Annexure – VI
PRESENTATION
ON
MINIMUM STANDARDS OF PERFORMANCE
BY THE DISTRIBUTION LICENSEE
Presentation by Sri K.L. Panda, Jt. Director (Engg.) & Director (Engg.) I/c
The Electricity Act 2003 and the Consumer
One of the major objects of the Electricity Act, 2003 is to safeguard the
interests of consumers amongst other objects of developing the electricity
industry in a holistic fashion.
Section 57 of the Electricity Act, 2003 empowers the SERCs (the
Commission) to specify Standards of Performance of a Licensee.
Failure to meet Standards makes licensee liable to pay compensation to
affected consumer to be determined by the Commission.
This is without prejudice to any penalty which may be imposed or
prosecution initiated.
Standards of Performance
Under Section 58 the Commission can specify different standards for
different class of licensees.
Accordingly the Commission has framed the OERC (Licensee’s Standards of
Performance) Regulations, 2004 comprising:
1. Schedule-I: The Guaranteed Standards of Performance –
being the minimum standards of service to be achieved.
2. Schedule-II: The Overall Standards of Performance – which licensee seek to
achieve in discharge of obligations.
3. Schedule-III - is the compensation payable to consumer for failure to meet
Guaranteed Standards specified in Schedule-I.
Compensation must be paid within 90 days of failure of meet Guaranteed
Standards.
Manner of payment is automatic in certain defaults, i.e. licensee pays on
his own; in other cases of default, compensation is to be claimed from licensee.
Erring employee is liable to pay – Licensee may recover payments from
employee concerned.
The payment of compensation has been made effective since 15.10.2005.
Levels of Compensation and Guaranteed Standards
|
Sl. No. |
Types of service |
Time limit to do the job |
Compensation to be paid in case of failure (In Rupees) |
Whether to be paid automatically or to be claimed |
|
1 |
Restore power supply in normal fuse off calls |
6 hrs. (Urban) |
100 in each case of default |
Automatic |
|
2. |
Restore power supply in normal fuse off calls |
24 hrs. (Rural) |
100 in each case of default |
Automatic |
|
3 |
Restore power supply in line break down |
12 hrs. (Urban) |
100 to each affected consumer |
To be claimed |
|
4. |
Restore power supply in line break down |
24 hrs. (Rural) |
100 to each affected consumer |
To be claimed |
|
5. |
Restore power supply in major break down |
24 hrs. (Urban) |
100 to each affected consumer |
To be claimed |
|
6. |
Restore power supply in line break down |
48 hrs. (Rural) |
100 to each affected consumer |
To be claimed |
|
7. |
Restore power supply in Distribution Transformer failure |
24 hrs. (Urban) |
200 to each affected consumer |
To be claimed |
|
8. |
Restore power supply in Distribution Transformer failure |
48 hrs. (Rural) |
200 to each affected consumer |
To be claimed |
|
9. |
Restore power supply within time after scheduled outage |
6.00 P.M. in Summer |
200 to each affected consumer |
To be claimed |
|
10. |
Restore power supply within time after scheduled outage |
5.00 P.M. in Winter |
200 to each affected consumer |
To be claimed |
|
11. |
Improve voltage variation if no expansion/enhancement of network required |
15 days |
200 in each case of default |
Automatic |
|
12. |
Improve voltage variation if expansion/enhancement is required upto 11 KV |
120 days |
500 in each case of default |
Automatic |
|
13. |
Improve voltage variation if expansion/enhancement is required upto 33 KV |
180 days |
500 in each case of default |
Automatic |
|
14. |
Inspect and check the correctness of meter |
7 days |
100 in each case of default |
To be claimed |
|
15. |
Replace the meter if it is stuck up, running slow, fast or creeping, if it belongs to the Licensee. |
30 days of receiving the complaint |
100 in each case of default |
Automatic |
|
16. |
Replace the burnt meter if it is not due to the consumer. |
30 days after removal |
200 in each case of default |
Automatic |
|
17. |
Release of new connection, if no extension or new sub-station is required. |
30 days |
100 for each day of default |
Automatic |
|
18. |
If extension of distribution mains is required, power supply to be released in case of LT including Agriculture. |
30 days of receiving the application |
100 for each day of default |
To be claimed |
|
19. |
If extension of distribution mains is required, power supply to be released in case of 11 KV. |
60 days of receiving the application |
500 for each day of default |
To be claimed |
|
20. |
If extension of distribution mains is required, power supply to be released in case of 33 KV. |
90 days of receiving the application |
500 for each day of default |
Automatic |
|
21. |
If erection of substation is required, power supply to be released. |
Time limit as allowed by the Commission |
1000 for each day of default |
Automatic |
|
22. |
Title Transfer of ownership |
15 days of receiving application with necessary fees |
100 for each day of default |
Automatic |
|
23. |
Change of category |
30 days of receiving the application with necessary fees |
100 for each day of default |
Automatic |
|
24. |
Conversion from LT single phase to LT 3 phase and vice versa. |
30 days of receiving the application with necessary fees |
100 for each day of default |
Automatic |
|
25. |
Conversion from LT to 11 KV and vice versa. |
60 days of receiving the application with necessary fees |
200 for each day of default |
Automatic |
|
26. |
Conversion from LT to 33 KV and vice versa. |
90 days of receiving the application with necessary fees |
200 for each day of default |
Automatic |
|
27. |
Resolve billing complaint |
30 days of receiving the complaint |
50 for each day of default |
Automatic |
|
28. |
Reconnection of supply following disconnection due to non-payment of bills |
4 working hours of production of proof of payment |
100 for each day of default |
Automatic |
Information on Standards of Performance and Obligation to Report
The licensees are required to furnish reports on achievement of Guaranteed
Standards of Performance and Overall Standards of Performance at specified
frequencies.
Information on compensation paid, claims made and action taken by licensee
on delays or non-payment of compensation is to be reported.
The licensees are also required to furnish the consolidated report on
their achievement of the above standards annually. The Commission has been
receiving the above reports from the licensees periodically.
Authenticity of the achievement clamed by the licensees has been regularly
verified ‘through’ Commission’s own team, representatives of consumer groups and
consultants.
Feedbacks from such verification have revealed several instances of
deficient services.
Licensees have been cautioned leading to better and transparent maintenance of
registers/records.
Licensees have been sensitized to observance of statutory provisions and
render service promptly and reliably.
One Licensee was levied a penalty of Rs.1 lakh for contravention of the
statutory provisions.
The Commission is also regularly hearing matters about contravention of
licence condition and statutory provisions and has been cautioning the erring
licensees.
Proactive Role of the Commission to Meet the Standards by the Licensees
The
(a) System Average Interruption Frequency Index
(b) System Average Interruption Duration Index
(c) Momentary Average Interruption Frequency Index
for Bhubaneswar region had deteriorated.
The Distribution Operating Standards has generally deteriorated.
Similar situation was noticed at other important cities of the state.
The Commission made an independent study of deficiencies in these areas
and evolved rectificatory measures.
The Way Ahead
The Commission will ensure continued improvement in all reliability
indices with annual targets.
The Commission will also improve awareness among the consumers about their
rights and duties under the Act.
The Licensees Standards of delivery of services will be the focus of
continued improvements for quality and reliability.
The Commission seeks the active support of Govt. for better services of the
licensees with APDRP assistance, clearing of arrear of energy bills in Govt.
departments etc. and vigorous prosecutions to curb theft of electricity.