CASE NO. 2 of 1996
DATED BHUBANESWAR THE 20th JANUARY, 1997
Shri Somnath Som, Chairman
Shri A.R.Mohanty, Member
Shri D.K.Roy, Member
In the matter of application by M/s. Rexon Strips Limited, Rourkela.
M/s. Rexon Strips Limited - Petitioner
For the petitioner- Shri R.S.Kejriwal, Managing Director
Present- Shri S.P.Rath, Executive Engineer (Commercial)
representing Grid Corporation of Orissa Limited
The opinion of the Commission delivered by Shri S.Som, Chairman
S.SOM:- This is a petition under Section 44 of the Electricity
Supply Act, 1948 (hereinafter referred to as the Supply Act) read with sub-section (3) of Section 21 of Orissa
Electricity Reform Act, 1995 (for short the Reform Act) filed by M/s. Rexon Strips
Limited (Sponge Iron Division). The facts of this case fall within a small compass and can
be briefly stated.
2. The petitioner is a Joint Sector company set up
with financial assistance from Industrial Promotion and Investment Corporation of Orissa
Limited (IPICOL) and Orissa State Financial Corporation (OSFC) running a sponge iron plant
At : Kumakela, Via Lathikatha, Rourkela. For their unit they have taken power connection
with contracted demand of 200 KVA from OSEB under an agreement with the later executed on
04.07.94. The unit started production on 03.01.96. According to the petitioner, there were
frequent interruption in power supply under the agreement by the Board and later on by
Gridco. The unit has applied for installing a D.G. set of 280 KVA. Subsequently, the
rating of the proposed generating set was stated to be 380 KVA and finally it has been
indicated that it is of 365 KVA. As the contracted demand was 200 KVA and as it was
reported by the petitioner that he had already purchased a D.G. set and installed it,
notice was issued by the Commission to the petitioner for personal hearing. In response to
the notice, the petitioner appeared on 09.01.97 through its Managing Director and
indicated the following.
3. The unit is taking supply of electricity from 33 KV
line of the Board passing near the unit. But, there has been frequent interruption in
supply of power right from the beginning. It was submitted that even during installation
phase, because of frequent interruptions, the contractors who were fabricating machinery
at the site had to instal generating sets for ensuring dependable supply of power. As
already mentioned, the unit was commissioned on 03.01.96. From the beginning the
interruption was on an average nine times daily. It was also indicated that the plant of
the petitioner runs continuously for 90 days at a stretch with a stoppage of five days for
maintenance and for an interruption of even two minutes, the entire production cycle is
disturbed and 'B' grade material is produced resulting in substantial financial loss to
the petitioner. The petitioner purchased a D.G. set on 13.03.95 and installed it on
29.06.95. Prior to installation they applied on 09.05.95 to the Executive Engineer, OSEB
at Rourkela in proper form asking for permission to set up the generating set for stand by
power supply. Reminders were also sent on 12.07.95 and 13.09.95. In response, the S.E
(Commerce), Bhubaneswar in his letter dt. 14.11.95 asked the petitioner to supply certain
information for consideration of his prayer seeking permission to instal the generating
set. The required information was supplied by the petitioner in his letter dt. 09.02.96.
The petitioner had also written to the Chairman of the Electricity Board on dt. 14.02.96
asking for remedial action in respect of frequent interruption of power supply. With the
establishment of the Orissa Electricity Regulatory Commission the petitioner came up with
his application on 22.08.96 enclosing previous correspondence with the Board asking
permission to set up the generating set.
4. At this point, it will be necessary to refer to the
legal provisions in this regard. Under sub-section (1) of Section 44 of the Supply Act, it
is provided that notwithstanding anything contained in any other law for the time being in
force or in any license, but subject to the provisions of this Act, it shall not be lawful
for a licensee, or, any other person, not being the Central Government or any Corporation
created by a Central Act to establish or acquire a new generating station except with the
previous consent in writing of the Board. In other words before a generating set is
installed prior permission in writing of the Board has to be obtained. Under sub-section (3) of Section 21 of Reform
Act, it is provided that any person to whom the provisions of Section 44 of the Supply
Act applies shall be required to obtain permission from the Commission instead of the
Board as provided under that Section. That is how the petitioner is before us.
5. The first point to note, is that, the petitioner is
a Joint Sector company set up with financial assistance from IPICOL and OSFC and it
contracted for supply of power by Orissa State Electricity Board. Inspite of execution of
contract, there has been, according to the petitioner frequent interruption in power
supply resulting in considerable financial loss to the unit. At this point, it is relevant
to note that inspite of notice, the GRIDCO the successor-in-interest of OSEB has not filed
any report in respect of the petition. We have, therefore, to accept the petitioner's
contention that there has been frequent interruption in power supply resulting in
substantial loss of the production by the petitioner. We would also like to record that
even ignoring the lapse of Gridco in not sending the report, the petitioner during the
hearing before the Commission has been able to fully establish the fact of frequent
interruption in power supply.
6. The second aspect of the matter is that the
petitioner's contracted demand is 200 KVA as against which he has purchased and installed
a D.G. set of 365 KVA which is of much higher rating. The petitioner has submitted that he
has purchased a very well known brand of D.G. set named "Cater Pillar" (TIL
Limited) and has submitted the copy of an advice from the company suggesting purchase of a
D.G. set of 365 KVA as against the contracted load of 200 KVA. This is because in the
manufacturing process, the petitioner requires direct current for certain D.C. motors and
for converting A..C. to D.C. as A. C. is the normal supply by the Board, he had
established a Thyristor which requires additional power. Moreover, in case of
interruption, motors and machines have to come to full load at a time because of ongoing
process of production and this also requires a higher rating of the generating set as
against his contracted demand. We have considered this advice very carefully. While we
accept both the contentions that because of the Thyristor, the petition requires more
power and because in case of interruption the entire load is drawn instantaneously from
the generating set, the rating of the generating set has to be higher than the contracted
load, we are of the view that even taking these two factors in consideration, rating of
his generating sets could have be somewhat lower than 365 KVA. It is thus clear that the
petitioner has installed a generating set of higher rating than what needed by his
contracted load and distinctive requirements of the load profile.
7. The third and the most important aspect of the
matter that inspite of sub-section (1) of Section 44 of the Supply Act the petitioner has
gone ahead and installed the generating set. This has two implications. Firstly,
installation of D.G. set has been done without the consent of the Board and secondly,
petitioner has not given any intimation to the Electrical Inspector for inspection before
operating the D.G.set Therefore, Electrical Inspector has not checked the safety aspect of
the installation. Serious notice has to be taken of the lapses. The other aspect of this
matter is that the petitioner obviously has not been sending reports to the Electrical
Inspector about the quantum of the electricity generated and consumed and is not paying
any electricity duty on the units consumed from self-generation. It is understood that
according the relevant Industrial Policy Resolution, exemption may be available to him
from payment of electricity duty for a period ten years from the date of the commissioning
of the D.G. set, but even then the liability of submission of statutory return on
self-generation to the Electrical Inspector remains.
8. We have considered all the aspects very carefully.
We have also noted the fact that the petitioner did apply to the Board for permission
before actual installation of the generating set and had been repeatedly writing to the
Board on that subject. It is also noted that the petitioner had also been repeatedly
writing about the frequent interruption in power supply to his unit set up with financial
assistance from IPICOL & OSFC. No material has been placed before us showing what
action, if any, has been taken by the Board and the Gridco on the various petitions filed
by the petitioner. In consideration of the above permission is hereby granted to the
petitioner under Section 44 of the Supply Act read with sub-section
(3) of Section 21 of the Reform Act for installing the
generating set of 365 KVA. The permission shall be prospective in nature that shall be
effective from the date of issue by the Commission. It is also ordered that a copy of this
order should be sent to the Electrical Inspector who shall inspect the safety aspect of
the installation and send a copy of the Inspection Report to the Commission. The question
of levy and calculation of Electricity duty will no doubt be considered by the Electrical
Inspector in the light of the statutory provisions and the provisions in the concerned
Industrial Policy Resolution. We have noted earlier that the petitioner has established a
generating set with a higher rating costing more money, thus enabling him to draw higher
subsidy from the Industry Department than what he would have been entitled to in case he
had established a generating set of lower rating. This, however, is a matter to be
considered by the authority granting the subsidy. We order that the petitioner while
applying for subsidy from the concerned authority should submit a copy of this order to
that authority so that appropriate decision could be taken by the subsidy granting
authority in the matter.
9. Subject to the above observations the petition is
allowed.
10. Pronounced this day the Twentieth of January, 1997
in-the open court.
Typed to my dictation and corrected by me.
S/d
S.SOM
S/d
S.Som
CHAIRMAN
I agree.
S/d
A.R.Mohanty
MEMBER
I agree.
S/d
D.K.Roy
MEMBER
ORISSA ELECTRICITY REGULATORY COMMISSION BHUBANESWAR
(CASE NO. 2 OF 1996)
09.01.97 Petitioner represented by the Managing Director of the Company. Gridco
is represented by the Executive Engineer (Commercial). Heard the petitioner and
representative of Gridco. The petitioner is directed to submit information on date of
initial supply of power to the unit, date of purchase and installation of DG set, initial
correspondence with OSEB/GRIDCO regarding agreement and supply of power, the provision of
Industrial Policy Resolution, 1992 under which the petitioner wants to avail subsidy from
the Industries Department, cost and specification of the DG sets, characteristic of the DG
set for ensuring that full load for the unit could be taken from the DG set
instantaneously and cost of generation per unit from Diesel Generator. Petitioner submits
that information on the above points would be submitted by 15th January, 1997. The matter-
is posted to 20th January, 1997 for orders.
S/d
S.Som
S/d
A.R.Mohanty
S/d
D.K.Roy
20.01.97 Petitioner absent on call. Representative of Gridco is also absent. Order
delivered in separate sheets. The petition is allowed in terms of the order. Copies of the
order be sent to the Petitioner, Gridco and Electrical Inspector, Rourkela.
S/d
S.Som
S/d
A.R.Mohanty
S/d
D.K.Roy
Back to "Orders" |