential for GRIDCO to make all the listed documents available to
      the Objectors. The Commission will go through all relevant documents and accounts as
      considered necessary. The Commission is aware of its responsibility in this regard. The
      objection cannot be admitted. The Commission, therefore, does not admit any of the above preliminary
    objections raised by the objectors and the Commission orders that the proceeding should
    continue." 2.8 The above said decision was also challenged and the Commission was
    called upon to grant permission to file appeal to the Hon'ble High Court and to stay the
    proceedings for a reasonable period giving a chance to the objectors to move the Hon'ble
    High Court. The Members of the Commission considered the request and could not accede to
    the request for adjournment of the hearing. The Commission felt that the objectors had not
    been able to appreciate the nature and scope of the proceeding and were wrongly presuming
    it to be a case of adversarial nature. Hearing was neither a pre-requisite nor was it
    contemplated in the OER Act, 1995. The Act at Section 10 (5) enabled the Commission to consult affected
    groups "to the extent the Commission considers appropriate" and it is in
    this perspective that the hearing had been arranged. The time bound nature of Commission's
    task with regard to fixation of tariff did not permit the Commission to postpone and to
    have prolonged elaborate hearings before passing its order on the tariff application. For
    emphasis we may rely on the following statements of law in A.S. de Smith, Judicial Review
    of Administrative Action, as quoted with approval by Hon'ble Justice Bhagwati in (Smt.)
    Maneka Gandhi V. Union of India AIR 1978 SC 597: "
.Since the life of the law is not logic but experience and
    every legal proposition must, in the ultimate analysis, be tested on the touchstone of
    pragmatic realism, the audi alteram partem rule would, by the experimental test, be
    excluded, if importing the right to be heard has the effect of paralyzing the
    administrative process demands.....What opportunity may be regarded as reasonable would
    necessarily depend on the practical necessities of the situation. It may be a
    sophisticated full-fledged hearing or it may be a hearing which is very brief and minimal:
    it may be a hearing prior to the decision or it may even be post-decisional remedial
    hearing. The audi al teram partem rule is sufficiently flexible to permit
    modifications and variations to suit the exigencies of myriad kinds of situations which
    may arise.........".  In this perspective the Commission clarified that because of the
    special nature of the proceedings and the time bound nature of the proceeding, it was not
    considered desirable to postpone the hearing. The Commission declared that a formal order
    to this effect would be delivered next morning and that, in the meanwhile, the proceeding
    had to continue. 2.9 The substative part of the hearing was taken up thereafter and
    continued in the same afternoon and on the next day, the 22nd, as well as in the forenoon
    of 24th when it was concluded. Before going over to the substative part, it is appropriate
    to mention the text of the order mentioned at pare 2.8 which was formally read over during
    the course of hearing on the next day: "This order is with reference to three applications filed asking
    for time to go in appeal against the order passed by the Commission on 21st February
    rejecting the preliminary objections. Two identical applications have been moved by Sri
    K.N. Jena on behalf of Orissa Consumer Association and Sri Naba Kishore Mohapatra
    representing for the Trust for Research and Public Aid. Another application as a sequel to
    his oral submission was made by Sri Rajat Kumar Rath, Advocate representing, Orissa Sponge
    Iron Limited. The Petitioners have stated that they were not satisfied with order of
    the Commission rejecting the preliminary objections and, therefore, they intend to go in
    appeal before the Hon'ble High Court for which time should be granted. It has been claimed
    by two of the objectors that with pre-judged mind the Commission is bent upon adjudicating
    on the application of the licensee with prejudice and hence they would not like to
    participate in the proceedings. The Commission has carefully considered the facts stated in the
    application as well as oral submissions made for grant of time for appeal and for
    deferring the hearing of tariff application. The Commission has considered each one of the
    preliminary objections and has given its finding to the effect that there is no validity
    in any of the objections raised. The Commission feels that the objections have no solid
    basis and therefore there is no justification to adjourn the hearing and thereby put the
    tariff proceeding on the back burner. The postponement of tariff proceeding at this stage
    for the financial year 1997-98 will create insurmountable problem for implementation of
    the provisions of the OER Act, 1995 and will jeopardize the
    management of the electricity industry in the state in an efficient, economic and
    competitive manner which is one of the main aims of the Act. The Commission is bound by provisions of Chapter
    VIII of the OER Act, 1995 to conclude the tariff proceedings for
    financial 1997-98 and convey its decision on the tariff proposal well in time to enable
    the Gridco to submit calculation in conformity with the order passed by the Commission.
    The said calculation has to be examined by the Commission and after the decision of the
    Commission on the same it has to be published in the newspapers at least one week before
    the end of current financial year. If the hearing is postponed the tariff cannot be
    finalised for 1997-98 in time. The existing tariff for 1996-97 will remain valid till 31.03.97 because
    it is a part of the provisional licence which expires on 31.03.97. Therefore if the tariff
    for financial 1997-98 cannot be finalised as per schedule drawn up by the Commission,
    there will be no legal basis for any tariff for the sale of electricity on and from
    1.4.97. Section 26 of the OER Act, 1995 lays down detailed procedure for the tariff proceeding
    for the ensuing financial year. GRIDCO's proposal for tariff have been filed in procedural
    conformity with the methodology laid down by the Commission and hence the Commission is
    bound to consider the application and take a decision on the same. In terms of Section 26(4) of OER Act, 1995
    the Commission has to examine, deliberate upon and take a decision whether to accept
    reject or modify and if so to what extent. Keeping in view the time available to the
    Commission and its schedule for the remaining part of the current financial year, the
    Commission has granted as much reasonable opportunity as in possible for finalizing the
    tariff. The Commission is keenly conscious of the parameters laid down in Sub-section 2 of Section 26 of the Act
    which enjoins on the Commission to give due importance to all the three factors namely the
    financial principles in the Electricity Supply Act, the factors which would encourage
    efficiency, economic use of the resources, etc. and the interest of the Consumers. The
    Commission feels that the special nature of a proceeding relating to a public utility must
    be appreciated and it has to be ensured that objections are not admitted which will affect
    not only the financial and economic factors but also the overall interest of the
    Consumers. It is felt by the Commission that though the objection has been raised by on
    behalf of some consumers association, admitting the same objection would adversely affect
    overall interest of the consumers and will affect supply and distribution of an essential
    public utility service like electricity. The Commission would also like to note that in accordance with Section 10(5) of the OER Act, 1995,
    the Commission is required to consult to the extent the Commission considers appropriate
    from time to time such persons or groups of person who may be affected or likely to be
    affected by the decisions of the Commission. The Commission has carefully considered the
    extent to which it is appropriate and practicable to extend the process of consultation
    for finalizing decisions as a quasi-judicial authority. Reasonable opportunity has been
    granted to as many interested parties as possible and no objection has been summarily
    brushed aside. The validity of all objections have been carefully considered and orders
    passed. In the circumstances, the Commission finds no justification to delay or
    defer the hearing which is ordered to be resumed."   |  
  
    | 3.0 GRIDCO'S PROPOSAL:3.1 The GRIDCO's proposal envisages sale of 6380 MUs of electricity during 1997-98. In
    order to meet this demand GRIDCO proposes to purchase 11000 MUs on the assumption that the
    total Transmission and Distribution losses will be restricted to 42% (as against present
    level of loss of about 47%). The financial implications were as under (in crores of
    rupees):
 
      
        | Estimated cost of power(11,000 M.U.) | 1224.90 |  
        | Expenditure on transmission and distribution | 620.73 |  
        | Return on equity (at 17% of capital base) | 122.81 |  
        | Total revenue requirement | 1968.44 |  
        | Less Aggregate of expected revenue from charges as per tariffs proposed for 1997-98
 | 1561.55 |  
        | Uncovered gap | 406.89 | 3.2 At the outset of the hearing the Commission called upon
    Gridco to substantiate its projections, calculations and proposal for tariff for 1997-98,
    Mr. B.C. Jena, Director (Transmission & Distribution) presented the proposal. He
    reiterated the facts and figures given in GRIDCO's proposal and highlighted the essential
    features. He also dwelt on the objections, copies of which had been sent to GRIDCO. 3.3 The GRIDCO has not proposed any change in the categorization of
    consumers. No significant change has been proposed in other aspects also. But, the
    proposed tariff is at a higher level than existing at present. On an average the increase
    is higher by 19.53% over the present level. GRIDCO's proposal has a lesser financial
    impact on heavy industry, power intensive industry, railway traction and large industries
    with a contract demand of 110 KVA and above ostensibly because the existing level of
    tariff in these categories is comparatively high. The GRIDCO explained that efforts are
    being made as far as possible to have the same tariff rates at the same voltage of supply
    irrespective of the categories of consumers except in case of domestic and irrigation
    categories. It was noted by the Commission that there was an uncovered gap of about Rs.407
    crores. 3.4 According to GRIDCO, the need for a tariff revision with effect
    from 01.04.97 arose primarily out of the steep rise in the purchase cost of power. This
    stood at Rs.354.94 crores in 94-95 but went upto almost double that amount viz. Rs.659.64
    crores in 95-96. In the current year 96-97 the cost of power is anticipated to be Rs.954
    crores and it is likely to go upto about Rs.1225 crores in 1997-98. Even after the tariff
    revision of May, 1996, GRIDCO sustained a loss on every unit of energy sold on account of
    the difference between the cost of energy supplied and the revenue realised. Mr. Jena
    stated that it was very important that the situation is rectified at the earliest. He
    stated that rising costs have compelled almost all Electricity Boards and Utilities to go
    in for tariff revision in the last few months. These include Utter Pradesh, Karnataka,
    Andhra Pradesh, Maharashtra, Madhya Pradesh, Haryana, Rajasthan, CESC and West Bengal. 3.5 Mr. Jena dwelt at length on the objection that there was unduly
    high T&D loss due to GRIDCO's inefficiency and hence the cost of inefficiency should
    not be borne by consumers. He said that the T&D loss per se had never been precisely
    calculated either by OSEB or GRIDCO though the reports published periodically by the
    Central Electricity Authority have put such losses for Orissa at around 23% to 24%.
    Similar figures also appear against "system losses" in the various
    Administration Reports of GRIDCO. The Audited Accounts of OSEB, however, went into this
    matter in some detail. Audit has commented at the end of the Statement of Accounts for
    1990-91 that the transmission & distribution losses are 45.3% though in the relevant
    Statements in the Report the figure was put at 23.93%. Similarly Audit has commented in
    the Reports for 1991-92 and 1992-93 that the total losses are 44.8% and 45.01%
    respectively. The corresponding figure for the Audited Statement of Accounts for 1994-95
    is 46.54%. The statutory power restrictions which were in force for several years were
    finally lifted in July, 1994 and thereafter the quantum of energy available in the system
    went up and along with it, the system losses as well as commercial losses. A substantial
    injection of funds into the system by way of systems improvement schemes could have
    reduced the losses but though the agreement with the World Bank was signed in April/May,
    1996, till date no World Bank funds have been made available. Hence the total loss in the
    system including technical and commercial losses and unaccounted for energy is expected to
    remain at the same level at the end of 1996-97 as it was in 1995-96, namely 47%. 3.6 He stated that GRIDCO has now taken effective steps in addressing
    these problems despite serious financial and other constraints. These were outlined below
    : (i) System Loss(Technical) One of the significant reasons for high system losses is the
      small proportion of transmission lines of the category 66KV and above as different from
      the sub-transmission and distribution system comprising the network of 33KV and below. It
      is found that for the last three or four years, the total length of transmission lines (of
      66KV and above) constitute only 6% to 7% of the total length of the electricity network
      (transmission + sub-transmission + LT/distribution). With the rapid increase of rural
      electrification as part of the State Government's Programme, this distortion is only
      likely to get more pronounced. System Improvement measures, construction of new Grid S/S,
      33/11KV S/S and strengthening of lines are practical steps which GRIDCO have taken up or
      are in the process of implementing to correct the situation. In the last 12 months the
      following important Grid S/Ss have been commissioned. 
        
          The 132/33 KV S/S at Jagatsinghpur 
          The 132/33 KV S/S at Nimapara 
          The 220/132 KV S/S at Balasore. The following important Grid S/Ss are likely to be commissioned in the
      next six months. 
        
          The 132/33 KV S/S at Soro 
          The 132/33 KV S/S at Sijua 
          The 132/33 KV 40 KVA transformer at Duburi 
          The 132/33 KV S/S at Pattamundai. The upgradation of transformers in the existing GRIDCO Sub-Stations
      have been done or is being done in the if following cases : 
        
          Puri 2x20 MVA to 2x31.5 MVA
          Bhadrak 3x12.5 MVA to 3x20 MVA
          Aska lx20 MVA + 1x12.5 MVA to 2x20 MVA
          Berhampur 2x20 MVA to lx40 MVA + lx20 MVA
          Baripada 3x12.5 MVA to 2x31.5 MVA
          Chhatrapur 2x12.5 MVA to lx20 MVA + 1x12.5 MVA
          Sambalpur 2x12.5 MVA to 2x31.5 MVA
          Kesinga 2x12.5 MVA to 2x20 MVA System improvement works have just been completed or are in different
      stages of progress in the following places. 
        
          Bhubaneswar Laxmisagar 2x5 MVA 33/11 KV S/S under construction.
          Bhubaneswar Nayapalli-do-
          Bhubaneswar Satyanagar-do-
          Jatni-do-
          Berhampur Goods shed S/S-do-
          Berhampur Luchchapada-do-
          Jeypore Christian Cemetery-do-
          Jeypore Bariniput 1x6 MVA-do- The system losses will go down as a result and we aim to bring down
      such losses from the current level of 47X to 42X by the end of 1997-98. Simultaneously,
      there will also be improvement in the quality of power. (ii) Commercial Losses Proper energy accounting is the key in tackling this problem.
      Having realised this, GRIDCO has completed the first phase of fixing meters at all
      inter-circle transfer points. These meters along with the meters in Grid S/Ss enable
      GRIDCO to compute precisely the quantum of energy available for consumption in all the ten
      distribution circles of the State. Meters are being installed in inter-divisional transfer
      points and it is expected that in early 1997-98 this exercise will be completed. This will
      lead to effective and accurate energy accounting at the divisional level. Major consumers with contract demand of 100 KW and above are already
      being metered and conventional meters in their premises are being replaced by Trivector
      tamper proof electronic meters which record consumption and other data with greater
      accuracy. Along with the metering in the premises of such consumers, GRIDCO has already
      placed orders for 15,000 electronic meters of various capacities to be funded by World
      Bank loans out of which about 4,500 meters have been installed in the consumers' premises
      in the last few months. The remaining meters are proposed to be installed before the end
      of the financial year 1997-98. In addition to the 15,000 meters mentioned above, about 39,000 meters
      financed by OSEB/GRIDCO with/without assistance from PFC/ADB are also being installed and
      the installation programme is being regularly monitored. About 3,518 meters out of these
      have been installed in the consumers premises. The collection of revenue is monitored regularly and recently GRIDCO
      has introduced a system of monitoring the collection work on a Sub-Divisional basis every
      day. This will enable GRIDCO to take corrective action on a daily basis whenever such
      action is warranted. GRIDCO cash collection drives were conducted during 4 consecutive
      holidays (from 8.2.97 to 11.2.97) and after finding its successful, we have decided to
      keep the cash counters open on several holidays in March'97. Apart from this, special
      drives for installing meters, undertaking load surveys and effecting disconnection of
      wilful defaulters is in progress in several parts of the State to ensure that our dues are
      collected promptly. There is also a generous incentive scheme to encourage good
      collection." 3.7 With regard to complaint on poor quality of service GRIDCO
    submitted that it had started giving this area the highest priority. Mr. Jena stated :
    "Complaint Cells will be opened in a few Metropolitan Centres immediately and will be
    extended to other places in a phased manner. Field officers have been told categorically
    that in the event they are penalised by Consumer Courts for deficiency in service, the
    Costs penalties will be recoverable from them. GRIDCO proposes to have special
    customer-orientation courses for officers and staff who have dealings with the public to
    sensitize them to the needs of customers. We are also hopeful of improving the
    distribution infrastructure through construction/upgradation of distribution sub-stations.
    A scheme funded by ADB covering 863 individual schemes is under progress and till date
    about 447 schemes have been completed." 3.8 Further, GRIDCO gave following reason and perspective to justify
    tariff increase : "The Electricity Reform Movement has been accepted by the Central
    Government and the State Governments after prolonged and intensive discussions over the
    last several months. The Common Minimum National Action Plan for Power was accepted by the
    Central and State Government in December '96. This plan is based on the premise that
    electricity costs money and the cost is to be recovered from the users. The Electricity
    Utilities are expected to conduct their business in a manner which will earn them a
    reasonable return without any Government subsidy so that private investments will be
    attracted towards Power Sector which requires substantial outlay of funds for generation,
    transmission and distribution. While some cross-subsidisation between categories of
    consumers may be permissible, no Sector shall pay less than 50X of the average cost of
    supply namely, the cost of generation + transmission + distribution. Our tariff proposals
    for 1997-98 have kept in mind these principles. There are several categories of consumers in the existing tariff. It is
    the aim of GRIDCO to reduce these categories and to rationalize the tariff structure. The
    proposed tariff structure for 1997-98 contemplates the same tariff for several categories
    so that at a subsequent stage, the various categories can be merged into smaller and more
    rationally structured consumers groups. One of the basic purposes underlining the Electricity Reform Movement
    is that the sector should be able to attract substantial non-governmental funding. This
    will be possible only if investors in the Power Sector are assured of returns which are
    comparable to returns from other sectors. Keeping this in view, the State Government had
    permitted GRIDCO to revise the tariff by a weighted average of 17% in the provisional
    licence issued to GRIDCO with effect from 01.04.96. The World Bank Appraisal Report dated
    19th April, 1996 prepared at the time of the final round of negotiations with the World
    Bank loan of 350 Million US Dollars has envisaged a 18.1% increase in the tariff for the
    financial year 1997-98. At the time of the preparation of this document, it was argued on
    behalf of GRIDCO and the State Government that tariff is a matter which is to be decided
    by an independent autonomous Electricity Regulatory Commission. World Bank, on their part,
    took the stand that the Electricity Sector in Orissa is one of the several contenders for
    World Bank assistance and World Bank would not be willing to sanction funds for any Sector
    Programme unless the Bank is assured of certain cash flows. This is one of the compulsions
    of GRIDCO which we wish to place before the Orissa Electricity Regulatory
    Commission." 3.9 The GRIDCO urged on the Commission to approve the rate of tariff as
    proposed so as to enable itself to cover the costs and establish itself as a viable entity
    to achieve the aims and objects contemplated in the Orissa Electricity
    Reform Act, 1995. |  
  
    | 4.0 OBJECTIONS
    IN COURSE OF PERSONAL HEARING:OBJECTIONS
    IN COURSE OF PERSONAL HEARING:
 4.1 Out of 41 (forty one) persons admitted for personal hearing, only 24 (twenty
    four) appeared either personally or through their representatives. The essential issues
    made out by these objectors may be indicated in the following few paragraphs.
 4.1.1 Mr. Gobind Prasad Aggarwalla, Advocate, appearing for Tarini Cold
      Storage, Rairangpur pleaded that Cold Storages should have been categorized as agro-based
      industry and not as commercial enterprises and that there should have been no increase in
      the rate of tariff. He also alleged that Cold Storage at Pipili in Puri district and those
      under electrical divisions of Baripada, Sambalpur and Cuttack district were being charged
      at industrial rate of tariff as against the Cold Storages under Rairangpur electrical
      division which are being charged at commercial rate which is higher. It was further
      pleaded that incentive and concessional rate should be given to Cold Storages as in West
      Bengal. 4.1.2 Mr. G. C. Misra, President, Madhusudan Nagar Committee,
      Bhubaneswar, stated that there should be no increase in tariff in view of unjustified high
      loss of 42% and in view of recent increases in tariff on 16.7.94, 5.11.95 and 21.5.96. It
      was further claimed that there is no justification for increase in burden on domestic
      consumption which constitutes a small portion of total consumption of electricity in the
      State. Sri Misra also objected to Gridco's proposal for tariff on the ground that actual
      expenditure on production of electricity had not been exhibited so as to justify
      enhancement of tariff. 4.1.3 Mr. Gobind Prasad Aggarwalla, Advocate, appearing on behalf of
      M/s Ambika Cold Storage, Mayurbhanj, reiterated similar objections as in case of M/s
      Tarini Cold Storage. He made out two additional grounds. It was stated that more than 90%
      of total connected load was related to motor load (motive power) and hence it was logical
      to categorise Cold Storages as industrial consumer. Secondly, Cold Storages having been
      registered as small scale industry and having been given the status of industry in the
      Industrial Policy Resolution (IPR) there was no justification for treating it as
      "commercial" for the purpose of electricity charges. 4.1.4 Mr. D. K. Pattnaik, Bhubaneswar in his knowledgeable testimony
      objected to the high tariff and commented on various aspects of the proposal of Gridco. He
      appreciated the time constraint of the Commission in view of statutory limit regarding
      finalisation of tariff for the year 1997-98 and suggested that his objection could be
      taken into account to the extent possible in the current proceedings while the Commission
      should call for improved proposals from Gridco for subsequent years. He doubted the
      purchase cost of power as projected by the Gridco and suggested to the Commission to
      scrutinise and insist on most economical purchase. He suggested a scrutiny of the
      transmission and distribution cost of Rs.743.45 crores. Referring to the Annual Administration Report of OSEB submitted to the State Govt. he
      stated that the system loss figures of 23.40% and 23.02% for 1993-94 and 1994-95
      respectively as submitted to the Govt. should be presumed to be authentic. He also
      suggested that statistics of T&D loss in the latest report of Planning Commission
      should be relied upon rather than the proposal of Gridco indicating very high percentage
      of system loss. He expected the Commission to work on T&D loss figure for 1997-98 at
      23% as against 42% projected by Gridco. He suggested a number of steps to cover the gap
      between the cost of power delivered and revenue earned. The suggestions included a pilot
      project to study the consumption by various categories, insistence on subsidy from the
      Govt. of Orissa for concession granted to agricultural consumption, subvention by the
      State Govt. for revenue loss to Gridco on account of NTPC sale of power to power intensive
      industries, cash subsidy by the State Govt. for rural electrification expenses etc. With
      regard to reduction of T&D loss he suggested installation of meters and replacement of
      defective meters. He also suggested to the Commission to finilise regulations with regard
      to consumer protection and standard of performance. In view of all these grounds he
      requested the Commission not to allow any revision of existing tariff.
 4.1.5 Mr. Gobind Prasad Aggarwalla, Advocate, also appeared for M/s
      Kichakeswari Cold & Ice Store and reiterated his objections as in case of two other
      Cold Storages referred earlier. 4.1.6 Prof. Banikanta Misra appeared on behalf of Sri B. Bisoi, a
      domestic consumer, and objected to the tariff proposal on various grounds. Before
      outlining the objections he suggested to the Commission to limit the number of objections
      as in US Public Utility Commission so that more fruitful and meaningful proceeding could
      be conducted. He claimed that the proposal for tariff hike was defective as Gridco had not
      discharged its onus of giving sufficient justification for rise and had not indicated the
      norms, bench mark and standards against which the performance was to be judged and tariff
      was to be charged. He objected to the absence of energy audit and to the excessive high
      T&D loss compared to national average. Prof. Mishra pleaded that Gridco should not be
      allowed to burden the consumers the cost due to its inefficient management, excessive wage
      bill, high T & D loss and uneconomic power purchase. He also objected to the lack of
      clarity in the classification of consumers and absence of break up in the percentage of
      loss in different categories. 4.1.7 Mr. Khirod Pattnaik appeared on behalf of M/s United Hatchery
      Private Limited, Bhubaneswar and challenged the proposal on following grounds: 
        
          Proposal doesn't make any mention of the basis of classification of consumers.
          There is no appropriate differential rate for different voltage of supply.
          There was no clarity with regard to effective date for timely payment rebate and delayed
          payment surcharge etc.
          The proposed reduction of transmission loss by only 5% was considered low and
          unjustified. 4.1.8 Mr. P. K. Das appeared on behalf of M/s Tata Iron and Steel
      Company Limited, Bhubaneswar and objected on the following grounds: 
        
          Charges for power intensive and large industries were unjustifiably high even though
          transmission loss was minimal in supply through High Tension line.
          Cross-subsidisation has been allowed against the Reform Policy.
          In view of rise in tariff in June'96 further increase would be unaffordable for
          industries.
          There was no improvement in quality of supply as the voltage fluctuation and
          interruption continued at same rate as before.
          The realisation from industrial sector was the best and the fastest and therefore, there
          was no justification for further increase in tariff in this category.
          There is no justification for increase before reducing T & D loss and stoppage of
          pilferage.
          The tariff rate for HT consumers should be fixed on cost of supply basis. 4.1.9 Sri R. N. Sarkar, General Secretary appeared on behalf of the
      objector, M/s Orissa Young Entrepreneurs Association, Cuttack. His objections were on the
      following grounds: 
        
          There has been frequent increase in tariff in the recent past.
          It was objectionable to collect monthly minimum charges, monthly demand charges, delayed
          payment surcharge, power factor penalty and monthly meter reading charge etc.
          The electronic meters presently under installation have not been standardized and
          accepted in India and hence should not have been introduced.
          The small scale industry cannot bear high financial burden on account of increase in
          electricity bill. 4.1.10 Mr. L. Pangari, Advocate, appeared on behalf of M/s IPISTEEL
      Limited, Cuttack. In his elaborate arguments he called for special and concessional
      dispensation in electricity tariff on the ground that mini steel plants are supposed to be
      encouraged by the State Govt. in accordance with Industrial Policy Resolution (IPR). He
      objected to the normal rate of tariff for the mini steel plants in view of special status
      of the industry as a joint sector project under BIFR coverage and in view of its
      tremendous export potential. 4.1.11 The main objection of M/s Ipitata Refractories Limited was on
      the ground that the industry was already sick and any additional tariff would further
      cripple the same. 4.1.12 Mr. R. K. Rath, Advocate, appeared on behalf of the objector,
      M/s Orissa Sponge Iron Limited. Mr. Rath raised some preliminary objection to the effect
      that sufficient opportunity was not granted to prove the inadequacy of Gridco's proposal
      and that under a fiscal statute/taxing statute there could not be additional burden
      without quid pro quo benefit which was missing in Gridco's proposal. He stated that
      further details should have been filed by Gridco and all papers filed by Gridco should
      have been given to the objectors. He stated that application and statements by Gridco
      should not be admitted unless proved with supporting evidence. He also objected on the ground of high T & D loss, lack of improvement in service and
      performance and absence of details in Annexure-2 of the application. With regard to
      specific case of the objector it was claimed that the tariff on mini steel industry was
      unreasonably high.
 4.1.13 Sri S. Praharaj appeared on behalf of the objector, M/s
      Neelachal Ispat Nigam Limited, Bhubaneswar. He objected to the proposal of Gridco on the
      following grounds. 
        
          Veracity of Gridco's figures and claims were not established.
          Quantum of high loss claimed was unjustified.
          There was absence of economic purchase of power and no plan for sale of surplus power to
          the neighbouring states to reduce the cost.
          Due to failure of Gridco in installing meters and keeping meters in running condition
          the figures indicated by them regarding consumption as well as production of sale could
          not be relied upon.
          The reasons of loss, level of maintenance and other details should have given in the
          application of Gridco so that cost could be analysed.
          The full level of revenue had not been revealed as security deposit and interest on the
          same had not been indicated and there was no mention of electricity duty. 4.1.14 Sri D. S. Nanda appeared on behalf of the Nayapalli Community
      Care Association, Bhubaneswar and objected to increase of tariff mainly on the following
      grounds: 
        
          There is no justification for increase in the cost of power. In this connection Sri
          Nanda gave an analysis with reference to different source of purchase of power. He claimed
          that Gridco has unduly projected availability of less low-cost and more high-cost power.
          The Gridco has not given reasons for high percentage of T & D loss. The inability to
          segregate technical loss and commercial loss was objectionable and such high percentage of
          loss should not be allowed.
          Revaluation of assets and depreciation on original cost of capital assets created
          artificial liability on the consumers.
          The manner in which capital loss of Rs.722 crores has been acquired by Gridco should
          have been examined and profit on revaluation of assets should have been taken into account
          in Gridco's finances.
          The percentage of rise tariff for industry should have been at par with the percentage
          of rise for other categories of consumers. Thrust of Mr. Nanda's argument was that with so much defect in Gridco's proposal of tariff
          further increase in tariff which would cause great hardship to domestic consumers should
          not be allowed.
 4.1.15 Sri R.C. Pattnaik, Unit-IV, Bhubaneswar complained that there
      was no consumer service at all by GRIDCO and huge arrears of energy charges due from
      medium and heavy industries were not been collected by GRIDCO. He gave certain suggestions
      and requested that the Commission should ask the GRIDCO to improve service and should
      desist from causing undue hardship to domestic consumers by revising tariff. 4.1.16 Sri B. N. Das, Chief Electrical Inspector (Rtd.) Bhubaneswar in
      his well argued testimony objected to the tariff on the following grounds: 
        
          Undue high percentage of System loss of 42% necessitating higher quantum of power
          procurement was uncalled for.
          Artificial revaluation of assets by 2 to 2.5 times of book value has created uncalled
          for financial liability to be borne by consumers.
          Profit has been calculated on fictitious capital of Gridco.
          Purchase of high cost power consequent upon revaluation of assets transferred to OHPC
          and sale of TTPS to NTPC was avoidable and the financial impact should not be passed on to
          consumers.
          Recovery of depreciation at a rate which enables Gridco, OPGC, OHPC and NTPC to recover
          90% of the cost of equipments in half of the life span and recovery of depreciation at
          percentage applicable to new assets by artificial increase in the cost of second-hand
          assets should be disapproved.
          In their proposal Gridco has not taken into account the loss incurred on account of
          policy direction given by the Govt to defunct OSEB with regard to Rural Electrification,
          Lift Irrigation, Industrial Policy Resolution, Kutir Jyoti Programme, direct sale of power
          by Captive Power Plants to industries and direct sale of power to export oriented
          industries by NTPC.
          The basis of forecast for tariff revision in 1997-98 by Gridco has not been made clear
          and this should be reviewed by the Commission. Mr. Das pleaded that the Commission should examine the above issues in details keeping in
          view efficiency, economic use of resources etc. with adequate emphasis on the interest of
          the consumers. He concluded by saying that the Commission should not encourage
          inefficiency by allowing Gridco to pass on the cost of inefficiency to the consumers.
 4.1.17 Mr. M. V. Rao appeared on behalf of The Utkal Chamber of
      Commerce & Industry Ltd., Cuttack and strongly objected to the tariff proposal. He
      made out the following main points: 
        
          The tariff increase in May'96 has already caused undue burden and should be reviewed.
          The present proposal does not satisfy the condition of Section 26(2) of OER Act and
          hence should be summarily rejected by the Commission.
          The system loss figure shown at 42% for 1997-98 was unduly high. The Commission should
          not accept this position when Gridco admits that loss figure had increased than shown
          earlier.
          Revaluation of assets increasing loan components of Govt., increased depreciation and
          artificially increased operation and maintenance expense have caused undue financial
          burden to be passed on to the consumers.
          Cheaper sources of power purchase should have been tapped.
          Revenue requirements due to increase in depreciation and the burden of cross subsidy
          could not be further loaded on the industry against express provisions of law. Mr. Rao highlighted the adverse impact of tariff revision on various types of industries
          in the State and strongly pleaded that in the interest of industrial development and
          equity there should be no increase-in the tariff on the industrial customers.
 4.1.18 Mr. T.M. Srinivas, representative of Ballapur Industries
      Limited, Jeypore reiterated the facts mentioned in the written petition and stated that
      poor quality of service and the lack of reliability in power had been causing considerable
      production and financial loss to the consumers and hence there was absolutely no
      justification for increase in tariff. He gave an example of interruption of power as many
      as 18 times in a day and stated that production loss of 12 1/2 days amounted to Rs. 72
      lakhs and loss on account of poor quality of power resulting in poor quality product
      amounts to 86 lakhs. He claimed that as many as 42 motors have been burnt out during a
      year due to defective power supply. He urged the Commission to direct Gridco to improve
      quality of power before asking for increase in tariff. He also stated that as a sick
      industry increased power tariff will have disastrous effect. 4.1.19 Mr. Damodar Das, Manager (Commercial) appeared on behalf of M/s
      Aska Spinning Mill & Baripada Spinning Mill and urged that there should be special
      consideration for employment-oriented sick industry for which any further increase in
      tariff will cause intolerable financial burden. It was requested that the fixation of
      minimum charge should be waived in case of sick industries. 4.1.20 Mr. B. S. Bhasin, President of Mini Cement Plant Association of
      Orissa, Rajgangpur reiterated general issues made out by Sri D. K. Pattnaik and Prof.
      Banikanta Misra before dwelling at length on issues stated in his own written
      representation. His objections were mainly on the following grounds: 
        
          Complete details of calculation regarding cost of production and other relevant data
          have not been given by the Gridco.
          Cross-subsidy should not have been built into the tariff proposal.
          The classification of consumers was defective particularly with regard to small scale
          industry.
          tariff should have been made at flat rate of tariff.
          The effective tariff was high and hence a maximum ceiling of tariff at Rs.2.73 per unit
          should have been fixed for small scale and medium units.
          The tariff has not been set in accordance with the provisions of the Electricity Supply
          Act, 1948.
          Tariff has not been fixed on different categories on respective cost basis.
          Gridco has not taken any step for improving of efficiency and reduction of T&D loss.
          The minimum charge for single part tariff and the maximum demand charges should have
          been reduced to reasonable level.
          The projection of bad debts at 3% of total sales source and 17% return on capital base
          project were high considering industry norms.
          Revenue receipts from interest and power factor penalty have not been shown, and there
          is no scheme for reward or incentive for improvement of financial position.
          The tariff aspects of load factor, load management and emergency power supply to CPP and
          reasonable transmission tariff have not been taken into account. Mr. Bhasin strongly pleaded for insisting on reduction of T&D loss, better performance
          of Gridco, effective action to reduce the burden on consumers and improvement of consumer
          service.
 4.1.21 Mr. S. K. Nanda appeared on behalf of the Confederation of
      Indian Industry and objected to the increase in tariff mainly on the following grounds:  
        
          There is no valid basis for the load forecast, quantum of power to be purchased and
          unusually high component and cost of NTPC power.
          The high T&D loss were unjustified and the cost for the same should not be passed to
          the customers.
          Avoidable expenses on foreign consultants and other peripheral aspects have increased
          the cost.
          Without improving the quality of supply or efficiency n service there is no
          justification for tariff increase.
          With substantially high hydro-power capacity in Orissa there is no justification for
          higher rate of tariff than in other states. Mr. Nanda also objected to the increase in the book value of assets, artificially high
          depreciation claim by Gridco, high O&M charges etc. and requested the Commission to
          ensure that GRIDCO should give paramount importance to the interest of consumers and on
          maintenance of quality and reliability of power.
 4.1.22 Mr. Smrutidhar Das, General Secretary, Confederation of Citizens
      Association, Bhubaneswar objected to the gap of Rs.423.58 crores the high cost of power
      purchase, high T&D losses, administrative failure of Gridco, preferential charges for
      colony consumption of industries, etc. He stated that the proposed increase was
      unjustifiably high for domestic and industrial consumers as against the industrial sector.
      He urged the Commission to disallow the proposal of Gridco to increase the rate of tariff. 4.1.23 Mr. Prakash Rao appeared on behalf of M/s FACOR and stated that
      the Charge Chrome industries in Orissa were under financial crisis due to recession in the
      international market and were losing heavily on every tonne of Charge Chrome manufactured
      and exported. The rise in tariff in recent years have come to an unacceptably high level
      and hence, there should be no further increase in tariff. He explained that on account of
      tariff and demand charges taken together there has been 300% increase in the total
      liability within a span of 5 years. He highlighted the predicament of the power intensive
      industries who were being deprived of ability to compete in the international market. He
      gave some concrete suggestions so as to enable the power intensive industries to survive.
      In this connection he suggested variable tariffs for peak and non-peak hour. He further
      suggested as below: 
        
          Power intensive industries should be given preferential treatment in the context of
          their export potential.
          Minimum charges should not be made applicable when actual consumption figures were
          recorded and were available.
          The industry should be allowed to reduce or increase the contract demand with prior
          notice of one month as against moratorium of three years.
          Delayed payment surcharge should be charged after taking into account, the security
          deposit amount lying with Gridco. Purchase of cheaper power from third party
          (private/public generating stations) should be allowed by Gridco with appropriate wheeling
          charges. Mr. Prakash Rao also referred to the higher purchase cost of power from TTPS and suggested
          that TTPS Talcher should be re-purchased by Gridco, so that the cost burden will go down
          giving a respite to consumers.
 4.1.24 Mr. M. S. Pattnaik appeared on behalf of M/s Bhima Ice Factory
      & Cold Storage. The objector is a partnership from whose ice factory has already been
      closed and who is being charged monthly energy bill at commercial rate. It was pleaded
      that the tariff proposal was unreasonable, unjustified, and would not contribute to
      promote economic efficiency. He emphasized on the special nature and social role of a cold
      storage with regard to agriculture development and pleaded for lower tariff. 4.1.25 Dr. Nabakishore Mohapatra, an objector represented the Trust for
      Research and Public Aids. He reiterated the facts stated in his written petition
      dt.18.2.97 filed before the Commission. The first part of his objection was with regard to
      publication of notice in English language, lack of sufficient opportunity to the objectors
      and poor consumer service by Gridco. In the 2nd part of his argument, he stated that,
      Gridco had not satisfied the conditions regarding economic use of resources and good
      performance and therefore, the Commission should take recourse to provision of Section 26 of the OER Act, 1995
      so as to reject the tariff proposal and to decide upon an alternative calculation of the
      aggregate revenue requirements as well as tariff. In the 3rd part of his objection Mr.
      Mohapatra objected to the recent practice of Gridco to insist on purchase of meter by the
      consumer. In the 4th part it was claimed that there should be only two rates Wholesale and
      retail as against thirty five rates. According to him the categorization should be done
      after taking public opinion. He referred to certain other aspects of unsatisfactory
      service of Gridco and the effect of tariff rise on the common man. Mr. Mohapatra strongly
      pleaded for focusing the attention of the Commission on common man and his financial
      problems so as to bring down the electricity charges to a lower level. He suggested
      certain economic measures and demand side management, and objected to the privatization
      policy which according to him was the cause of tariff rise. 4.1.26 Mr. N. C. Nayak appeared on behalf of M/s J. K. Corporation
      Limited and referred to the disastrous impact of tariff rise on the consumer which had a
      large industry of manufacturing synthetics. It was claimed that from 1988 till today there
      has never been a delay in payment of electricity dues by the company whereas on the other
      side due to non-maintenance of quality and voltage stability in the power supplied by
      Gridco, there is substantial loss from time to time on quantity and quality of production.
      The burden of security deposit without interest and the need for purchase of D.G. sets was
      causing avoidable burden on the consumer. It was suggested that the Commission should
      direct Gridco to be satisfied with bank guarantee and not insist on security deposit from
      big power intensive industries on whom the high security deposit amount was a great
      financial burden. Mr. Nayak requested the Commission not to allow any raise in tariff.     |  
  
    | 5. OTHER OBJECTION:5.1 Before analysing the substance of the GRIDCO's proposal and the validity of the
    objections, it will be appropriate to outline the essential objections contained in the
    written submission of those who had been admitted for personal hearing but did not attend
    for some reason or other.
 5.2 Sri Bimal Kishore Kar, Secretary, Baragada Dist. Consumer Forum
    objected to the tariff proposal on the grounds that the proposal was arbitrary and
    excessive, the financial burden was being created due to mix-management and internal
    subversion, dues were not being collected from different commercial undertakings, and
    industrial houses etc. 5.3 Sri K.N. Jena, General Secretary, Orissa Consumers Association had
    sent a petition enlisting a number of objections. The first part of the objection related
    to legal grounds. It was claimed that GRIDCO as a provisional licensee was not entitled to
    ask for an increase in tariff. Regulations on tariff methodology and procedure have not
    been prescribed by the Commission, publication of notice has not been properly done,
    copies of the application have not been supplied to the objectors and rating committee has
    not been constituted. He further took the ground that the proposed tariff was excessive
    and unreasonable necessiated due to inefficiency and uneconomic working of the GRIDCO. It
    was submitted by the objector that practically nothing was right with the GRIDCO and hence
    the application for tariff should not be entertained. 5.4 Sri Debabrata Jena, General Secretary, Federation of Consumer
    Organisation mainly referred to the adverse economic impact on various aspects of the
    proposal made by GRIDCO and claimed that the corrupt practices, inefficiency and wrong
    methods adopted by GRIDCO should be stopped and GRIDCO should not be allowed to increase
    electricity tariff which will result in price hike in every sphere and in suffering of
    consumers. 5.5 In a petition from Balasore Chamber of Commerce and Industry,
    objection was raised on the grounds that the tariff would have adverse effect on industry.
    There has been frequent increase in tariff, the quality of electricity supply had been
    extremely poor, causing financial losses to the consumers. The transmission loss projected
    by GRIDCO was too high and GRIDCO had shown artificial and exaggerated cost of assets etc. 5.6 In a letter from Tata Refractories Limited, Mr. D.K. Singh,
    Director (Operations) objected to the revision of electricity tariff on the ground that it
    would create additional financial burden which will further cripple the loss making
    industry. He suggested that the consumption of electricity in the industrial colonies
    should be calculated as per the actuals and tariff should not be revised for at least
    three (3) years. 5.7 M/s Utkal Polymer Limited, Balasore objected on the ground that the
    earlier rise of electricity is pending before the Hon'ble High Court and that in the
    background of high T & D loss, poor quality of supply, adverse impact on the industry
    and artificially high cost on investment, GRIDCO should not be allowed to revise the
    tariff. 5.8 The Orissa Small Scale Industries Association in their letter dated
    18.02.97 objected on various grounds. It was stated that the relevant accounting figures
    had not been provided by GRIDCO and the value of assets and the depreciation amount have
    been artificially increased. Meter rent should not be charged, monthly minimum charges
    should not levied, security deposit for old customer should not have been increased and
    the quality of power supply has not been improved. 5.9 Mr. Sarat Kumar Pattnaik, Advocate, Khurda objected on many
    grounds. The gross capital cost was inflected, the depreciation was claimed on a higher
    amount, the reasonable return on base capital was unduly large at 17%, cost of power has
    been inflated, T & D loss have not been limited to desired level, the quality of power
    was extremely poor and no improvement had been effected by GRIDCO. He also referred to the
    adverse impact on the LT consumers and the proposal for fixation of tariff on transmission
    etc. He requested that the defective deficit tariff budget on inflated capital base should
    not be admitted and GRIDCO should not be allowed to enhance the tariff without considering
    public interest. 5.10 Sri B.S. Mohanty, General Secretary, Acharya Bihar Parishad
    referred to high T & D loss and the recent increase in tariff and suggested that there
    should be no increase in tariff on the domestic consumers. 5.11 Sri Dhaneswar Dhal, Sahid Nagar assailed the GRIDCO's proposal on
    various grounds such as uneconomic power purchase, unduly high operating cost, unusually
    high level of T & D loss and non provision of subsidy from State Govt. etc.. He has
    given a number of suggestions relating to calculation of the cost of GRIDCO. 5.12 In a petition from Orichem Limited, objection was made on the
    ground of recent increase, adverse impact on industries, poor quality of supply, voltage
    fluctuation etc.   6.1 Objections of those who were not
    admitted for personal hearing either because they did not request for personal hearing or
    because they had not complied with the formalities for the same were scanned by the
    Commission mainly to identify relevant points as might not have been covered specifically
    in course of personal hearing. The objections looked into were from Ipitata Sponge Iron
    Limited, Orient Paper Mills, Rourkela Steel Plant, Mr. S.K. Misra, M/s Ferochrome Plant of
    IDC Limited, Magnetic (India) Limited, Mr. Birabhadra Misra, M/s Birla Tyres, Balasore
    District Small Scale Industries Association! Mayurbhani District Small Scale Association,
    Hotel Association of Puri, Oriclen Private Limited, M/s Jayashree Chemical Limited M/s Sea
    Food Exporters Association Limited. Dr. Chakradhar Das, M/s Jagdish Mines and Metals(P)
    Ltd., M/s Tisco and Shiva Agree gates Pvt. Limited. 6.2 One of the objectors suggested that the tariff proceedings should
    be kept pending till Hon'ble High Court issues orders on the earlier tariff. Rourkela
    Steel Plant objected on the ground of adverse impact on cost of production and claimed
    that concession should have been given as in Madhya Pradesh and West Bengal. M/s
    Ferochrome Plant of IDC Ltd. claimed that further hike in power tariff will increase the
    production cost and would make its product uncompetitive in international market. 6.3 M/s Magnetic (India) Limited considered the proposal of GRIDCO as a
    monopolistic exploitation of the consumers. He referred to the lack of care and action
    with regard to theft, transmission loss, cross-subsidisation, over head burden of
    operating expenditure and poor maintenance etc. According to the objector, there was no
    justification for GRIDCO to pass on the burden to non-subsidised consumers and to give
    undue preference to some particular categories of consumers. The Company also suggested
    incentive to consumers. 6.4 M/s Hotel Association of Puri and Sea Food Exports Association of
    India have claimed in identical petitions that power failure has continued as before and
    privatisation has not been a success. They claimed that Orissa should emulate Punjab in
    granting relief in electricity tariff and that the State should have special consideration
    for industries which are bound to go sick, if there was further increase in tariff. 6.5 M/s Jayshree Chemicals Limited has furnished facts and figures to
    claim that the cost of power was unduly high for industrial consumers, the transmission
    loss was too high and the cost of power procurement is unduly high. It was stated that the
    cost of tariff is quite high compared to other countries and pleaded that the power
    intensive industry should be given special consideration in order to make the industries
    financially viable and competitive in the international contest. 6.6 M/s Jagdish Mines and Metals Pvt. Ltd. stated that some tariff
    increase could be allowed only after obtaining assurance of better service. But, the
    increase could be accepted after prior approval of the Govt. in the Assembly and in any
    case the practices of billing on minimum energy charges should be abolished permanently.   7.0 GRIDCO'S
    REPLY TO THE OBJECTIONS :GRIDCO'S
    REPLY TO THE OBJECTIONS :
 7.1 Availing the opportunity of right of reply, Mr. B.C. Jena, Director
    (Transmission & Distribution) of Gridco replied to the various points raised by the
    objectors. He denied most of the allegations, gave explanations for some issues, admitted
    deficiencies in some and in the end urged the Commission to approve the tariff proposal in
    the best interest of the people and electricity industry of the state. He assured that
    Gridco was doing its best to achieve the objectives laid down in the OER
    Act, 1995.
    8.0 VALIDITY OF OBJECTIONS:8.1 Commission considered the objections in the light of facts stated in Gridco's
    proposal, the replies given by Gridco and Commission's own analysis. The objectors have
    raised extremely vital issues and enlightened the Commission with some useful suggestions
    on the basis of which the tariff proposal has to be examined. At the same time Commission
    has noted that many objections are not directly relevant to the tariff proceeding and even
    though some may have impact on tariff they have to be put aside for appropriate
    proceeding. Issues which are directly relevant to tariff fixation have to be specifically
    dealt at length by the Commission in its own analysis and judgement in this order.
 8.2 Those issues which are not relevant and those which have some
    impact but do not arise out of Gridco's proposal may be briefly mentioned. While doing so,
    the Commission is aware that most objections were raised because in an unprecedented
    public nearing of this nature the interested parties were not aware of the exact nature
    and scope of the proceeding. So far, tariff fixation has been a confidential and internal
    matter between SEBs and Government. The opinion and consultation with the public was not
    considered necessary. This Commission has thrown the issue open to public scrutiny in the
    true spirit of OER Act, 1995. On the first available opportunity of
    a public hearing, many consumer organisations and representatives have taken the
    opportunity of ventilating all their grievances, objection and suggestions in the matter
    of electricity supply. While the Commission has benefitted from many of them, it has noted
    that even with a most liberal expansion of the scope of the current proceeding it is
    neither permissible nor practicable to deal with issues not directly relevant to the
    present examination of the validity of Gridco's proposed schedule of tariff. 8.3 Objections with regard to poor quality of supply, poor maintenance
    and poor consumer service are considered relevant by the Commission only for purpose of
    bench marking and putting the Gridco in a path to function in an efficient, economic and
    competitive manner. It is not possible to deal with these aspects effectively while
    approving, disapproving or modifying. tariff proposal under Section 26 of OER Act, 1995. 8.4 Objections with regard to reform, restructuring and steps for
    privatisation programme, and various facets of transfer scheme, revaluation of assets,
    etc. are beyond the scope of this Commission as these have been done either in consequence
    or through an Act of the legislature of which the Commission is a creature. Moreover, some
    of these issues as well as the issue of tariff revision of May'96 are before Hon'ble High
    Court and hence should not have been raised before the Commission. 8.5 The objections by three cold storages were looked into. No evidence
    was given to support the allegation of discrimination and Gridco has denied that any cold
    storage in the state was categorised as industrial consumer It is understood that a suit
    in the Hon'ble High Court of Orissa by M/s. Ambika Cold Storage on the issue of
    classification has been dismissed. The Commission does not approve the suppression of such
    a relevant fact in the testimony of the objector before the Commission. Even otherwise,
    the objections raised by the Cold Storages are not relevant to the general issues of
    tariff proposal of Gridco under examination by the Commission. 8.6 Issues such as classification of consumers, minimum charges, demand
    charges, security deposits and interest on security deposit, etc. are either related to
    tariff or have impact on tariff. As Gridco has not suggested any change of the existing
    practice or rate the Commission does not consider it necessary to now deal with these
    issues. 8.7 The objections by industries which are sick or
    potentially sick, the objections by the export oriented industries, the Hotel
    Associations, Sea Foods Association, the small scale sector and of all those who have
    sought for protection, concession, special treatment, etc. have received not only careful
    but anxious consideration of the Commission. These objections have been raised on the
    assumption that Gridco has to implement Govt. policy regarding industrial and economic
    development of the State and has to give concessions in fixing tariff considering the
    socio-economic perspective of the Government and the ability of various types of consumers
    to pay. The Commission is not competent nor is Gridco entitled to go beyond the OER Act, 1995 which is more or less a self-contained statute regulating
    the electricity industry in the State of Orissa. In the matter of tariff the Commission is
    entitled to examine whether and to what extent Gridco, which is a licensee, has complied
    with the provisions of the Act. Gridco is an independent corporate entity and therefore,
    has no obligation for socio-economic objectives and government policy except those which
    are issued within the scope and in harmony with the OER Act, 1995.
    The Government shall be entitled to issue policy directives under Section 12 of the OER Act, 1995.
    No such directive has yet been issued. Section 26(5)
    outlines the essential attributes of tariff and Section
    26(2) makes it obligatory for the OERC to be bound by the three parameters within
    which terms and conditions for determination of revenue and tariffs have to be considered.
    Seen in this light, the Commission has to hold that many objections fall outside the
    purview of this proceeding. The sooner it is realised by all concerned that OER Act, 1995 has dramatically changed the legal and socio-economic
    basis of electricity industry in the State, it is better. The Commission in the later part
    of this order will give its findings on Gridco's proposal against parameters enshrined in Section 26 and shall accordingly deal with those
    objections which are relevant for present purpose of tariff setting. To allay misgivings,
    Commission makes it clear that "the interest of the consumers' is one of the prime
    considerations which are weighing its mind but the interest has to be the overall interest
    such as the maximum good for maximum people and not interest of individuals classes or
    specific categories of consumers. 8.8 The Commission has taken note of all relevant objections and have
    analysed Gridco's proposal in the light of these objections. The issues emerging from
    Gridco's application and the public hearing was placed before the Commission Advisory
    Committee in its meeting on 25th February'97. The salient issues were discussed and the
    members of the Committee raised similar sentiments and opinion as in the public hearings.
    In the process of consultation the consensus that emerged was that decision on tariff
    should be related to Gridco's performance.   9.0 COMMISSION'S
    ANALYSIS AND DECISION ON GRIDCO'S PROPOSAL9.0 COMMISSION'S
    ANALYSIS AND DECISION ON GRIDCO'S PROPOSAL: 9.1 Gridco's proposal has to be analysed in detail. As this is first time Gridco has
    submitted a proposal to the Commission, there are certain deficiency with regard to the
    formalities and presentation of the facts and figures. However, it has been possible for
    the Commission to collect all the relevant facts and to recast them for examination
    against parameters set forth in Section 26 of the OER Act, 1995. The macro picture of the financial implications of the
    Gridco's proposal is as under :
 
      
        | Cost of power purchases | Rs.1224.90 crores |  
        | add Expenditure on Transmission & Distribution | Rs. 620.73 crores |  
        |  | Rs.1845.63 crores | As against this minimum revenue requirement without taking into
    account the return on equity Gridco has proposed to collect a revenue of Rs.1562.00 crores
    by way of tariff and meter rent from all consumers. The implications of this figure are
    that the expenditure exceeds income by Rs.283.63 crores which remains an uncovered gap.
    Thus, the Gridco is not in a position to earn any return, what to speak of reasonable
    return, on capital. The financial condition of Gridco due to historical causes is in such
    a state that in its tariff proposal it has not even made an effort to realise the cost of
    supply. The situation is understandable because to realise the average cost Gridco has to
    set the tariff at a level which will be unacceptable to the consumers. The apparent
    strategy of Gridco is to improve the performance on the one hand and ask for increase of
    tariff in subsequent years so a s to close the gap and to evolve as an efficient, viable
    entity. Though Gridco has made mention of reasonable return at Rs.122.80 crores, this is
    only for presentation purpose and does not have any meaning when on their own admission an
    uncovered gap of Rs.400.00 crores is left hanging. 9.1.1 It may be appropriate to make the revenue requirement as the
      starting point of the analysis and observations of the Commission. 1. Cost of power purchase (11000 Million Units) Rs.1224.90 crores 2. O & M expenses 
        (a) Employees cost 214.00 crore . (b) Material 72.00 crore (c) Administrative & General Expenses 17.40 crore (Total) Rs.303.40 crores 3. Depreciation Rs.150.50 crores 4. Interest on loans Rs.114.30 crores 5. Contingency Rs.7.50 crores 6. Bad debts Rs.45.00 crores 7 Reasonable Return Rs.122.81 crores Total Rs.1968.44 crores The Commission have analysed each component of the requirement and
      consider the following provision as appropriate mentioned against each.     |  
  
    | 9.2  COST OF POWER: 9.2.1 Gridco seems to have inherited a run down system resulting in
      higher technical losses due to lack of adequate investment and high non-technical losses
      due to lack of proper management. Commission is of the view that such high system losses
      should not be passed on to the consumers in the long run and Gridco should concentrate its
      efforts on rapid reduction of these losses to an acceptable level. In connection with the
      load forecast and generation planning, Gridco have projected a loss reduction programme.
      The total loss in 1995-96 had been projected at 46.4% comprising of 25.5% in non-technical
      and 20.9% technical losses. The non-technical losses were proposed to be brought down to
      5% by 2000-01 and technical losses to 15% by 2002-03. For the year 1997-98 the technical
      losses are expected to be brought down to the level of 20% and non-technical losses to the
      level of 15% so that the total T&D losses are estimated to be around 35%. The
      Commission considers 35% an appropriate figure for T&D losses for the year 1997-98.
      The T&D losses are an area of major concern and Commission expects the Gridco to
      concentrate on this aspect of the business to achieve rapid reduction in the level of
      T&D losses. The Commission is, therefore, of the view that for the year 1997-98,
      T&D losses have to restricted to 35 percent. 9.2.2 With a sale volume of 6380 MU and T&D
      losses 35%, the total power requirement for purchase works out to 9815 MUs. The sale
      volume of 6380 MUs included 194 MUs to be supplied to Exported Oriented Units (EOU) from
      NTPC supply and a volume of 95 MU as back up power supply to ICCL/IMFA. These transaction
      are covered by special arrangements. The supply to EOU from unallocated power of NTPC is a
      result of Government of India decision and back up power supply to ICCL/IMFA are under
      bilateral agreement between erstwhile OSEB and the concerned companies. These have
      contractual rates outside the tariff structure pending before the Commission. Taking out
      this volume, the net sale volume works out to 6091 MUs and the corresponding volume of
      power purchase works out to 9371 MUs. 9.2.3 The Gridco has to purchase power from different sources with
      different tariff arrangements. Several of the generating stations are dedicated to Gridco
      so that the fixed charges have to be paid irrespective of the quantum of power drawn.
      These are hydro power station of OHPC, Machkund Hydro Electric Power Station, the Talcher
      Thermal Power Station and Ib Thermal Power Station. The Central Sector generation such as
      from Chukha, Farakka, Kahalgaon and Talcher Super Thermal have a different tariff
      arrangement under which fixed charges are payable in proportion of energy drawn. It is,
      therefore, necessary that Gridco maximises its energy drawal from the dedicated power
      stations to reduce the average cost of power purchase. In addition to the above, Gridco
      draws power from Captive Power Plants such as those owned by ICCL, Nalco. The charges
      payable for energy drawal from such Captive Power Plants are in single part and the costs
      are generally lower than those for the Central Sector Generation except for Chukha (Hydel)
      The Gridco's proposal on power purchase from specified power stations and the purchase
      approved by the Commission are given below based on above consideration. * 95 MU have been excluded
      as such sale is made by Gridco to ICCL under special arrangement.
        
          | Purchase of Power | Gridco projectionM.U.
 | Commission proposalM.U.
 |  
          | A. Hydro (State) | 3800.00 | 3800.00 |  
          | B. Hydro (Machkund) | 300.00 | 300.00 |  
          | C. Hydro (Chukha) | 200.00 | 200.00 |  
          | D. Kaniha Infirm | 100.00 | 100.00 |  
          | E. Thermal (CPP) | 1000.00 | 905.00* |  
          | F. Thermal (TTPS) | 1600.00 | 1600.00 |  
          | Total | 7000.00 | 6905.00 |  
          | G. IB TPS (OPGC) | 2330.00 | 2330.77 |  
          | Total | 9330.00 | 9235.77 |  
          | H. Farakka | 900.00 | 134.84 |  
          | Total | 10230.00 | 9370.62 |  
          | I. Firm (Kaniha) | 470.00 | 0.00 |  
          | J. Kahalgaon | 300.00 | 0.00 |  
          | Total | 11000.00 | 9370.62 | Gridco had estimated cost of power from various generating stations.
      These have been analysed by the Commission and we have found it necessary to correct the
      unit rates proposed by Gridco in respect of TTPS, ITPS, Farakka, Kahalgaon and STPS
      (Kaniha). The changes in purchase cost considered necessary by the Commission under each
      case is briefly stated below. 
        
        
          :- GRIDCO proposal indicates an annual fixed charge of Rs.120.95 Crores
          corresponding to a P.L.F. of 43.27% as per the PPA & MOU signed between OSEB and NTPC.
          This works out to a rate of 79.04 P/U.TTPSThe present notified cost of coal has been taken as 337.90/MT and oil price as Rs.7857.00.
          Assuming a further rise of 10% in the cost corresponding to a P.L.F. of 45.25% or 1600 MU
          availability the cost/unit works out to 130.68 P/U as against 140 P/U proposed by GRIDCO.
 
          ITPS:- The tariff of ITPS has been calculated by GRIDCO @ 165 P/U considering the
          cost of coal at Rs.451.44/Ton and cost of oil at Rs.7791/Kl.On verification of the current coal & oil bills of OPGC, it is found that the present
          cost of coal is Rs.365.56/Ton and that of oil is Rs.8818.09/Kl.
 Annual average value of GCV of coal supplied during the calendar year 1996 is 2994 Kl/Kg.
          Taking the current price of coal & oil into consideration, the cost of variable
          charges works out 36.83 P/kWh.
 The annual fixed cost submitted by GRIDCO is Rs.285.10 Crores as against Rs.280.50 Crores
          calculated by the Commission averaged over a period of three years as provided in the PPA
          between OPGC and GRIDCO vide Sl. No.11 of Schedule-II.
 At an energy
          availability of 70% the fixed cost/unit taking incentive into consideration comes to
          120.87 paise/kWh. Thus the total cost per unit at 70X P.L.F. works out to 157.70
          paise/unit for this station.
          Kahalgaon, Farakka:- The cost of power has been calculated by the Commission
          using cost data of CEA and giving due weightage for transmission charges and transmission
          losses.STPS:- The cost of infirm powers as proposed by Gridco has
          been accepted by the Commission. The cost of power after commercial operation of Kaniha S.T.P.S. may be
          same as that of Kahalgaon S.T,P.S. but in absence of complete data in respect of Kaniha
          Station, the rate accepted for Kahalgaon is being adopted for Kaniha. The unit cost of power from different power stations as proposed by
          Gridco and as accepted by the Commission are given below. 
            
          
            
              | Purchase of Power | Gridco proposalRate P/U
 | Commission proposalRate P/U
 |  
              | A. Hydro (State) | 49.00 | 49.00 |  
              | B. Hydro (Machkund) | 8.00 | 8.00 |  
              | C. Hydro (Chukha) | 76.00 | 76.00 |  
              | D. Kaniha Infirm | 48.00 | 48.00 |  
              | E. Thermal (CPP) | 90.00 | 90.00 |  
              | F. Thermal (TTPS) | 140.00 | 138.68 |  
              | G. IB TPS (OPGC) | 165.00 | 157.82 |  
              | H. Farakka | 135.00 | 126.00 |  
              | I. Firm (Kaniha) | 255.00 | 176.05 |  
              | J. Kahalgaon | 255.00 | 176.05 |  Gridco had observed that achieving the optimum power purchase may not
          be possible with the prevailing Grid situation in the Eastern Region with transmission and
          frequency constraints. Projected sale and the corresponding purchase may also undergo
          change. The Commission is of the view that such changes beyond the control of Gridco can
          be allowed through an adjustment with adequate justification furnished by Gridco. 
      9.2.4 O & M EXPENSES:(a) Employees cost: Gridco have estimated the employees cost to be Rs.214
      crores. While originally details were not furnished, Gridco have in their letter dated
      20.2.97 furnished the basis of calculation. Gridco have taken the base year figure of
      1995-96 from the unaudited accounts of OSEB and have adjusted these figures towards normal
      annual increment of 2.5% and annual inflation. No additional man power has been proposed.
      The basis and the figure proposed by Gridco are found reasonable and are accepted by the
      Commission.
 (b) Material cost: Gridco has estimated its material cost amounting to Rs.72
      crores The basis for adopting these figures has been furnished by Gridco in their letter
      dated 20.2.97 assuming material cost at 5% of the gross asset value as on 1.4.97. The
      impact of the revaluation of asset has not been considered by Gridco in working out the
      material cost and therefore, the Commission found this figure acceptable. The material
      cost of OSEB for earlier years were in the order of 3.5 to 4X of the asset value. The
      material cost provided in previous years are apparently not adequate in view of present
      run down condition of the installation and therefore, present proposal of 5% is allowed by
      the Commission.
 (c) Administration and General Expenses: Gridco have estimated the annual
      Administration and General Expenses amounting to Rs.17.40 crores and have furnished the
      basis of calculation in their letter dated 20.2.97. They have adopted the base year figure
      of 1995-96 from the unaudited accounts of the OSEB for the year and reflected annual
      inflation. Therefore, the basis adopted by Gridco and figure proposed are reasonable and
      accepted by the Commission.
 9.2.5 Depreciation : Gridco had proposed an amount of
      Rs.150.53 crores towards depreciation in their tariff application. This was based on a
      rate of 6.55% on EHT assets, 7.84% on HT assets and 7.84% on LT assets as on 1.4.96. The
      asset wise classification and depreciation applicable thereon has not been furnished and
      in the absence of this the Commission does not find this acceptable. In the unaudited
      accounts of OSEB for the year 1995-96 OSEB have worked out the detailed calculation of
      depreciation based on Ministry of Power Notification No. SO-266 (E) dt.
      29.03.94. Though, this notification refers to the State Electricity Boards and a Notification
      265 (E) dt.27.3.94 is intended for licensees, the percentage of depreciation are
      same in both the cases. In this annual account the percentage of depreciation for EHT
      installation works out to 5.32% and that for the distribution installation works out to
      6.94%. The Commission have applied this percentages to the asset base as on 1.4.97 and
      have worked out the amounts of depreciation for 1997-98 as Rs.57.43 crores for EHT and
      Rs.70.59 crores for HT and LT works. Thus, the total depreciation works out to Rs.128.02
      crores. Calculation of depreciation as estimated by the Commission is as follows: CALCULATION OF DEPRECIATION FOR 1997-98 
        
      
        
          |  |  |   Gen. |   Trans. |   Dist. |   Others | Rs. in crores Total |  
          | 1 | Total amount for the year
          95-96 & arrear for 94-95, Source: Prov Account 95-96 |   18.67 |   32.67 |   52.65 |   2.16 |   106.15 |  
          | 2 | Arrear depreciation for
          1994-95 | 3.75 | 6.88 | 13.26 | 2.16 | 24.47 |  
          | 3 | Depreciation for the year
          1995-96 | 14.92 | 25.79 | 39.39 | 0.58 | 81.68 |  
          | 4 | Gross Fixed Asset in use as
          on 01.04.1995 | 413.03 | 485.01 | 567.87 | 1.58 | 1507.05 |  
          | 5 | Percentage of depr. to GFA
          (Item 3 as % of Item 4) |   | 5.32% | 6.94% | 41.14% |  |  
          | 6 | Asset in use as on
          01.04.1997 Source: Gridco Tariff filling |   |   1080.00 |   1017.70 |   3.84 |   2097.70 |  
          | 7 | Amount of depr. for 1997-98 |   | 57.43 | 70.59 |  | 128.02 |  9.2.6 Interest on loans: Gridco have
      proposed an amount of Rs.114.30 crores towards interest on loans. The provision in their
      OSEB unaudited accounts for the year 1995-96 was Rs.127.95 crores. Out of this interest on
      account of State Govt. loan allocable to Hydro Generating Station amounts to Rs.24.00
      crores The net interest on loans for 1995-96, therefore, is of the order of Rs.103.00
      crores which corresponds to T&D investment. Considering an investment of Rs.140.00
      crores by Gridco during 1996-97, Commission found the proposal of Rs.114.30 crores
      acceptable.  9.2.7 Bad debts: Gridco has proposed an amount of 45
      crores towards bad and doubtful debts for the year 1997-98. This has been worked out as 3%
      of the revenue from sale of power for the year. The Commission feels that this provision
      is on the higher side. In OSEB, the principle followed for providing reserve towards bad
      and doubtful debts was calculated at 10% of book debt against regular consumers and at the
      rate of 100% of the book debts against the permanently disconnected consumers. Govt. of
      Orissa have transferred the book debt of Rs.146.80 crores as against the gross book debt
      of 588.7 crores as on 31.3.96. Thus, the amount of Rs.438.9 crores has been written off as
      bad debt. It is presumed that this provision of Rs.146.8 crores is towards bad debts are
      against regular consumers. The provision of 15% on the differential of book debt as on
      1.4.97 and 1.4.98 as calculated below is considered appropriate by the Commission. (Rs. in crores) 1. Amount of Gross Book Debt as on 01.04.97 202.00 2. Amount of Gross Book Debt as on 01.04.98 286.00 3. Increase in Book Debt during 1997-98 (2-1) 84.00 4. Provision @ 15% (15% on Item 3) 12.60 Therefore, the provision for 1997-98 towards bad debts should be 12.60
      crores. 9.2.8 Contribution to Contingency Reserve: Gridco has
      accorded a provision of 7.5 crores towards the contribution to contingency reserve under
      Para IV of Schedule VI of Supply Act, 1948. As per the provision of Para IV of the
      Schedule VI such contingency reserve should have a minimum value of one quarter of 1% of
      the asset value which works out to 5.25 crores and a maximum value of half of 1% of asset
      value which works out to 10.50 crores, taking into account the asset value of 2097 crores.
      As the provision proposed by Gridco of 7.5 crores is within the limit, it is considered
      reasonable and admissible. Based on the above observation, the expenditure to be incurred by Gridco in accordance
      with sixth schedule for assessing the revenue requirement as per Section 26(4) of the OER Act, 1995
      is indicated below: 
        
      
        
          | ExpenditurePara XVII Clause-2 (b)
 | Rs. in crores |  
          | I | Generation and purchase of
          Energy | 833.98 |  
          | II | Distribution & Sale of
          Energy (a) Employees cost 214.34 (b) Material cost 67.35 (c) Admn. & General Expenses 17.41 | 299.10 |  
          | III | Rent, rates and taxes other
          than all taxed income & profits | (included in A&G expenses) |  
          | IV | Interest on loans advanced
          by Gridco 
            
              Interest on loan borrowed from organisation
              Interest on debenture issued by licensee | 114.30 -- |  
          | V | Interest on security
          deposit | -- |  
          | VI | Legal charges | (included in A&G expenses) |  
          | VII | Bad debt | 12.60 |  
          | VIII | Auditor's fees | (included in A&G expenses) |  
          | IX | Management including
          managing agents remuneration | 5.00 |  
          | X | Depreciation | 128.02 |  
          | XI | Other expenses | -- |  
          | XII | Contribution to P.F., Staff
          pension, Gratuity 
            
              Expenses on training & other training scheme
              Bonus | (included in employees cost) (included in
          employees cost) (included in employees cost) |  
          |  | Total expenses I to XII | 1443.00 |  Special appropriation to cover 
          
        
          | Para XVII
          Clause 2(c) | Rs. in crores |  
          | I | Previous loss | Nil |  
          | II | All taxes on income & profits | Nil |  
          | III | Instalments of written down account in respect
          of intangible assets and new capital issue expenses | Nil |  
          | IV | Contribution to contingency reserve | 7.50 |  
          | V | Contribution towards arrear depreciation 
            
              Contribution to development reserve
              Debt reduction and obligation | Nil Nil Nil |  
          | VI | Other special appropriation permitted by State
          Govt. | Nil |  
          |  | Total of (C) | 7.50 |  
          |  | Total (B + C) | 1450.50 |  Rs. 1451 crores is considered adequate to cover all
      expenses including the obligation of interest payment and also depreciation.   |  
  
    | 9.3 Para I of sixth schedule states that the licensee
    shall so adjust his charges for the sale of electricity whether by enhancing or reducing
    them that his clear profit in any year of account shall not, as far as possible, exceed
    the amount of reasonable return. In other words, licensee is entitled to earn clear profit
    not exceeding a stipulated percentage over reasonable return. Section 26 (2) (a),(b),(c) of the OER
    Act, 1995 stipulates that the Commission shall be bound by the parameters of the
    financial principles and their applications provided in Section 57 of Indian Supply Act,
    1948 and in the sixth schedule thereto as well as factors which would encourage
    efficiency, economic use of resources, good performance, optimum investment and finally
    interest of consumers. Commission has carefully examined the factors specified in the
    sixth schedule in the background of the licensee's performance in the matter of high
    system loss. The views expressed before the Commission by the objectors in the hearing
    brought out the unanimous complaint about Gridco's poor performance in not providing the
    meters resulting in huge losses. Commission is of the view that Gridco has to reduce its
    T&D losses and strengthen its revenue collection system by repair and replacement of
    meters. An excessive system loss which includes a large amount of commercial losses, is a
    burden on the consumer as this increases the purchase power bill requiring to be paid by
    the limited consumers existing under the net of revenue collection system. Commission is
    also aware of a large number of unauthorised consumers enjoying free electricity burdening
    the paying consumers and creating losses to Gridco. In fact, this phenomenon is of such a
    serious significance that the whole process of tariff making gets vitiated. Another factor
    of loss creeping into the revenue collection system is the non-functioning or
    non-existence of meters to a large extent among the consumers. In the present practice of
    Gridco, a consumer is charged at various load factors applicable to different category of
    consumer where the meters are not working. But, such a levy of charges based on load
    factor leads to unrestricted drawal of energy burdening the power system both
    operationally as well as financially. Therefore, it is of paramount importance that meters
    at the consumer's premises must be repaired or replaced at the earliest as a first step in
    the attempt to gain revenue. Until T & D loss is brought down to an acceptable level
    the Commission does not consider it appropriate in the interest of consumers to allow
    expenditure on purchase of power mentioned at Para VII Clause 2 (b) (i) in the SIXTH
    SCHEDULE to the extent proposed by GRIDCO. The Commission has, therefore, decided to
    depart from the above said factors specified in the SIXTH SCHEDULE to the extent of
    limiting expenditure on power purchase. The comparative position of GRIDCO's proposal and
    that approved by the Commission is given below: CALCULATION OF CLEAR PROFIT FOR THE FINANCIAL YEAR
    1997-98 AS PER SCHEDULE VI OF ELECTRICITY SUPPLY ACT, 1948 PARA - XVII (2) 
      
        | Rs. in Crores |  
        |  | GRIDCO Proposal | Commission Proposal |  
        | (A) Income derived from: Gross receipt from Sale of energy less discounts applicable thereto. | 1556.37 | 1422.68 |  
        | Rental of meters and other
        apparatus hired to consumers | 5.18 | 5.00 |  
        | Sale & repair lamps and
        apparatus | -- | -- |  
        | Rents | -- | -- |  
        | Transfer fees | -- | -- |  
        | Interest on investment | -- | -- |  
        | Other general receipts
        accountable for income tax and arising from and ancillary or incidental to business of
        electricity supply | -- | 8.5(transmission charges)
 15.0(D.P.S)
 |  
        | Total of (A) (i to vii) | 1561.55 | 1451.18 |  
        |  |  
        | (B) Expenditure properly incurred on: Generation & purchase of energy | 1224.90 | 883.98 |  
        | Distribution & sale of
        energy 
          
            Employees cost
            Material
            A & G expenses | 214.00 67.00 17.40 | 214.34 67.35 17.41 |  
        | Rents, rates & taxes, other than all taxed
        on income and profit | Included in A&G expenses | Included in A&G expenses |  
        | Interest on loan advanced
        by Board 
          
            Interest on loan borrowed from organisation
            Interest on debenture issued by licensee | -- 114.30 -- | -- 114.30 -- |  
        | Interest on security deposit | -- | -- |  
        | Legal charges | Included in A&G expenses | Included in A&G expenses |  
        | Bad debts | 45.00 | 12.60 |  
        | Auditors fees | Included in A&G expenses | Included in A&G expenses |  
        | Management including
        managing agents remuneration | 5.00 | 5.00 |  
        | Depreciation | 150.53 | 128.02 |  
        | Other expenses | -- | -- |  
        | Contribution to P.F., staff
        pension and gratuity | Included in employees cost | Included in employees cost |  
        | 
          
            Expenses on apprentice and other training scheme | Included in employees cost | Included in employees cost |  
        | 
          
            Bonus | Included in employees cost | Included in employees cost |  
        | Total expenditure i.e.
        total of (B) (i to xiii) | 1838.13 | 1443.00 |  
        |  |  
        | (C) Special appropriation
        to cover: |  |  |  
        | Previous losses | -- | -- |  
        | All tax on income and
        profits | -- | -- |  
        | Installments of written
        down amounts in respect of intangible asset and new capital issue expenses | -- | -- |  
        | Contribution to contingency
        reserve | 7.50 | 7.50 |  
        | Contribution towards arrear
        depreciation | -- | -- |  
        | Contribution to Development Reserve, referred
        to in para | -- | -- |  
        | Debt redemption obligation | -- | -- |  
        | Other special appropriation permitted by the
        State Government | -- | -- |  
        | Total of (C) (i to vi) | 7.50 | 7.50 |  
        | CLEAR PROFIT (A-B-C) | (-) 284.08 | (+) 0.68 |  
        | Reasonable Return (Annexure-A) | 89.05 | 89.05 |  
        | Excess or deficit of clear profit over reasonable return | (-) 373.13 | (-) 88.37 | 9.4 The tariff setting to raise a
    revenue of Rs. 1451 crores has to keep in view the cost of supply at various voltage
    levels, their load factor, power factor, quantum of consumption and the prevailing tariff
    of other utilities in the country. 9.5 Consumers on High Tension (HT) and Extra High Tension (EMT) voltage
    levels requested to eliminate cross subsidisation and fixation of tariff appropriate to
    their cost levels. Consumers on the low voltage level, specifically the domestic consumers
    expressed their views that there should not be any rise in tariff for this category as
    unlike industrial consumers they have no scope to pass on the additional burden to
    somebody else. Some of them have expressed their views that the power purchase from the
    cheaper sources should be allocated exclusively for this domestic category of consumers so
    that they can remain at the lower level of tariff. 9.6 As stated earlier the industrial consumers availing power
    supply at low voltage level expressed their apprehension that tariff rise would make their
    products less competitive in the market. So the Commission has a complex task of balancing
    the interest of various consumer groups on the one hand and the financial health of the
    licensee on the other. It may also be highlighted that the present run down condition of
    the installation of Gridco needs investment for improving service and bringing down the
    technical losses of the system. Commission has considered very carefully the tariff
    proposal of Gridco proposing an overall increase of 19.53% at T & D losses at a level
    of 42%, leaving deficit of Rs.407 crores. To achieve this overall rise of 19.53% Gridco
    has proposed a raise varying from 13.22% to 52.16% on the existing level of tariff. The
    Commission, therefore, examined all levels of the existing tariff structure and decided to
    rationalise to the extent possible and fix a tariff which would impose the minimum burden. 9.7 Commission has elaborately examined the case of supply at
    different voltage levels to assess the impact of revision. In this regard the Commission
    has come to the conclusion that the present levy of additional charges on account of
    supply at a voltage other than the declared voltage of tariff need revision. Citing an
    example for illustration : A consumer at contract demand of 5000 KVA or above availing
    power supply at 33 KV is required to pay an additional charge of 7.5% over and above
    tariff rate payable by the consumer of same category availing power supply at the tariff
    voltage of 132 KV. But the cost of supply at 33 KV compared to the cost of 132 KV works
    out much higher than the present additional levy of 7.5%. Conversely, a consumer is
    entitled to reduction of charges if power is availed at higher voltage level than the
    declared tariff voltage level. Therefore, there is a provision of incentive and
    disincentive for the consumer to avail power supply at a higher or lower voltage. Complete
    rationalisation is not possible at one stroke. The Commission decided to increase the
    present level of additional charges by a margin of 2.5% for all voltage levels. 9.8 REVENUE ASSESSMENT FROM DEMAND CHARGES:  9.8.1 Gridco while submitting the calculation of the expected revenue
      from charges for the year 1997-98 has separately indicated the revenue likely to be earned
      on account of demand charges and on account of energy charges separately. 9.8.2 In case of consumers with contract demand of 100 KVA or above and
      billed under two part tariff, the demand charge is levied as per the recorded maximum
      demand or at 80X of the contract demand, which ever is higher. In calculating the demand
      charges, 80% of the demand component has been taken into consideration to work out the
      revenue likely to be realised from these category of consumers by GRIDCO. The industrial
      consumer has to pay demand charges at penal rates if actual maximum demand exceeds the
      Contract Demand. He has to pay a minimum Demand Charge based upon 80% of Contract Demand.
      The Maximum Demand would, therefore, be above 80% of Contract Demand but below 100% of
      contract demand in general. 9.8.3 It would be appropriate on the part of Gridco to work out the
      peak demand attained by such category of consumers and work out the demand charges. On the
      other hand calculation of demand charges at 80% of the Contract Demand reflects an
      understatement of the revenue to be realised. The Commission after careful consideration
      have decided to work out the revenue requirement for this category of consumer assuming
      maximum demand at 90% of the contract demand, for the year 1997-98. 9.8.4 It is hoped that in future tariff proposals, Gridco will work
      out, in respect of these type of consumers, the average of peak demand of the last 12
      months to assess the demand charges reasonable to such category of consumers.  9.9 Cross-subsidy: Commission is aware that the burden of
    intra-class subsidy falls heavily on the large industry groups. Several such industries
    are finding it economical to set up Captive Power Plants of their own. It is in the
    interest of customers paying tariff below the cost of supply that large industries group
    do not migrate from Gridco's power supply due to heavy tariff burden. The Commission has
    attempted to reduce the intra-class subsidy keeping in view the life line rates for the
    very small consumers. Increase in tariff rates has been higher for customer classes who
    are paying smaller portion of the average cost of supply. A beginning has been made in
    this order for reduction of cross-subsidy. 9.10 Irrigation: As in other states of India, the tariff
    rates for agriculture is very much below the average cost of supply. The agriculture load
    generally comes up during off-peak hours and would not add significantly to the peak
    demand of Gridco. Further, rate increase has to be gradual. Commission has, decided on an
    increase in the rate keeping all these aspects in view. 9.11 Domestic: A large majority of consumers, more than a
    million, estimated to consume around 30% of the total sale projected are being levied at a
    much lower level of tariff, compared to their cost of supply. This pattern of consumption
    brings in an additional load, particularly during the peak load hours, where cost of power
    purchase is the highest, leaving apart the additional operational system problem for
    meeting larger peak. But, considering the interest of very small consumers for whom small
    amount of electricity is essential, Commission has proposed no rise in respect of
    consumers whose monthly consumption is less than 30 units per month. In respect of other
    volumes of domestic consumption, the Commission has approved a progressively higher rate
    of increase. 9.12 Industrial colonies: Power supply to industrial
    colonies, when drawn together with the industrial supply through a common meter under two
    part tariff, has in effect a demand charge component levied. Therefore, the energy charges
    for such type of consumption has been kept lower than that for supply to other residential
    colonies. 9.13 Subsidy: It is understood that OSEB was claiming
    revenue subsidy under the following heads: 
      
        Rural electrification operation. 
        Industrial policy resolution. GRIDCO have not shown any such subsidy in their tariff application. The
    Commission, has therefore, not provided for any subsidy in working out the revenue
    requirement of GRIDCO and presume that any loss of revenue sustained by the GRIDCO in
    complying with Government policy directions shall be claimed separately by GRIDCO under
    intimation to the Commission and the subsidy when received shall be passed on to the
    concerned consumer groups. GRIDCO have provided a lower rate for domestic consumers when
    such consumption does not exceed 30 unit per month. It is not clear, if consumption in
    this category includes Kutir Joyti connection numbering about 95,000 Nos. by the year
    1996. In case GRIDCO is incurring any revenue loss on account of such policy direction of
    the State Government, the loss could be quantified and subsidy claimed from the State
    Government. The Commission have not considered this in approving the tariff.   10.0 The Commission has had a difficult task
    and hard choices in finalizing the tariff. The transitional problems associated with the
    conversion of a protected industry fully under control of the Government to a competitive
    environment are enormous. The most important part of the regulatory control is tariff
    design which has a crucial link with investment incentive. The Commission is aware that
    the Regulators are required to approve a tariff design which must permit utilities to
    operate prudently and economically and to generate enough revenue to cover reasonable
    operational costs, taxes, amortization and a rate of return. But as in case of
    transitional phase in all developing countries, raising the price to even the cost level
    brings wide-spread discontentment and suspicion of the consumers. This discontentment is
    encouraged and enhanced by vested interests who have been benefitting from an inefficient
    and loss-making utility. The big task before the Commission is to convey the message that
    the price increase reflects the costs previously suppressed and subsidized by the
    Government. A short-term populist decision to defer any increase in price will bring in
    further deterioration in maintenance and services of electricity and will jeopardise not
    only industrial development of the State but also the supply of continuous and reliable
    power to existing customers. The Commission has therefore decided to balance on the one
    hand the interest of electricity industry in getting reimbursed for the increased cost of
    production and supply and on the other hand the financial impact on the consumers of all
    categories as would not be intolerable. Gridco has to realize that any increase in tariff
    has to be linked to performance and the consumers have to realise that the cost of supply
    of electricity like that of any other produced goods are liable to economic factors of
    increased cost and inflation. These compulsions as enshrined in the parameters set forth
    in Section 26(2) of the OER
    Act, 1995 have guided the Commission in setting a tariff design to be effective from
    01.04.97. We have linked the increase of tariff to efficient performance of Gridco and
    heave restricted the raising of price to the minimum level we consider reasonable and
    inevitable in the interest of consumers.   11.0 FIXATION OF TARIFF: 11.1 The Commission would like to conclude that it does not approve
    either Gridco's calculation of revenue requirement for 1997-98 or the tariffs proposed for
    different categories of consumers. The determination of licensee's revenue as considered
    reasonable by the Commission have been indicated in the earlier part of this order. 11.2 The Commission orders that tariff for supply of electricity for
    each category of consumers within GRIDCO's licensed area of supply, shall be as given in
    the table below with effect from 01.04.1997. TARIFF EFFECTIVE FROM 1ST APRIL 1997 
        
      
        | Sl.No | Category of
        Consumers | Voltage of tariff |   | Demand Charges Rs/KVA | Energy Charges P/KWH | Rebate Paise / KWH or DPS* |  
        | 1 | Domestic | 230/400V | Cons.<=30units/month |  | 90 | 10 |  
        |  |  | Cons.>30 units/month |  |  |  |  
        |  |  | 1st 75 units |  | 105 | 10 |  
        |  |  | Next 75 units |  | 150 | 10 |  
        |  |  | Rest units |  | 220 | 10 |  
        | Residential
        Colony | 230/400/11KV | ALL UNITS |  | 150 | 10 |  
        | 2 | Commercial | 230/400V / 11KV | All units if does not
        exceed: |  |  | 10 |  
        |  |  | a) 100 units/month |  | 245 | 10 |  
        |  |  | b) 300 units/month |  | 290 | 10 |  
        |  |  | c) if exceeds 300
        units/month |  | 320 | 10 |  
        | 3 | Irrigation | 230/400V / 11/33KV | All Units if does not
        exceed: |  |  | 10 |  
        |  |  | 150 units/month |  | 80 | 10 |  
        |  |  | If exceeds 150 units/month |  | 90 | 10 |  
        | 4 | Street Light | 230V/400V |  |  | 200 | DPS |  
        | 5 | Small Industry | 230V/400V |  |  | 215 | 10 |  
        | 6 | Medium Industry | 400V |  |  | 265 | DPS |  
        |  | 11KV/33KV |  |  | 255 | DPS |  
        | 7 | Public
        Institution | 33KV | All Units |  | 200 | DPS |  
        | 8 | Gen. Purpose | 11KV/33KV,
        CD=>110KVA and<555KVA | 200 | 230 | DPS |  
        |  | 33KV,
        CD=>555KVA and<1110KVA | 200 | 230 | DPS |  
        |  | 33KV
        CD=>1110KVA and <5000KVA | 200 | 250 | DPS |  
        |  | 132KV
        CD=>5000KVA | 200 | 250 | DPS |  
        | 9 | PublicW.W. | 11KV/33KV,
        CD=>110kVA | 200 | 230 | DPS |  
        |  | 230V/40V,
        CD<110KVA | - | 270 | DPS |  
        |  | 11KV/33KV,
        CD<110KVA | - | 260 | DPS |  
        | 10 | Large
        Industry | 11KV/33KV,
        CD=>110KVA and <555KVA | 200 | 230 | DPS |  
        |  | 33KV,
        CD=>555KVAand<1110KVA | 200 | 230 | DPS |  
        |  | 33KV,
        CD=>1110KVAand<5000KVA | 200 | 250 | DPS |  
        |  | 132/220/400KV,
        CD=>5000KVA | 200 | 250 | DPS |  
        | Colony | LTD TO 10% OF
        TOTAL CONSM. |  | 130 |  |  
        | 11 | Rly. Traction | 132KV/220V | 200 | 250 | DPS |  
        | 12 | Heavy Industry | 132KV/220KV | 200 | 250 | DPS |  
        | Colony | LTD TO 10% OF
        TOTAL CONSM. |  | 130 |  |  
        | 13 | Power Int. Ind. | 132KV/220KV | 200 | 250 | DPS |  
        | Colony | LTD TO 10% OF
        TOTAL CONSM. |  | 130 |  |  
        | 14 | Mini Steel Plant | 132KV/220KV | 200 | 200 | DPS |  
        | Colony | LTD TO 10% OF
        TOTAL CONSM. |  | 130 |  |  
        | 15 | Emg. PS to CPP |  | 300 | 260 | DPS |  
        | D.C. Services |  | RATE FOR
        D.C.SUPPLY |  
        | 16 | Domestic |  | RATE AT
        SL.1+25% SURCHARGE |  
        | 17 | Commercial |  | RATE AT
        SL.2+25% SURCHARGE |  
        | 18 | Small Industry |  | RATE AT
        SL.5+25% SURCHARGE |  * DPS as applicable   |  
  
    | 11.3 The Commission also authorises levy of other charges as given
    below: 
      OTHER CHARGES EFFECTIVE FROM 01.04.97 
      
        DEMAND CHARGEThe monthly Demand Charge will be calculated on
        recorded/evaluated Maximum Demand or 80% Contract Demand whichever is higher.
        MONTHLY MINIMUMThe Monthly Minimum Energy Charges
        ENERGY CHARGES for different category of consumers will be calculated
        on UNITS calculated as given: CATEGORY UNITS FOR MONTHLY MINIMUM ENERGY CHARGES Domestic 22 units per half KW of contract demand Commercial 23 units per half KW of contract demand Irrigation 31 units per BHP of contract demand for the months of June,
        July, August, September & October. 62 units per BHP for rest seven months. Street Light 30 units per half KW of contract demand Small Industry 56 units per KW or 42 units per BHP of contract demand Medium Industry 56 units per KW or 42 units per BHP of contract demand Public Institution 18 units per half KW of contract demand General Purpose P.F. of 0.9, L.F. of 0.2 on the contract demand. For
        the air conditioned cinemas for the months of November to March P.F. of 0.9, L.F. of 0.1
        on the contract demand Public Water Works CD => 110KVA P.F. of 0.9, L.F. of 0.2 on the
        contract demand Public Water Works CD < 110KVA 62 units per KW or 47 units per BHP
        of contract demand Large Industry P.F. of 0.9, L.F. of 0.2 on the contract demand Railway Traction P.F. of 0.9, L.F. of 0.2 on the contract demand Heavy Industry P.F. of 0.9 L.F. of 0.4 on the contract demand Power Intensive Industry P.F. of 0.9, L.F. of 0.4 on the contract
        demand Mini Steel Plant P.F. of 0.9, L.F. of 0.2 on the contract demand Emergency Supply to CPP Nil METERING ON LT SIDE OF CONSUMER'S TRANSFORMER.Transformer loss computed as given below to be added to
      the consumption as per meter reading. Energy Loss = 730 X KVA rating of transformer/100 Loss in Demand = One percent of the rating of
      transformer. (For Two part tariff) SUPPLY AT VOLTAGE OTHER THAN SPECIFIED VOLTAGE
        
      
        
          | Category of Consumer | Contract Demand | Specified Voltage | Increase in the rate of Demand
          Charges & Energy Charges in % of Supply Voltage |  
          | LT | 11KV | 33KV | 132 / 220KV |  
          | Domestic Bulk Supply | All | 1KV/33KV | +15 | --- | --- | --- |  
          | Public Institution | All | 33KV | +15 | +5 | --- | --- |  
          | Power Intensive Industry | 2000KVA and above | 132/220KV | --- | +10 | +7.5 | --- |  
          | Mini Steel Plant | 4444KVA and above | 132/220KV | --- | +10 | +7.5 | --- |  
          | Emergency PS to CPP | All | 132/220KV | --- | +10 | +7.5 | --- |  
          | Heavy Industry | 25000 KVA and above | 132/220KV | --- | +10 | +7.5 | --- |  
          | Railway Traction | All | 132/220KV | --- | --- | +7.5 (25kv) | --- |  
          | Large Industry & Gen. Purpose     | 110KVA and above but <555KVA | 11KV/33KV | +15 | --- | --- | -7.5 |  
          | 555 KVA and above but 132<5000KVA | 33KV | +15 | +5 | --- | -7.5 |  
          | 5000KVA and above | 132/220/400 KV | --- | +10 | +7.5 | --- |  
          | Small Industry | Less than 22 KVA | LT | --- | -7.5 | --- | --- |  
          | Public Water Works | 110 KVA and above | 1KV/33KV | +15 | --- | --- | --- |  DELAYED PAYMENT For Large Industry, Medium Industry,  SURCHARGE Public Water Works, Railway Traction, Street Light, Power
        Intensive Industry, Heavy Industry, General Purpose Supply, Public Institution, Mini Steel
        Plant, Emergency Supply to CPP, a DPS @ 2% per month shall be levied prorata for the
        period of delay from the due date i.e. from the 16th day of the bill, on the amount
        remaining unpaid, if the bills are not paid within 15 days of the bill. PENALTY FOR For Maximum Demand in excess of  OVERDRAWAL Contract Demand in a month, a penalty at the rate for Demand
        charges together with charges for supply at a voltage other than prescribed voltage shall
        be added. POWER FACTOR For Large Industry, Medium Industry,  PENALTY Public Water Works, Railway Traction, Power Intensive Industry,
        Heavy Industry, General Purpose Supply, Public Institution, Ministeel Plant, &
        Emergency Supply to CPP, a Power Factor Penalty shall be added as a percentage of monthly
        demand charges & energy charges as given below : 
        
          0.5% for every one % fall from 90% upto and including 60%Plus 
          1% for every one % fall below 60 upto and including 30%Plus 
          2% for every one % fall below 30%. EMERGENCY POWER The Demand charges shall be levied on SUPPLY TO CPP. recorded Maximum Demand. The existing
        provision of levy of Demand Charges on MD recorded over 25% of the rated capacity of the
        largest unit of the CPP shall be discontinued. TRANSMISSION TARIFF The Transmission Tariff for
        Transmission of power at 132KV/220 KV shall be as follows. 
        
          Out of Energy supplied to GRIDCO for transmission, 7.5% of the energy
          shall be deducted towards Transmission Loss and balance energy delivered at the delivery
          point at 132 KV/220 KV.
          A Transmission charge @ 40 paise/ unit on the energy received for
          transmission. LOAD FACTOR For unmetered supply or defective meter,
        billing shall continue to be at prevailing percentage of connected load.MONTHLY METER RENTMETER RENT IN RUPEES 1 Single phase electro-magnetic KWH meter 15.00 2 Three phase electro-magnetic KWH meter 30.00 3 Three phase electro-magnetic Trivector meter 500.00 4 Trivector meter for Railway Traction 750.00 5 Single phase Static KWH meter 50.00 6 Three phase Static KWH meter 100.00 7 Three phase Static Trivector meter 1200.00 8 Three phase Static Bivector meter 1200.00 9 A set of LT Current Transformer 75.00 10 11 KV Metering Unit without meter 600.00 11 33 KV Metering Unit without meter 900.00 12 EHT Metering arrangement without meter 2000.00 RECONNECTION CHARGES1 Single Phase Domestic consumer 30.00 2 Single Phase Other consumer 50.00 3 Three Phase LT consumer 100.00 4 HT and EHT consumer 500.00 
        Transmission Tariff: GRIDCO's application proposes a transmission tariff
        of 30 paise per unit after allowing the loss of 7.5% for the extra high voltage system. It
        is estimated that the marginal cost of EHT service excluding loss during the financial
        year 97-98 shall be about 37 paise per unit. The charge based upon marginal cost will
        promote efficiency in the use of the system and existing new users on transmission service
        should pay a charge equal to at least the marginal cost of providing the service. In
        addition, all users of GRIDCO system should make some contribution to the cost of
        non-technical losses on the system until these losses are brought under control. Based
        upon these considerations, the Commission have decided to set the transmission tariff at
        40 paise/kWh which is slightly more than the marginal cost of providing the service loss
        of 7.5% as applied for.
        Gridco is directed to take appropriate action in pursuance of this order.   -Sd/-(A.R.MOHANTY)
 MEMBER
 -Sd/-(D.K.ROY)
 MEMBER
 
   ANNEXURE - A Calculation of capital base and reasonable return for
    1997-98 [in accordance with para XVII of Schedule VI of Electricity (Supply) Act, 1948]. 
      
        | A | (Rs. in Crores)1997-98
 |  
        | a | Original cost of fixed
        asset | 2389.80 |  
        |   | Less consumers contribution | 200.10 |  
        |   |   | 2189.70 |  
        | b | Cost of intangible asset | --- |  
        | c | The original cost of Work
        in Progress | 370.30 |  
        | d | The amount of investment
        compulsorily made under para-IV | --- |  
        | e | An amount on account of
        working capital equal to the sum of |   |  
        |   | (i) Average cost of stores (1/12th of the sum of the stores materials
        and supplies including fuel in hand at the end of each month of the year) | 9.00 |  
        |   | (ii) Average cash and bank
        balance (1/12th of the sum of cash and bank balance
        whether credit or debit and call and short term deposits at the end of each month of the
        year) | 9.00 |  
        | Total of A | 2578.00 |  
        | Less |   |  
        | B |  
        | i | The amounts written off or
        set aside on account of depreciation of fixed assets. | 325.80 |  
        | ii | The amount of any loan
        advanced by Board | --- |  
        | ii-a | The amount of any loans
        borrowed from organisations or institutions approved by the State Govt. | 1101.40 |  
        | ii-b | The amount of any debenture
        issued by the licensee | 550.00 |  
        | iii | The amounts deposited in
        cash with the licensee by consumers, by way of security | 77.00 |  
        | iv | The amount standing to the
        credit of Tariffs and Dividends control reserve at the beginning of the year of account | --- |  
        | v | The amount standing to the
        credit of the Development reserve at the close of the year | --- |  
        | vi | The amount carried forward
        (at the beginning of the year of accounting) in the accounts of the Licensee for
        distribution to consumers. | --- |  
        | Total of B | 2054.20 |  
        | Capital Base
        (A-B) | 523.80 |  
        | Reasonable
        return @17% on Capital Base | 89.05 | 
 |  |