55/2021Application under Section 94 (1) (g) read with Section 86 (1) (k) of the Electricity Act, 2003 and Reg. 70 of the OERC (Conduct of Business) Regulations 2004 and all other enabling provisions of the Act for issuance of suitable directions for (a) Settlement of outstanding due from CESU, WESCO, NESCO25-Jun-21OPTCL
OTHERSRESP.
SECRETARY, OERCRESP.

(B) Hearing Details

(Click on order document (.pdf) to view the complete/final order)

Hearing No.Date of HearingInterim/FinalAbstract of OrderOrder Document
103-Aug-21INTERIMCase No. 55/2021 Interim Order No-1 Date of hearing: 03.08.2021 Date of order: 03.08.2021 Due to Covid-19 pandemic situation the Commission had decided to hear the matter through Video Conferencing in the Virtual Court on 03.08.2021. Accordingly the parties were intimated. 2. Shri Srikanta Kumar Sahoo, GRIDCO, Shri Vidydhar Wagle TPCODL, Shri K. C. Nanda, DGM (F.), TPWODL, Shri Binod Nayak, Asst. GM (Comm.), TPSODL, Shri Pratap Mohanty, Sr. GM (Regulatory & Legal), TPNODL, are present. 3. The case is taken up for hearing on question of admission as well as on merit through video conferencing. During hearing the representatives of the TPWODL & TPSODL pray the Commission to direct the petitioner to serve the copy of their petition on them as they have not received the same till date. TPSODL, TPWODL and TPNODL have also prayed for adjournment of hearing today as they have to file their reply in the above matter. 4. Prayer for adjournment of hearing by the respondents is allowed. The petitioner is directed to serve the soft copy of its petition on the respondents through email today. The respondents who have not filed their reply are directed to file the same by 17.08.2021 serving a copy of the same on the petitioner. GRIDCO is directed to file its rejoinder to the reply of the respondents by 31.08.2021 serving copy on the other side. 5. Post the matter on 07.09.2021 at 11.00 AM for hearing on question of admission as well as on merit. No further notice shall be issued to the parties concerned in this regard. Sd/- Sd/- Sd/- Member (M) Member (P) Chairperson

207-Sep-21INTERIMCase No. 55/2021 Interim Order No-2 Date of hearing: 07.09.2021 Date of order: 07.09.2021 Due to Covid-19 pandemic situation the Commission had decided to hear the matter through Video Conferencing in the Virtual Court on 07.09.2021. Accordingly the parties were intimated. 2. Shri Srikanta Kumar Sahoo, GRIDCO, Shri Soumya Mishra, TPCODL, Shri K. C. Nanda, DGM (F.), TPWODL, Shri Binod Nayak, Asst. GM (Comm.), TPSODL, Ms. Ma;ancha Ghose, RA and Shri Pratap Mohanty, Sr. GM (Regulatory & Legal), TPNODL are present. Nobody is present on behalf of DoE, GoO. The reply filed by TPSODL, TPWODL and TPCODL are taken on record. 3. During hearing the representatives of the GRIDCO prays for 7 days time for filing of its consolidated rejoinder to the reply of the respondents. Some Respondents have also sought time to file their replies. 4. Prayer of the Respondents is allowed. They are directed to file their replies by 14.09.20021. GRIDCO is directed to file its consolidated rejoinder by 21.09.2021 serving copies on the respondents. 5. Post the matter on 28.09.2021 at 11.00 AM for hearing on question of admission as well as on merit. No further notice shall be issued to the parties concerned in this regard. Sd/- Sd/- Sd/- Member (M) Member (P) Chairperson

328-Sep-21INTERIMCase No. 55/2021 Interim Order No-3 Date of hearing: 28.09.2021 Date of order: 28.09.2021 Due to Covid-19 pandemic situation the Commission had decided to hear the matter through Video Conferencing in the Virtual Court on 28.09.2021. Accordingly the parties were intimated. 2. Shri Srikanta Kumar Sahoo, GRIDCO, Shri Puneet Munjal, Chief Regulatory & Govt., TPCODL, Shri K. C. Nanda, DGM (F.), TPWODL, Shri Binod Nayak, Asst. GM (Comm.), TPSODL, Ms. Malancha Ghose, RA and Shri Pratap Mohanty, Sr. GM (Regulatory & Legal), TPNODL are present. Nobody is present on behalf of DoE, GoO. The rejoinder of GRIDCO Ltd. to the reply of filed by TPWODL, TPNODL and TPCODL is taken on record. 3. During hearing the representative of the GRIDCO submits that GRIDCO has received the replies of the respondents except TPSODL and prays for 7 days time for filing of its consolidated rejoinder to the reply of TPSODL after it receives the same from TPSODL. 4. Prayer of the GRIDCO is allowed. TPSODL is directed to serve the copy of their reply on GRIDCO today. GRIDCO is directed to file its consolidated rejoinder by 05.10.2021 serving copy on TPSODL. 5. Post the matter on 26.10.2021 at 11.00 AM for hearing on question of admission as well as merit. No further notice shall be issued to the parties concerned in this regard. Sd/- Sd/- Sd/- Member (M) Member (P) Chairperson

426-Oct-21INTERIMCase No. 55/2021 Interim Order No-4 Date of hearing: 26.10.2021 Date of order: 26.10.2021 Due to Covid-19 pandemic situation the Commission had decided to hear the matter through Video Conferencing in the Virtual Court on 26.10.2021. Accordingly the parties were intimated. 2. Shri Srikanta Kumar Sahoo, GRIDCO, Shri V.Wagle, TPCODL, Shri K. C. Nanda, DGM (F.), TPWODL, Shri Binod Nayak, Asst. GM (Comm.), TPSODL, Ms. Malancha Ghose, RA and Shri Pratap Mohanty, Sr. GM (Regulatory & Legal), TPNODL are present. Nobody is present on behalf of DoE, GoO. The rejoinder of GRIDCO Ltd. to the reply of filed by TPCODL is taken on record. 3. During hearing the representative of the GRIDCO prays for 7 days time for filing of its consolidated rejoinder to the reply of the respondents. 4. Prayer of the GRIDCO is allowed. GRIDCO is directed to file its consolidated rejoinder by 02.11.2021 serving copy on the respondents. 5. Post the matter on 09.11.2021 at 11.00 AM for hearing on question of admission as well as merit. No further notice shall be issued to the parties concerned in this regard. Sd/- Sd/- Sd/- Member (M) Member (P) Chairperson

509-Nov-21INTERIMCase No. 55/2021 Interim Order No-5 Date of hearing: 09.11.2021 Date of order: 09.11.2021 Due to Covid-19 pandemic situation the Commission had decided to hear the matter through Video Conferencing in the Virtual Court on 09.11.2021. Accordingly the parties were intimated. 2. Shri Srikanta Kumar Sahoo, GRIDCO, Shri V. Wagle, TPCODL, Shri K. C. Nanda, DGM (F.), TPWODL, Shri Binod Nayak, Asst. GM (Comm.), TPSODL, Ms. Malancha Ghose, RA and Shri Pratap Mohanty, Sr. GM (Regulatory & Legal), TPNODL are present. Nobody is present on behalf of DoE, GoO. The rejoinder of GRIDCO Ltd. to the reply filed by TPSODL is taken on record. 3. During hearing the representative of the GRIDCO submits that they have filed their rejoinder to the reply of TPSODL on 01.11.2021 and they will file a consolidated rejoinder to the reply of the respondents, which needs 7 days time to go through all the replies of the respondents. Therefore, he prays for adjournment to another date. 4. Prayer of the GRIDCO is allowed. GRIDCO is directed to file its consolidated rejoinder by 16.11.2021 serving copy on the respondents. The respondents may file their reply to the consolidated rejoinder of GRIDCO by 23.11.2021 serving copy on GRIDCO. 5. Post the matter on 30.11.2021 at 11.00 AM for hearing on question of admission as well as merit. No further notice shall be issued to the parties concerned in this regard. Sd/- Sd/- Member (M) Chairperson

630-Nov-21INTERIMCase No. 55/2021 Interim Order No-6 Date of hearing: 30.11.2021 Date of order: 30.11.2021 Due to Covid-19 pandemic situation the Commission had decided to hear the matter through Video Conferencing in the Virtual Court on 30.11.2021. Accordingly the parties were intimated. 2. Shri Srikanta Kumar Sahoo and Ms. Susmita Mohanty, DGM, GRIDCO, Shri V. Wagle, TPCODL, Shri K. C. Nanda, DGM (F.), TPWODL, Shri Binod Nayak, Asst. GM (Comm.), TPSODL, Ms. Malancha Ghose, RA and Shri Pratap Mohanty, Sr. GM (Regulatory & Legal), TPNODL and Ms. Sonali Pattnaik, ALO, DoE, GoO are present. 3. Heard the parties at length. Parties are directed to file their written note of submission, if any, by 06.12.2021. 4. Hearing concluded. Post the matter on 14.12.2021 for Orders. Sd/- Sd/- Member (M) Chairperson

714-Dec-21INTERIMFor order.

821-Dec-21INTERIMFor order.

928-Dec-21INTERIMFor order.

1004-Jan-22FINALOrder passed.

ORDERS\2021\C-55-2021.PDF