CASE NO. 1 of 1996
DATED BHUBANESWAR THE 7th NOVEMBER, 1996
Sri Somnath Som, Chairman
Sri A. R. Mohanty, Member
Sri D. K. Roy, Member
In the matter of application by M/s. United Hatchery Pvt. Ltd.,
Jagamara, Khandagiri, Bhubaneswar.
M/s. United Hatchery Pvt. Ltd. - Petitioner
Vrs
GRID Corporation of Orissa Ltd. - Opposite party
For the petitioner - Sri Khirod Mohan Pattnaik
For the opposite party - Sri R.C. Das, Superintending Engineer
Sri B.K. Khatua, Executive Engineer.
The opinion of the Commission delivered by Sri S. Som, Chairman.
S.SOM :- This is a petition filed on 19.08.1996 by M/s. United
Hatchery (Pvt.) Ltd., Jagamara, Khandagiri, Bhubaneswar. Opposite party is Grid
Corporation of Orissa Limited. The petition was initially taken up on 26.8.96 and in
presence of both the parties an interim order was passed. Opposite party filed his
objection with copy to the petitioner and the matter was heard in detail on 27.9.96.
Before going into the various issues which have arisen in this case, the facts of this
case which fall within a small compass can be briefly stated.
2. Petitioner is a farm engaged in production of
broiler chicks using electrically operated machinery. The unit is located at Vill :
Bhatakudi, Dist : Khurda. It has been submitted during the hearing by the petitioner that
he gets eggs hatched in his unit and sells around 12,000 one-day-old chicks per week. For
supply of electricity to his unit, the petitioner entered into an agreement dated 24.12.92
with the erstwhile Orissa State Electricity Board, the predecessor-in-interest of the
opposite party GRIDCO.
3. In the preamble to the agreement, it has been
mentioned that the consumer, meaning the present petitioner, has requested Orissa State
Electricity Board for supply of electrical energy for the purpose of hatchery unit. The
agreement is initially valid for five years and is terminable through six months notice on
either side.
4. Clause 3 of the agreement provides that the
petitioner shall take from the opposite party supply of electrical energy upto but not
exceeding a maximum demand of 31 Horse Power (HP) to run different types of motor and 29
KW of light load. Power required to run 31 HP motor load works to 23.13 KW, since 1 HP is
equal to 0.746 KW. This along with 29 KW of light load comes to 52.13 KW of power rounding
off to 52.5 KW. The contracted load of the petitioner is thus 52.5 KW.
5. The agreement indicates the tariff for such supply
of energy: provision of payment of minimum charges and it is also agreed to between the
parties that in case of unmetered or defective meter supply the energy consumption shall
be assessed at load factor of 20% on the connected load rounding off to next 1/2 KW. There
is also provision for collection of fuel surcharge and electricity duty over and above the
tariff. fender the agreement the petitioner further agrees to abide by all the terms and
conditions of Orissa State Electricity Board (General conditions of Supply) Regulations,
1981 as modified from time to time. The tariff and conditions of supply between the
parties are also subject to future revision by the Board. Clause 9 of the agreement
provides that in case of any dispute -or difference between the consumer and the Board as
to supply of electrical energy or interpretation of the agreement, such dispute shall be
referred to the Arbitration Tribunal constituted by Govt. of Orissa and such arbitration
shall be covered by the Indian Arbitration Act, 1940. This Clause contains the important
proviso that any dispute or difference with regard to the rate of tariff, surcharge or any
other duties payable under the agreement and the liability of the consumer to pay the same
shall not be deemed to be a dispute within the meaning of this Clause. The agreement also
gives the details of the list of motors, their number and different Horse Powers. The
total load works out to 31 HP and the details of light load work out to 29 KW as mentioned
earlier.
6. After execution of the agreement, the petitioner
installed some machinery and submitted a test report on 01.04.93. The installation was
done by a contractor authorised by the Electrical Licensing Board to install electrical
machinery. This test report was signed by the petitioner. He had indicated 119 points with
a total wattage of 24070 or 24.5 KW. On submission of the test report, energy was supplied
the same day.
7. The Vigilance Wing of Grid Corporation of Orissa
Ltd. carried out a surprise inspection of the petitioner's premises on 17.11.95. The
petitioner being away for business purposes, an employee of the petitioner who was the
hatchery-in-charge remained present during this surprise inspection. In course of this
inspection, it was reportedly found that the petitioner had a connected load of 27.25 KW
for running motors as against a contracted load of 23.13 KW as mentioned earlier and a
connected light load of 36.96 KW as against a contracted load of 29 KW, thus, totaling a
connected load of 64.21 KW. It is important to note that at the time of this inspection,
the meter in the premises of the petitioner was running as mentioned in the surprise
inspection report. On receipt of the report of surprise inspection, the Executive Engineer
in his letter No.1828 aft. 25.3.96 directed the petitioner to intimate
the date of enhancement of the connected load without execution of fresh
agreement/security deposit. It was intimated that if no reply is received within fifteen
days energy bill would be claimed at penal rate i.e. double the tariff rate with
retrospective effect. As no reply was sent by the petitioner, on the basis of the total
load of 64.21 KW as found during surprise inspection against the contracted demand of 52.5
KW, the Board charged him with arrears of Rs.49,110/-. this amount along with the bill for
current energy charges for the month of June, 1996 amounting to Rs.21,080.60 paise and
electricity duty of Rs.1,097.10 paise came to Rs.71,287.70 paise. The petitioner was
directed to pay the bill within 15 days from the date of the issue which was 15.07.96. The
petitioner took up the matter with the Superintending Engineer, Bhubaneswar Circle in his
letter dt 23.7.96 in which he claimed that his actual load did not justify paying of
arrears at double rates. He also stated that there was no justification for using a load
of 100 watt and 1000 watt for unused plug points which have been provided to connect
mobile or emergency load. He also filed a petition before the Chairman, Grid Corporation
of Orissa Limited on dt.09.08.96 contesting the demand for arrears and also claiming that
he should be charged at medium industry rate and not at commercial rate. It is relevant to
note that prior to all this, on 12th Nov., 1993, the petitioner had applied to the
Superintending Engineer, Bhubaneswar Circle praying that the rate of tariff charged to him
should be changed from commercial rate to the rates applicable to medium industry. Against
the above background the petitioner has come up before the Commission with the present
petition on dt.19.08.96.
8. In his petition before us, as also in course of his
oral submissions the petitioner made the following points :
-
According to the Orissa State Electricity Board (General conditions of Supply)
Regulation, 1981, he should be charged at the rate applicable to medium industry and not
at commercial rate as at present.
-
The enumeration of the connected load as indicated in the inspection report of the
Vigilance Wing is incorrect and suffers from various deficiencies.
-
As a consequence, the penalty of Rs.49,110/- charged to him is illegal and is not
payable by him.
9. In their reply GRIDCO has pointed out that the rate
applicable to commercial category has been rightly charged to the petitioner. They have
also submitted that the calculation of connected load in the inspection report of the
Vigilance Wing has been correctly done and the bill has been correctly worked out.
10. Before considering the submissions of both the
parties, the question of maintainability has to be decided first. Even though this point
has not been raised before us, it is well settled that consent of parties cannot confer
jurisdiction on a court. The question of maintainability is specially important in view of
sub-section (2) of Section 33 of the Reform Act of 1995 which lays down that nothing in this Act shall
affect the rights and privileges of consumers under any other law including the Consumer
Protection Act, 1986. Under the Consumer Protection Act, 1986, a hierarchy of Courts have
been set up at the District, State and National levels. These courts are presided over by
Senior Judicial Officers of vast experience. The Consumer Courts at the state and national
levels are headed by Hon'ble Justices of the High Court and the Supreme Court. In dealing
with complaints of consumers against the licensee, the Commission will therefore, have to
be careful in not encroaching upon areas which under the law are covered by the Consumer
Protection Act, 1986. It will, therefore, be necessary to look into the provisions of the
Act of 1986 for deciding the question of maintainability of this petition before us.
11. Clause (d) of Section 2 of the Act of 1986 inter
alia defines consumer as a person who buys goods for consideration but does not include a
person who obtains such goods for resale or for any commercial purpose. It is well settled
that electricity is goods but the petitioner in this case does not come within this part
of the definition of consumer, because he is buying electricity from Gridco for a
commercial purpose. The second part of the definition of consumer denotes any person who
hires any services for a consideration. Clause (o) of the same Section defines service.
This inclusive definition specifically mentions supply of electrical or other energy. The
exceptions provided under this Clause relating to rendering any service free of charge or
under a contract of personal service are not applicable to the petitioner. It is,
therefore, clear that supply of electricity is a service and the petitioner is a consumer
within the definition of this Act. But, the complaint of the petitioner is not regarding
any deficiency in service provided by the opposite party. The petitioner complains that he
has been billed for an amount which is not legally recoverable from him. His other
grievance is about the tariff applied to him. Thus, the allegations against the opposite
party do not reveal any deficiency in service provided by the opposite party. Therefore,
the petition dtd. 19.08.96 is not a complaint as defined under Clause (c) of Section 2 of
the Act and therefore, the present petition could not have been filed before the concerned
Consumer Court. In course or his oral submissions the petitioner has also mentioned that
he has been advised by his lawyer that his complaint is not maintainable before the
Consumer Court.
12. The second aspect of question of maintainability
is that under Clause 9 of the agreement between the petitioner and the opposite party
referred to earlier, any dispute between the parties is required to referred to the
Arbitration Tribunal. But as earlier mentioned, under the proviso to this Clause any
dispute or difference with regard to the rate of tariff surcharge or any other dues
payable under the agreement shall not be deemed to be a dispute within the meaning of this
Clause. Therefore, with regard to the points raised in this petition the Arbitration
Clause of the agreement is not attracted.
13. On the other hand, under sub-section (1) of Section 18 of the Orissa
Electricity Reform Act, 1995, the Commission may enquire into the conduct or
functioning of any license in carrying out the obligations under the Act upon receiving a
complaint from any consumer. The petitioner is a consumer and therefore his complaint
against the opposite party as alleged in hits petition is required to be adjudicated by
the Commission. On the above consideration I hold that the petition is maintainable before
us.
14. Of the three contentions of the petitioner, the
second contention is taken up first. It has been urged by the petitioner that the
enumeration of the connected load as indicated in the inspection report of the Vigilance
Wing is incorrect as it suffers from various deficiencies. In support of this contention,
in course of his oral submissions, the petitioner made the following points. It was stated
that under circular No. 14769 dated 6th September 1989 of Chief Engineer (Commerce) of the
erstwhile Orissa State Electricity Board norms were laid down for fixation of contract
demand in respect of loads governed by single part tariff. In respect of commercial load
the norm fixed provides that for each 5 Amp convenient plug point, load has to be taken as
100 watt and for each 15 Amp plug point as 1000 watt. It has been submitted by the
petitioner that taking the load at 100 watt and 1000 watt each at uniform rate for all the
5 Amp and 15 Amp power plug points is illogical because the consumer is not expected to
utilise all the plug points at any given point of time. According to the petitioner, the
diversity factor should have been built into fixing of such norm as has been done in
respect of domestic consumers under the same circular. The petitioner has also stated that
issuing of this circular by Chief Engineer (Commerce) is without any legal basis and the
connected load cannot be legally fixed in this fashion. The term connected load has been
defined in sub-clause (ix) of Clause 3 of the Orissa State Electricity Board (General
Conditions of Supply) Regulation, 1981 (1981 Regulation). Shorn of technical details,
according to this definition, connected load means the total of the manufacturer's rating
of all the apparatus including portable apparatus on the consumer's premises which is
supplied with energy and apparatus in respect of which declaration has been made by the
consumer for taking supply. Thus, it is clear that connected load has to be normally
determined with reference to the rating of different apparatus on the premises of the
consumer. In this case connected load has not been determined on the basis of
manufacturers rating of the different apparatus with the consumer that is the petitioner;
but on the basis of the rating of the different electrical installations according to the
circular referred to earlier. The question is whether such calculation of the connected
load is legal specially in view of the contention of the petitioner that the circular aft.
6th Sept. 1989 has been issued without any authority and therefore, is not binding on him.
The above contention is not correct because under Clause 19 of the 1981 Regulation, it has
been provided that where for any reason it is not possible to determine the maximum
demand, power factor or any other electrical quantity contained in the supply in respect
of an installation the Board shall determine such quantities periodically by
rating/re-rating/physical measurement or any other method approved by the Board which
shall be binding on the consumer. This Clause gives the authority to the Board to lay down
principles and guidelines for fixation of connected load on the basis of rating of all
electrical installations and the circular of the Chief Engineer (Commerce) has been issued
in exercise of this power of the Board. Therefore, the circular cannot be said to be
without any authority.
15. As regards, the question of diversity factor, it
is seen that in case of domestic consumer, the circular provides that for 5 Amp wall plug
point, the first two plug points should be taken as having a load of 100 watt each and for
each additional 5 Amp plug points the connected load should be taken as 20 watt.
Similarly, for 15 Amp power plug points on the premises of domestic consumers it has been
laid down that the first two 15 Amp plug point would be taken to be having a load of 1000
watt each and for additional plug points load will be taken as 300 watt each. The
contention of the petitioner is that such diversity factor has not been applied while
laying down the norm for fixing the contract demand in respect of commercial consumers.
This contention is not correct because of the following reason. While fixing 100 watt for
each 5 Amp power plug point and 1000 watt for each 15 Amp power plug point in case of
commercial consumers, diversity factor has been taken into account. This is because
wattage is derived by multiplying the unit of the current with the voltage. Generally, the
supply is made at voltage ranging between 220 to 230 volt. Taking the lower end of 220
volt for calculating wattage for a 5 Amp plug point the wattage is generally speaking 5 X
220 = 1100 watt as against which for commercial consumer an uniform wattage of 100 watt
has been adopted. Similarly, for 15 Amp plug point at 220 volt the wattage would be 3300
watt as against which an uniform wattage of 1000 watt has been taken for each 15 Amp plug
point in the impugned circular. The contention of the petitioner on this point must
therefore, be rejected. This calculation takes into account, and to my mind quiet
liberally, the diversity factor while fixing the norm of wattage for commercial consumers.
It is a fact that for domestic consumers a further relaxation has been given in the above
circular by taking the wattage of the third and further 5 Amp plug points as 20 watt each
and similarly, for second and further plug points of 15 Amp as 300 watt each. But, the
petitioner cannot claim as of right, further, concession in respect of his rating because
as earlier mentioned under Clause 19, the rating made by the Board is binding on him.
Moreover, in the initial test report submitted by him on 1.4.93 he had himself taken each
15 Amp plug point as having a wattage of 1000 watt each. It is, therefore, not open for
him now to question the calculation of wattage in this manner.
16. The petitioner has further stated that a plug
point by its very nature is meant for occasional use because for continuous and permanent
use generally a switch is fixed. On this ground also he had challenged the above circular.
Even though it may be true that a plug point is meant for occasional use but it cannot be
said to be invariably so. The person can continuously run a T.V. or any other electrically
operated machine through a plug point. Moreover, once a certain number of plug points has
been fixed in a premise it is open for the owner/occupier of the premises to utilise all
the plug points simultaneously and draw power. Thus, every plug point denotes the
possibility of drawing power and also simultaneous use of all the plug points at the
choice of the owner/occupier. I, therefore, do not find anything unreasonable in
calculation of wattage in this way. As regards the other details of installation of
machinery as mentioned in the inspection report of the Vigilance Wing those have not been
challenged by the petitioner. The representative of the petitioner was present at the time
of inspection and had signed the inspection report. This contention of the petitioner is
therefore rejected.
|