Case No. 29 & 30 of 2000
Present : Shri D.K.Roy, Chairman
Shri H.S. Sahu, Member |
Grid
Corporation of Orissa Ltd. . . . . . . . . . . . . . Petitioner |
Vs |
1.
|
Central Electricity Supply Company of Orissa
(CESCO)
|
2.
|
Western Electricity Supply Company of Orissa
(WESCO)
|
3.
|
North Electricity Supply Company of Orissa
(NESCO)
|
4.
|
Southern Electricity Supply Company of Orissa
(SOUTHCO)
|
|
Respondents |
5.
|
Orissa Hydro Power Corporation (OHPC)
|
6.
|
Orissa Power Generation Corporation (OPGC)
|
7.
|
Govt. of Orissa represented through Secretary,
Deptt. Of Energy.
|
|
Affected Parties |
Date of argument : 27.12.2000
Date of order : 16.03.2001 |
|
ORDER |
1.
|
M/s GRIDCO the holder
of Orissa Transmission & Bulk Supply Licence had filed one application for approval of
the re-scheduling of certain loans and issue of certain bonds and another application for
approval of its Financial Restructuring Plan (FRP). The Commission examined both the
applications and admitted these applications as Case No.29 and 30 of 2000. These
applications were filed in pursuance of condition nos. 10 & 11 of the Orissa
Transmission and Bulk supply license, which make it mandatory for the Licensee to obtain
written approval of the Commission for major investments and for disposal of assets in any
manner.
|
2.
|
As the subject matters
of both the cases were inter-linked, the Commission decided to hear and dispose of the
matter together. Both the Cases were accordingly heard together and are being disposed of
by this common order.
|
3.
|
In the case no.30 of
2000, Financial Restructuring Plan (FRP) the applicant, M/s GRIDCO had arraigned the four
Distcos as respondents and accordingly the Commission issued notices to them to appear and
file their replies. As the FRP proposed by the applicant has major implications for all
stakeholders, the Commission decided to implead the generating companies of the State
i.e., OHPC & OPGC as well as the State Government as affected parties in this case.
|
4.
|
The respondents and
the affected parties appeared before the Commission, filed their replies and put forth
their respective arguments. The Commission heard the respondents and the expert views of
the Director (Tariff), OERC and carefully considered the applications, the replies
supported by relevant documents and the arguments advanced by the parties.
|
5.
|
The licensee M/s
GRIDCO is passing through a serious financial crisis and is in acute need of infusion of
fresh capital. The applicant has felt that the up-valuation of assets at the time of asset
transfer during the formation of GRIDCO from OSEB, has been the primary reason for the
current financial crisis. The facts preceding the FRP application may be restated to put
the case in proper perspective.
|
6.
|
The transfer of assets
from OSEB to GRIDCO was carried out after the revaluation of the same, thus leading to an
increase in the revenue requirement of GRIDCO in subsequent years, due to additional
depreciation on the capitalized assets, enhanced requirement for operations and
maintenance costs, increased employee costs and return on revalued capital base.
|
7.
|
This also meant that
the Govt. of Orissa, could adjust its dues to GRIDCO, against the notional receipts to
itself, through this transfer. It was believed at that point in time, that subsequent
performance improvements would ensure the viability of GRIDCO and the newly formed
Distcos. It is obvious that expectations have been belied and performance improvements
have not materialised. The transfer process was structured in a fashion, where the Govt.
of Orissa, offset its dues to GRIDCO, against the upvaluation amount, and consequently
wrote away Rs. 340 crores of power bills and unpaid subsidies, which otherwise would have
accrued to GRIDCO. The power purchase liability
amount of Rs. 318.7 crores (Rs. 465.5 cr. Accounts payable netted off against the Rs.
146.8 cr receivables), of OSEB was transferred to GRIDCO, which started off commercial
operations, with this liability figure. |
8.
|
It was stated by
GRIDCO that on account of the initial cash deficit and obligation to service substantial
fresh debt and bonds, it was driven to the wall by the creditors necessitating a series of
measures including issue of bonds through private placement (Rs. 310 crores), issue of
bonds to generators (Rs. 360 crores) and rescheduling of loans of the power finance
corporation (PFC) and Rural Electrification Corporation (REC). It is admitted by GRIDCO
that these palliatives only served to postpone the day of reckoning and GRIDCO has landed
itself in a debt trap.
|
9.
|
The Board of GRIDCO
noted that its cash deficit for 1999-00 would go upto Rs. 500 crore and that options much
as raising more funds from the open market, approaching generation companies for further
conversion of overdue payments to bonds or approaching the state govt. for loans, grants
or subsidies were no longer available to GRIDCO. Hence it felt the need for an overall
financial restructuring.
|
10.
|
The FRP has been
designed on the basis of assumptions in the following aspects:
transmission losses,
-
reductions in distribution losses by the Distcos,
-
changes in costs of power purchase,
-
capital investments both ongoing and planned,
-
addition of generation capacity and
-
likely Bulk Supply Tariff increases over the period under
consideration.
|
11.
|
The plan assumes
assistance from all the stakeholders, namely the National Thermal Power Corporation,
financial institutions, state generating stations, state govt. and central govt. The
support envisaged is in the form of a reduction of obligations to these, concessions in
terms of sale, issuance of bonds to these entities by GRIDCO, in lieu of financial
obligations, and certain concessional provisions to be made by the Govt. of India.
-
The generators will defer the collection of receivables from GRIDCO
by accepting long-term bonds, and DPS would be waived.
-
Power Finance Corporation and Rural Electrification Corporation will
reschedule their loans and these will be refinanced by tax-free bonds.
-
The Govt. of India would have to allow tax-free status to these
bonds.
-
The distribution companies would have to reduce the T& D losses
and make timely payments of bulk supply bills as well as timely repayment of loan interest
and installments on the basis of the back-to back arrangements.
-
Government of Orissa would guarantee the bonds and also provide cash
support over 5 years towards accumulated defaults and to cover cash deficits remaining
after these measures.
-
OERC would be approached to increase the tariff at a desired rate.
|
12.
|
The following are the
salient components of the amended FRP presented to OERC by GRIDCO
i. Dues
to Central Generating stations to be securitised by issue of tax free bonds |
Rs. 600
crores |
ii. REC
and PFC loans to be discharged by issuing tax free bonds with state Govt. guarantee |
Rs. 800
crores |
iii.
GRIDCOs dues to state owned generating companies |
Rs. 560
crores |
a. Rs.
360 crores of the dues to the state govt. and OHPC would be managed through the issue of
tax free bonds with State Govt. guarantee. The balance would be paid out of soft loans
receivable from the World Bank.
|
b. The
WB would be approached to provide another Rs. 200 crores for managing deficits until the
turnaround of GRIDCO.
|
|
13.
|
Besides these certain
other measures as a part of FRP have been approved in the 52nd meeting of the
Board of GRIDCO. These are as follows:
-
Rs. 340 crores taken out of GRIDCO at the time of the first transfer
scheme, would be reinvested in GRIDCO, by disinvesting OPGC and OHPC equity.
-
Set off of government dues against corresponding GRIDCO dues
-
Conversion of zero coupon bond to equity
-
Reduction of staff strength by 10%
-
Waiver of DPS and penal interest
|
14.
|
GRIDCO had
submitted the following main documents for the FRP :
-
projected financial statements upto FY 09-10.
-
Detailed investment schedules and justifications for the same
As per these:
-
GRIDCO would turnaround in the FY 04 and earn profits of Rs. 98.7
crores for the year.
-
Gross assets would be increased by Rs. 2141.9 crores from Rs.1426.6
crores as on 99-00 to Rs. 3571.5 crores by 2010.
|
Presentation
by affected parties
|
15.
|
The first
hearing on the FRP was held on the of 8th November, 2000 during which the
following views were expressed:
-
The OPGC expressed its inability to accept the proposal given by
GRIDCO, stating that the issue of bonds by GRIDCO to itself was not an attractive
proposition. It also maintained that the waived of DPS and penal charges on non-payment of
dues was not an option it was considering.
-
The OHPC submitted a response to the FRP stating that despite being
the cheapest power supplier to GRIDCO, its dues were mounting and that GRIDCO, was
honouring liabilities of other suppliers like NTPC, OPGC, etc. prior to paying the dues of
OHPC. The total outstanding as on 31st October, 2000 stood at Rs. 400.40 cr.,
and since there is no inflow of funds, from GRIDCO, and no commitments of early settlement
of dues, the FRP would put additional burden on the finances of OHPC.
-
Southco in its written submission has stated that FRP assumes an
indicative profile of Bulk Supply Tariff (BST) for the next 5 years, which in
Southcos view amounts to a multi-year tariff and a violation of Section 26 of OER
Act. It does not agree to the claim that the 10-15% increase p.a. in Bulk supply tariffs
in the first 4 years will have no impact on the retail supply tariffs. Hence Southco
prayed the Commission not to consider any BST increase, and to consider giving
clarifications for the amount of new loans, interest for which could be passed through in
future tariff applications.
-
Southco reserved the right to estimate load growth on a year-to-year
basis at the time of filing of the revenue requirements, and did not accept the figures
quoted by GRIDCO.
-
Southco disputed the loss reduction figures quoted by GRIDCO, and
offered the following loss reduction targets: 3% p.a. for the first 3 years and 2 % p.a.
in the 4th and 5th years. Further it wanted the surplus generated by
this loss reduction to be allowed to itself to service loans for capital expenditure,
system improvement, own incremental expenditure and unabsorbed losses. It prayed the
Commission not to allow GRIDCO, to build in or claim any surplus generated out of
distribution loss reduction by Southco in the FRP.
-
Southco has challenged the capital expenses of GRIDCO of the order of
Rs. 1315 crores as against the capital base of Rs. 1155 cr., without any corresponding
increase in energy procured for distribution companies. It held that any investment
designed to sell power to third parties other than distribution companies, should not be
increasing the cost burden of the distribution companies in terms of the BST. The cost of
assets not used or not productive should be written off by GRIDCO, and not loaded on to
the Distribution companies.
-
Southco also held the view that the disputed dues of the distribution
companies with GRIDCO should be resolved as per procedure, which would resolve the cash
deficit problem of GRIDCO. The undisputed amounts could be squared by the issue of bonds
by the distribution companies, which could be then reassigned by GRIDCO, on to NTPC. In
light of all the above, Southco wanted the rejection of the FRP.
-
WESCO and NESCO held similar views on the FRP.
-
CESCO held that the loss reduction programme envisaged by GRIDCO was
too ambitious. It contended that if all the assumptions taken by GRIDCO were fulfilled,
CESCO might be able to achieve a loss reduction of 2.5% p.a.
-
The govt. of Orissa, held the view that given the current financial
situation of Orissa, it would be extremely difficult for it to infuse any equity into
GRIDCO or to intervene financially.
|
Views
of the Consultants on the FRP
|
16.
|
The Commission
appointed M/s Verve Consulting Pvt. Ltd. for examining the various aspects of the
Financial Restructuring Proposal. The Consultants carefully studied the FRP, its
assumptions and its utility and the consequences of the same. After taking into account
the analysis made by the consultants, the Commission formulated a set of queries for the
respondent.
|
17.
|
Verve Consulting
in its draft report made the following observations on the FRP:
-
FRP in its current form is not a proper deficit-financing model as it
is merely relying on loans to discharge liabilities. The use of the loans for achieving
efficiency gains through investments in technology upgradation, (spending not merely on
meters but also improving grid interconnectivity, and hence creating opportunities for
interstate sales) appears to be missing.
-
The time period, for which projections have been made, seems to be
too short considering that some of the loans are being infused in mid-course (additional
borrowings in year 01 and 02) and that repayments are starting late in the projection
period.
-
Since the FRP has far reaching ramifications all the stakeholders
should have been involved. All the distribution companies in the hearing have challenged
the assumptions made by GRIDCO specifically in regard to the projected performance of the
Distcos.
|
Transmission
Loss
|
18.
|
Transmission
loss in GRIDCO has been projected at 4.86% for FY 00 (since actual data is not available
as yet) and at 5.30% for subsequent years. This in the opinion of the Consultants is too
high and is not reflective of the system improvement investments, expected to be made, as
well as those already in motion. The OERC has recommended loss levels of 3.7% as normative
transmission losses to be applicable from the year FY01.
|
Load Growth |
19.
|
The load growth
is not commensurate with the increase in capital investment. A calculation of the demand
forecasts from FY00 to FY10 suggests that load growth is 8.3% for the year 2004, which
does not match with realistic projections.
Year |
FY
00 |
FY01 |
FY02 |
FY03 |
FY04 |
FY05 |
FY06 |
FY07 |
FY08 |
FY09 |
FY10 |
Distco
Sales |
5,758 |
5,918 |
6,088 |
6,376 |
6,903 |
7,013 |
7,275 |
7,551 |
7,866 |
8,259 |
8,672 |
Incr% |
|
2.8% |
2.9% |
4.7% |
8.3% |
1.6% |
3.7% |
3.8% |
4.2% |
5.0% |
5.0% |
There is an aberration in BST for FY 2000, with BST
calculated being Rs. 1.22 whereas that used for the model is Rs. 1.28. Besides the final
projected BST appears to be very high. The application for BST for the year 2001-02 made
to the Commission (@ Rs. 1.79 per unit of power purchase), also does not match with the
figures given in the FRP (Rs. 1.58 for FY 2001 and Rs. 1.76 for FY 2002). |
Loss Reduction |
20.
|
Assumptions on
reduction of Distribution loss, have not been agreed to by the Distribution companies (as
shown in their prayer to commission) on behalf of which GRIDCO has set the assumptions and
they considered these reduction targets as unrealistic.
|
Loans |
21.
|
Loan retirement : The loan retirement plan is to be analyzed as the
costs of the various loans would dictate the priorities of GRIDCO. However the DSCR has to
be maintained at a healthy level to enable the same. The interest costs for all the loans
need to be calculated to ensure the accurate computation of the loan retirement strategy,
and as has been mentioned earlier, the interest computations given are incorrect.
|
22.
|
Debt Service
Coverage Ratio (DSCR): Any DSCR of less than 2.0 is worrisome for any financing
institution. The current FRP suggests that the moment turnaround is achieved, the debts
are going to be retired, en masse, which leads to DSCRs as below.
-
This obviously implies that the earning potential of GRIDCO is being
utilized to retire debt too hastily in the period FY 06-10, whereas prior to this period
there is inadequate earning potential. It also means that there is a mismatch in the term
of the loans, as loans are taken in a period, when there is an inability to service them.
-
Besides the implications of the earlier comments are that earning
levels are going to be lower, as the allowable losses by the commission, have been usually
lower than that achieved. Hence the utilities while working with higher losses will only
have allowable losses to pass on to consumers, leading to lower margins and hence lesser
debt serviceability. Hence we might have to work with an even lower DSCR, than that
presented below.
Year |
00 |
01 |
02 |
03 |
04 |
05 |
06 |
07 |
08 |
09 |
10 |
DSCR |
0.5 |
0.2 |
0.7 |
0.6 |
0.8 |
0.9 |
1.5 |
1.6 |
1.4 |
1.7 |
4.1 |
Based on these
deliberations, the commission raised the following queries for the respondents: |
Queries |
23.
|
Based on the
analysis of the consultants the following queries were made by the Commission to GRIDCO on
the 29th November 2000 on the FRP.
-
Whether GRIDCO had explored equity infusion alternatives ?
-
What were the alternatives for liability reduction of GRIDCO
?
-
What were the short and long term measures contemplated by
GRIDCO for power inter-state exports?
-
The load growth projection by the Distcos from 99-2000 to
2010 is of the order of was only 12.96% against a projected fixed asset addition of 170%.
Hence what degree of restrictions can be imposed on investments so as not to burden
consumers ?
-
Without significant load growth, whether loan funds could be
used to retire other expensive debt instead of asset building ?
-
Whether GRIDCO had received assurances from related sources
about waiver of DPS/ Penal interest from generators/ FIs as stated in the FRP ?
-
Whether the investments could be prioritised to give
importance to power exports rather than internal strengthening ?
-
The legality of the tax free bonds and the precedents if any
were required to be furnished.
-
The impact of the BST on the retail tariff needed to be
reexamined.
-
The interest calculations for loans alongwith the basis of
interest calculations as well as the repayment schedules was required
-
The calculations for gross block, depreciation and net block
and capital WIP did not add up
-
Are VRS costs included in the employee cost calculations or
not ? The financial effects of attrition of employees was required
-
The repayment ability of GRIDCO in the event of adverse
change in earnings leading to inability to service debt needs analysis
-
Transmission loss is above normative levels and hence the
effect of system improvements on technical loss needed to be demonstrated alongwith
variance from norms
-
The basis of employee costs, A&G costs to be given
-
The latest audited accounts are required to be submitted
|
Clarifications from GRIDCO
The following clarifications were received
from the respondent on 19th December 2000. |
Equity
infusion
|
24.
|
GRIDCO had requested
Government of Orissa (GoO) to convert Rs. 400 crores zero coupon bonds into government
equity in GRIDCO. The Secretary (Energy) has indicated to the Board of GRIDCO that the GoO
has agreed to this. The high-powered committee of the
Ministry of Power of Government of India (GoI) in its interim proposal had recommended an
infusion of Rs. 340 cr. through equity or soft loans, ensured through direct GoI payment
to NTPC by deductions from Central Plan Assistance (CPA) over and above the existing 15%
ceiling on CPA cuts in case of GoO default. This money could be raised through divestment
from OHPC/ OPGC and failing this the earlier mechanism could be enforced. |
25.
|
Dis-investment
does not seem to be a realistic proposition given the un-viability of the sector. Further
dis-investment in the distribution companies would not raise significant cash given the
current poor performance of the Distcos and the low levels of equity holding of GRIDCO in
these (39%).
|
Power export
|
26.
|
The sale to
other states is contemplated at the current levels till 2010, as it is not contemplating
new interstate lines. It has negotiated a deal only with AP, although it has connections
with MP and West Bengal too. GRIDCO is now focussing on improving internal systems, though
it is willing to consider investments in EHT lines if other states are willing to commit
to purchasing power from GRIDCO.
|
Load growth |
27.
|
Statistical
calculations between 1974 and 2000 indicate a load growth of 68.4%. The growth between the
years 1991 and 2000 is 81.5%. (Reference: Annexure I of Clarification to queries submitted
by GRIDCO vide letter no. dated 19th December 2000). A conservative load growth
estimate of 12.96% has been assumed from 2000-2010. These projections have been made in
the absence of any projections made by the Distcos. The loss reduction figures have also
been assumed by GRIDCO, at an annual reduction of 5% for 3 years and 2.5% for the
subsequent 2 years. The base figure for losses are
the actual loss figures reported for the year 2000. The power procurement from generators
by GRIDCO was based on the energy requirement of the Distcos. |
Asset building
|
28.
|
The 400 kV and
220 kV lines have enough loading currently with much lower substation loads and new line
and substations at 132 kV to reduce the losses in the excising 33 kV lines are required.
|
29.
|
About 75% of the
capital expenditure upto FY05 are towards a few critical projects, planned for
contingencies as well as for long term sectoral benefits, for providing crucial evacuation
facilities (thus lowering the cost of power procurement). GRIDCO however seeks the
approval of OERC for the same. Capital expenditure beyond FY05 is assumed at a normative
value of Rs. 90 crores.
|
30.
|
The process of
construction of EHT lines and substations takes about 5 years, and hence procurement
action has been initiated on the same, on the basis of the report prepared by Monenco Agra
on the line requirements, with funding from REC, ADB, OECF, PFC, HIW, DFID and from
internal resources. The criterion for design of the Transmission system is on a single
contingency basis, i.e. on the outage of any single element, the system performance should
continue to be satisfactory, without the need for load shedding and with voltage within
permissible limits at any of the substations.
|
31.
|
The existing
voltages in the GRIDCO stations are lower than the permissible limits, thus necessitating
the immediate strengthening of the system. Data supporting this has been furnished by
GRIDCO, with the voltages at the 132 kV and 132 kV substations given as per which 9 nos.
132 kV substations and 4 nos. 220 kV substations are operating below these limits.
|
32.
|
The details of
the capital expenditure works undertaken by GRIDCO have been given by GRIDCO. The
necessity of the following have also been given as follows:
-
220 kV Ib TPS- Budhipadar
This is required for evacuation of generation capacity at Ib when the second stage of
generation capacities comes up. The existing double circuit 220 kV line needs to be
augmented to manage the entire generation capacity.
-
400 kV Chandaka-Meramandali
The available voltage being lower than permissible, this will strengthen the supply and
prevent voltage collapse.
400 kV Ib to Meramandali
-
This is under construction and will help remove the system
collapse in the event of outage of one of the 2 existing TTPS-Bhanjanagar 20 kV lines.
-
220 kV Budhipadar-Bolangir
This double circuit line will reinforce the power supply at Bolangir currently supplied by
a single circuit 132 KV line.
|
33.
|
GRIDCO has also
provided data highlighting the need for augmenting transformer capacities at a number of
substations, with a view to increasing the reliability of power supply.
|
Liability reduction |
34.
|
GRIDCO has
expressed the view that it has continuously been trying for waiver of DPS and reduction of
penalties with the central PSUs, and this has culminated in the committee of the Ministry
of Power (MoP) asking for waiver of penalties and DPS by all the central PSUs. However the
PSUs are apprehensive of setting a precedent in Orissa, which could be used by other
reforming states to reduce their dues to these PSUs. This view has been publicly expressed
by the PSUs. However GRIDCO has managed to obtain settlements in its favour with regard to
DPS and a waiver of 25% of the same from NTPC. It has also managed to reschedule its loans
with REC/PFC.
|
Rescheduling of investments |
35.
|
There is
no avoidable investment by GRIDCO and it is GRIDCOs view that reliable power supply
can not be continued with the current state of the system, unless fresh investments are
made.
|
Legality of tax-free bonds
|
36.
|
There is
no similar precedent. However GRIDCO is optimistic after its negotiations with MoP and
DEA. The Secretary DEA has ruled out other alternatives and has conceded that this seems
to be the only viable alternative, in the inter-ministerial committee in which the Finance
ministry has also been represented. GRIDCO has also pointed out that there is no cash loss
to the GoI as only a potential opportunity of gaining from tax would be lost as there
would be no bond issue otherwise and hence no tax receipts from the same. The tax-free
nature of the bonds would also improve their marketability thus providing larger benefits
to the bond issuing entities.
|
BST-Retail tariff |
37.
|
The assumptions
on this topic as made by GRIDCO are as follows :
-
Costs other than power purchase are 30% of the total costs of the
Distcos
-
No increase in these other costs have been assumed for the next 10
years.
-
A decrease in distribution loss percentage of 5% p.a. for the first 3
years and 2.5% for the subsequent years till the overall loss percentage reaches 20%
GRIDCO has shown the impact of a rise in BST on the retail
tariff in its reply. |
Interest calculation |
38.
|
The interest
calculation details have been furnished by GRIDCO.
|
Fixed Asset Mismatch |
39.
|
The
corrected Funds flow statement reflecting all the details of the gross block, interest
capitalized, net block, depreciation and capital work in progress have been furnished.
|
Employee costs |
40.
|
Staff reduction
in the next 3 years shall only be through natural attrition and no VRS scheme has been
proposed. The employee costs increase annually by 6% with an intermittent 15% increase
every 5 years to take care of fitment and wage revision.
|
41.
|
The details of
the basis of the employee costs, A&G costs and the interest calculations are based on
the FY98 audited accounts and the management accounts of FY99 and FY00
|
Debt
Service Coverage Ratio
|
42.
|
The average DSCR
is 1.56 over the period FY00 to FY10, with a DSCR of 4.3 in FY10.
|
Transmission loss |
43.
|
The transmission
loss of 5.3% of the FRP has been calculated on the net basis which equates to a 4% loss on
gross basis. Further changes have not been taken into account.
|
Observations
of the Consultants on the Clarifications
|
44.
|
The impact of
BST on retail tariff as has been presented in the Clarification, shows some interesting
figures. There is a huge increase in units sold in the year 2004, which has not been
supported by any significant load growth in the power sector in Orissa. The subsequent BST
increase in FY 2006 also appears to be justified only by the induction of fresh generating
capacity through IPPs, which at this point of time appears uncertain at best. It is
interesting to note that the calculations given by GRIDCO does not take into account the
implications of the Bonds to be issued to the tune of Rs. 960 crores, as given in the FRP.
The impact of the bond servicing costs is bound to affect the BST dramatically and in fact
could significantly alter all the projections given in the FRP.
|
45.
|
The loss
reduction targets set for the Distcos in the FRP are unrealistic especially in the light
of the performance in this regard till date. The Commission has allowed level of 34%
T&D losses to the Distcos in their tariff applications, for FY 01, owing to the poor
compliance with earlier targets. Hence non-compliance by the Distcos to these loss levels
would imply the failure of the model used in the FRP or would necessitate large tariff
rises.
|
46.
|
The FRP can even
be seen in the light of realistic and achievable performance parameters set for Distcos,
which would fundamentally alter the financial projections. The calculations for the same
are given in the Annexure, based on a possible alternative scenario for Bulk supply
tariff. In the event of loss projections being higher than given in the FRP, and taking
the Commissions approved loss figure of 31%, and a progressive reduction of 1% p.a.,
the domino effect of this, create a series of opportunities. On the one hand, Distcos are
given realistic targets to achieve in terms of distribution and transmission losses, and
are incentivized for performances surpassing these benchmarks, leading to a creation of
repayment ability. This would also help them clear outstanding liabilities especially in
the context of term loans and power purchase dues. On the other, GRIDCO, would have a
larger power purchase requirement, due to the larger no. of units of power required to be
sold to the Distcos. Taking into account, the contribution of every additional unit of
sales, a larger volume of sales would translate into, lower bulk supply tariffs, and
better revenue streams. The cash flow management would also be eased, as the requirement
of funding for shortfalls and accrued liabilities could be reduced through this improved
revenue inflows.
|
47.
|
The impact of
the earlier scenario is far reaching in terms of the overall FRP. The current FRP,
projects a healthy GRIDCO by the year 2006. This coincides with the commencement of the
repayment of the large quanta of borrowing from the World Bank and other sources. Hence
any fresh liabilities undertaken during he current financial as proposed in the FRP, would
be offset by the larger earning potential in 2006. However in the revised plan, as
presented in the Annexure, there is a smaller requirement for the borrowings envisaged
leading to lower burden of debt for the consumer, and hence lower revenue requirements for
GRIDCO and consequently lower BST. The Debt
Service Coverage ratios improve considerably in the period 2000-2006, leading to a
creation of ability to repay the current debt and not to reschedule the same to a later
year, thus creating a leaner financial profile for GRIDCO. In the event that Distcos can
manage a better loss reduction programme, the benefits of the same can be utilized by them
to prepay their contingent liabilities and improve sectoral health. |
48.
|
The current
deficit of GRIDCO is partly due to the lack of punctual repayments by the Distcos. This
aspect is expected to be remedied, after better implementation of the escrow mechanism,
which did not function in the desired manner, for the first few months. It is expected
that some of the shortfall in funds will be met from the accumulated dues of the Distcos
and this will yield substantial relief to GRIDCO.
|
49.
|
The schedule of
investments detailed out by GRIDCO, would have to be accepted in the absence of more
substantive data, but GRIDCO is advised to carefully weigh the merits of each investment
proposition, as it is felt that system security, which is what is hoped to be achieved,
through these investments should not be established only through elaborate transmission
networks which remain significantly underloaded. A thorough load flow analysis needs to be
carried out for these HT and EHT lines planned, along with contingency plan for
maintaining system stability for unanticipated events and developments.
|
50.
|
It is the
Consultants opinion, that the Current FRP, be amended suitably with realistic performance
benchmarks and subsequent revision of all the projections. However this is contingent upon
GRIDCO, achieving the stipulations laid down by the Commission, vis-à-vis Transmission
losses, managing the current deficit through issuance of bonds, conversion of bonds into
equity and securitisation of outstanding liabilities. As is evident, the process of
convergence towards ideal performance targets, is gradual and each step is arduous. Hence
it would be unwise on the part of the Commission to guarantee financial packages based on
current performance and each decision of the Commission would have to be contingent on the
situation prevalent, to ensure the best deal for all stakeholders in the sector.
|
ABT
and its impact
|
51.
|
Availability
based tariffs are expected to be introduced by May 2001 in power sector in India. This is
going to have far reaching implications for all the players in the sector. We present
below a comparative picture of the existing system and how it is likely to change in the
event of introduction of ABT.
|
52.
|
Under the ABT
regime beneficiaries may transfer part of their allocated share for a specified period to
other states. Consequently, GRIDCO has to aggressively promote inter-state sales as it
could have a surplus in years of slow load growth. After ABT, the central sector power (in
this case NTPC) is also likely to change significantly. Therefore GRIDCO will have to
analyse options on surrender of costly power unless long term trading can be ensured at
appropriate price.
|
53.
|
Optimal
forecasting of advance day schedules and committing to it will warrant investments in
forecasting, dispatch and monitoring systems apart from accurate metering of consumption.
The issue of ABT has not been factored into the FRP and might prove to be critical in the
final analysis.
|
Deficit
financing
|
54.
|
The FRP has been
designed to infuse cash into a cash-starved company, with a bright foreseeable future,
given the right operating conditions. The cash is to be infused only in the form of
borrowings, though book adjustments are sought through the conversion of govt. bonds into
equity. However the reasons for the deficit and the current burden of liabilities are not
difficult to find. A significant proportion of the deficit is the legacy of GRIDCO prior
to privatization of distribution. The deficit has burgeoned thanks to the inability/
unwillingness of Distcos to pay their legitimate dues to GRIDCO. However it is the view of
the Consultants that GRIDCO, can not seek relief for the imperfections in performance
during the period from April 1, 1996 to March 31, 1999 for the 3 distribution companies
WESCO, SOUTHCO and NESCO and till August 31 1999, for CESCO, during which time it managed
the power distribution business in the state along with its current activities in
transmission and load dispatch.
|
Observations of the Commission |
55.
|
The Commission
has carefully looked into the proposals for financial restructuring and for the
rescheduling of certain loans and bonds made by GRIDCO to tide over the financial crisis.
The views and analyses of the consultants were discussed at length with the licensee
through technical meetings at the level of the Director (Tariff) and subsequently all
important issues were raised during the open hearings. It is as clear as daylight that
GRIDCO is in a debt trap, from which it has to find a structured solution and hence a
proposal for FRP is an understandable step. Before we record our observations, on some of
the specific components of the FRP and pass our orders, it is appropriate to give our
observations on the genesis of the financial problem necessitating the FRP and whether the
problem could have been avoided or its dimensions diminished. Our observations are called
for in pursuance of the mandate under the OER Act, 1995 and particularly Section 11 of the
Act to regulate the working of the licensees and to promote their working in an efficient
economic and equitable manner
|
56.
|
56.1 We agree with the petitioner GRIDCO that the cash problems of GRIDCO
started at the moment of its birth when the GoO upvalued its assets by Rs. 1153 crores and
adjusted a good part of receivable against the dues of the state govt. and passed on to
GRIDCO, payables to NTPC and other creditors on 1.4.96, amounting to Rs. 465.5 crores.
56.2 Secondly the financial modelling in the reform
programme had an inherent flaw with regard to the assumption on prevailing levels of
T&D loss, the pace of reduction in T&D losses, possibility of improvement in
revenue generation in the short term and the load growth in the sector. In this context,
we look at the projections made in the Staff Appraisal report (SAR) dated April 1996 by
the World Bank and corresponding projections by GRIDCO in the FRP.
Loss
Target |
1997 |
1998 |
1999 |
2000 |
2001 |
2002 |
System
Loss Target as per SAR |
40% |
35% |
30% |
25% |
23% |
22% |
System
Loss As per FRP submitted by GRIDCO |
52%
(Actual) |
48%
(Actual) |
46% |
40% |
35% |
30%
|
T&D losses will reach a target level of
20 percent in FY 06 as per the FRP, which is a postponement of SAR objectives by 5 years.
Even so, these loss reduction targets have not been acceptable to the Distcos as they
consider it too ambitious.
Debt
service |
1997 |
1998 |
1999 |
2000 |
2001 |
2002 |
DSCR
Target as per SAR |
1.5 |
1.5 |
1.5 |
1.5 |
1.5 |
1.5 |
DSCR As
per FRP |
0.3 |
0.4 |
0.3 |
0.5 |
0.2 |
0.7 |
56.3
We are constrained to observe that the congenital financial problem has aggravated due to
the inadequacy and inability of GRIDCO, to function as a corporatised licensee, to take
corrective measures for arresting the downslide and for taking proactive steps for its own
financial viability. It continued to function more or less as a wing of the Govt., without
concern for its own finances, it took up responsibility for unremunerative distribution
related work and it bore the burden of loans and payables to make the divestment process
attractive to the private investor. The writing on the wall was quite clear with regard to
the unviable nature of the financial model handed down by the SAR. The T&D losses did
not go down as expected, load growth did not materialize, the internal burden kept on
rising and the distribution companies did not pay their dues and the tariff rise granted
by OERC was short of expectations. These should have led to the reassessment of its
strategy, rescheduling of investments, economy in expenditure and proper asset management.
It is quite clear that the hesitant release of World Bank funds from the govt. of Orissa,
and procedural bottlenecks have handicapped GRIDCO. But on its part it did precious little
to improve its managerial efficiency and financial viability.
56.4 The main objectives of reform, to make the
sector financially viable so as to attract private capital and to relieve the Govt. of the
burden of investment and subsidy are bound to be defeated if fund management and asset
management are regulated to secondary place. It is unfortunate that this has happened for
very many reasons, not the least being GRIDCOs continuation of "business as
before" approach and failure to imbibe corporate philosophy and corporate strategies.
It is also a fact that the distribution companies did not help matters and that allocation
of all the risk and responsibility by the Govt. of Orissa, to GRIDCO was the bane of
GRIDCO. GRIDCO has not been able to get the benefit of an undiluted commercial
relationship with the Distcos because it holds 49% of the shares of these companies, the
chairman of both GRIDCO and the Distcos is common and GRIDCO has been the medium of
communication and financial dealings of the Government with the Distcos. The structural
unbundling of transmission and distribution has been diluted and enforcing accountability
has become difficult Trady Payment of electricity charges by Government Departments has
contributed to the malaise.
56.5 Having observed all that with regard to the
genesis of the financial problem, we however agree with GRIDCO that loans are to be
rescheduled and the FRP needs to be approved so that Reform is brought back on the rails.
A decision in this regard brooks no delay because of
the essential nature of the product we are regulating and the inherent monopoly in
providing service to the consumers of the state. |
57.
|
The Financial
restructuring plan as proposed by GRIDCO will leave GRIDCO with negative networth and a
very large debt burden. As per financial projections if all goes right, as proposed by
GRIDCO, it may have a positive net worth in the FY 04-05. However we find that the
requirements for this scenario are extremely demanding and tough to fulfill in the current
climate.
|
58.
|
As pointed out
in the last tariff order, it is not reasonable to burden the present consumers on account
of the past and present inefficiency of the licensees in realizing their dues. Further the
licensees will not be able to match expectations if they do not follow the guidelines
incorporated in the tariff order. For example we have fixed the overall T&D loss at
34% for FY 2002. Similarly we have reiterated the order about the ceiling on various items
of expenses the licensee should incur for transmission and supply of electricity.
|
59.
|
Non-conformance
with the earlier orders of the Commission and spending beyond the realistic levels, have
led to the licensee incurring heavy losses. The FRP represents an attempt for the
securitization of the same. This is because, the additional liabilities being proposed are
all geared towards meeting fund requirements and not so much towards fresh investments.
|
60.
|
While accepting
FRP for mitigating past losses and getting GRIDCO to improve its viability, capital
investments as proposed by GRIDCO may not be accepted in totality. It is seen from the
financial projections that GRIDCO has loaded investments on the system without
proportionate revenue growth. Projected capital expenses should not be construed as
approved unless they are vetted by the Commission and unless cost-benefit analyses as per
the license condition are carried out.
|
61.
|
The Commission
has noted the following errors and omissions in the FRP presented by GRIDCO :
-
The calculations for the FRP is flawed, as it does not include the
financial impact of the tax free bonds of Rs. 960 cr. proposed by GRIDCO. On the other
hand Gridco proposes additional Rs 1560 crores as additional borrowings without indicating
the source of funds and the rate of interest.
-
The transmission loss level assumed by GRIDCO is at 5.3% as opposed
to the benchmark level of 3.7% fixed by the Commission.
-
The provision for bad and doubtful debts has been treated as an
operating expense, which is not allowed by the Commission for transmission companies.
-
The net receivables for the sale of power have been reported to be
negative for the years FY 06 onwards and all calculations dependent on the same figures
need to be recomputed.
-
BST for FY 01 has been fixed by the Commission at Rs. 1.38 per unit
and not at the levels reported in the FRP (Rs. 1.51 per unit for FY 01) and the consequent
annual percentage increases in BST needs to be recalculated alongwith the rest of the FRP.
-
The income tax provisions as applicable to GRIDCO need to be checked
to ensure the accurate provision of the same. Income tax needs to be applied when the
retained earnings of the company gets out of the red, which as per the FRP is FY 07.
|
62.
|
We may observe
that the FRP should have been more aggressive to reallocate the risks and
responsibilities. As GRIDCO alone was not responsible for the financial morass, it was
desirable that sacrifices were made by the Govt., the PFC, REC, NTPC, the generation and
distribution companies in induction of capital, waiver of dues and complete waiver of DPS
rather than postpone the dues so that they are taken care of by efficiency improvements.
|
Conclusion |
|
-
The Commission is of the view that GRIDCO may be accorded in
principle approval of the FRP, though it believes that certain conditions would have to be
fulfilled before the FRP runs its full course.
The retail tariff levels as proposed in the FRP is
based on the BST calculations. The projections have not taken into account, the debt
servicing due to the Tax free Bonds to be issued by GRIDCO. On the other hand they have
proposed additional borrowing to the tune of Rs 929 crores in year 2001 and further Rs 631
crores in year 2002. This will definitely impact the BST as well as the Retail Tariff thus
upsetting some of the crucial FRP assumptions.
-
We are not in a position to give clearance and commitment for future
tariffs, as these will be dealt separately on a year-to-year basis in accordance with the
OER act. One of the fundamental assumptions of the FRP is that the Bulk Supply tariff
hikes which are necessary for the sustenance of GRIDCO, in the post FRP arena, will not
affect the retail tariffs and hence not be a burden on the consumers. However the
Commission does not consider it appropriate to comment on the tariff related issues of the
FRP, without the full materialization of the stipulations of the same. It has to keep its
option to scrutinize the tariff applications independently and in light of the
circumstances at the time of application for tariff changes.
The load growth assumptions have been suitably
amended by GRIDCO, to make them more realistic, but the investment scheduling requires to
be further tightened in a crisis situation, as is currently prevalent in the sector. There
must be commitment from the Distcos on the performance assumptions like load growth,
transmission and distribution losses, etc. and they must be involved in the process.
-
The success of the FRP depends very clearly on the shared sacrifices
to be made by various other stakeholders in the power sector, as also by the state and
central governments. Without adequate and timely commitments from these, the FRP might not
see the light of the day. Hence it is imperative that the GRIDCO, obtain the necessary
guarantees and get financial benefits, flowing before pursuing the further implementation
of the FRP. The Commission shall need to be fully satisfied with the compliance with the
corresponding assumptions of assistance from these stakeholders before allowing the FRP to
run its course.
-
It is the view of the Commission, that power sector reform is a
gradual process, where the successful completion of each constituent step is the primary
precondition for undertaking the next. In fact, the degree of success achieved in each
step would also dictate the size of the next. Hence it reserves the right to revisit
benchmarks set in each order, inasmuch as this helps in creating a better environment for
the overall fulfillment of the objectives of reform. This order does not aim to legalize
the requirements set forth in the FRP and the amended FRP, and should be seen as a
facilitating device in the overall sectoral improvement and rehabilitation.
-
It is relevant to note that a bold step for radical reform
of power sector was taken by the Govt. of Orissa in a totally untrodden path of
unbundling, privatisation, independent regulation and cost-reflective tariff. The whole of
this country is benefitted from the lessons and experiences of this dynamic experiment. As
Orissa hit the roadblock of cash crunch by adopting the so called World Bank model of
reform, other states on the threshold of reform have reoriented the model and the pace of
their power sector reform and Govt. of India has also recently devised a scheme of one
time settlement of SEB dues. Hence in the fitness of GRIDCO the main player who has borne
the brunt is not left high and dry; and that the benefit of one time settlement of dues
recently decided by the Govt. of India should first be granted to Gridco. Even otherwise
we strongly recommended that the Govt. of Orissa, Govt. of India, World Bank, the DFID,
PFC, REC and the generators offer their financial assistance through one-time settlement,
waiver of dues and fresh loans to revive GRIDCO from a financial morass, which is not
entirely of its own making. We also direct the distribution licensees to improve their
performance and revenue collection clear up the dues of GRIDCO in time so that the risks
and gains of reform of the sector are equitably shared by all stakeholders. We request
that Government of Orissa ensures timely payment of electricity dues to all the
Distribution Companies.
-
With the observations given above the Commission grants in
principle approval of the financial restructuring plan indicated in paras 12 & 13 of
this order and plan for rescheduling of loans as contained in their application dated
19.09.2000 vide case No.30/2000 dt.30.09.2000 and 29/2000 dt.19.09.2000 respectively.
GRIDCO with the support of the Govt. of Orissa must plead with the Govt. of India and the
funding agencies for one-time settlement, waiver of dues and fresh loans and after taking
the results into account, implement the financial restructuring plan to revive GRIDCO so
as to put it on recovery path towards viability.
|
|
Sd/- (H.S. SAHU)
MEMBER
|
Sd/-(D.K.
ROY)
CHAIRMAN |